9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Loading and unloading

Ÿ   Setup of casting yard

WA7

Ÿ   Preparation for bored piling

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

Ÿ    

Portion A (Land Section)

Ÿ   Site clearance and  formation

Ÿ   Timber Scaffolding

Ÿ   Pre-drilling work

Ÿ   Set-up facilities for marine delivery of concrete from land plants

Ÿ   Slewing of the tele©\communication & AA COM cables

Portion C

Ÿ   Satellite site office set up

Ÿ   Pre-drilling work

Ÿ   Protection work to the fuel pipes

Ÿ   Fabrication of reinforcement cage and piling jacket, setting up for land piling work

Western Water

Ÿ   Pre-drilling Work

Ÿ   Loading and Unloading

Ÿ   Setting up of silt-curtain

Ÿ   Platform installation for pre©\drilling works

Ÿ   Installation of temporary casings for the piling platform

Ÿ   Installation of permanent casing

Ÿ   Bored piling works

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

9.3         A tentative construction programme is provided in Appendix A.