8               ENVIRONMENTAL NON-CONFORMANCE (EXCEEDANCES)

Summary of Exceedances

 

8.1         Summary of exceedance is provided in Appendix L.

8.2         No Action/Limit Level exceedance was recorded for air quality, construction noise and underwater noise.

8.3         All water quality monitoring was conducted as scheduled in the reporting month. There is one Action Level exceedance for suspended solids were recorded.

 

8.4         According to the investigation, no pollution discharge from the marine works and sediment plume due to natural fluctuation of shallow water was observed. Therefore, all exceedances are considered not due to the Contract.

Summary of Environmental Complaint

8.5         One environmental related complaint was received in the reporting month. The Complaint Log is attached in Appendix P.

Summary of Notification of Summons and Successful Prosecution

8.6         There was no prosecution or notification of summons received since the Contract commencement.