1.
This is the 5th monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in June
2013.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
3rd, 7th,
13th, 19th, 25th and 28th June 2013 |
24-hr TSP Monitoring |
3rd, 7th,
13th, 19th, 25th and 28th June
2013 |
Noise Monitoring |
4th, 10th,
20th and 26th June 2013 |
Water Quality Monitoring |
3rd, 5th,
7th, 10th, 13th, 15th, 17th,
19th, 21st, 24th, 26th and 28th
June 2013 |
6th and 17th
June 2013 |
|
Construction-phase underwater Noise Monitoring |
N/A |
Dolphin Behaviour
Monitoring |
N/A |
Land-based Dolphin Behaviour
and Movement Monitoring |
N/A |
Environmental Site Inspection |
4th, 11th,
18th and 28th June 2013 |
Archaeological Site Inspection |
18th June 2013 |
Remark: N/A:
No monitoring was conducted in the reporting month as no underwater sockets
into rock can be carried out for marine bored piles in West Lantau
in May and June in accordance with EP Condition 3.1.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting month is tabulated in Table
II.
Table II Summary Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
0 |
0 |
0 |
0 |
1-hour TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was
recorded.
Water Quality
7.
All water quality monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance was recorded.
Complaint Log
8.
No environmental complaint was received in the reporting month.
Notification of Summons and Successful Prosecutions
9.
No notification of summons and successful prosecution was received in
the reporting month.
10.
This report has been developed in compliance with the reporting
requirements for the subsequent monthly EM&A Report as required by the
EM&A Manual for Hong Kong Link Road (EM&A Manual).
11.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Loading and
unloading
Setup of
casting yard
WA7
Fabrication
of rebar cages
Loading and
Unloading
Portion A (Land Section)
Site
clearance and erection of water
filled barriers as boundary
Timber
Scaffolding
Pre-drilling
work
Set-up
facilities for marine delivery of concrete from land plants
Portion C
Land piling
Slewing the tele-communication
cable and AA’s COM cable
Tree felling/transplant
Drainage and water main diversion
Western
Water
Pre-drilling
Work
Setting
up of silt-curtain
Platform
installation for pre‐drilling works and bored piling works
Installation
of temporary casings for the piling platform
Installation
of permanent casing
Bored
piling works