9.1
Major site activities for the coming reporting month will include:
WA4
Fabrication of rebar cages
Loading and unloading
Setup of casting yard
WA7
Preparation for bored piling
Fabrication of rebar cages
Loading and Unloading
Portion
A (Land Section)
Site clearance and formation
Timber Scaffolding
Pre-drilling work
Set-up facilities for marine delivery of
concrete from land plants
Slewing of the tele-communication
& AA COM cables
Portion
C
Erection of hoarding & fencing
Pre-drilling work
Protection work to the fuel pipes
Backfilling works
Fabrication of reinforcement cage and piling
jacket, setting up for land
piling work
Western
Water
Pre-drilling Work
Loading and Unloading
Setting up of silt-curtain
Platform installation for pre-drilling works
Installation of temporary casings for the
piling platform
Installation of permanent casing
Bored piling works
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.