EXECUTIVE SUMMARY

Introduction

1.              This is the 5th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in June 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

3rd, 7th, 13th, 19th, 25th and 28th June 2013

24-hr TSP Monitoring

3rd, 7th, 13th, 19th, 25th and 28th June 2013

Noise Monitoring

4th, 10th, 20th and 26th June 2013

Water Quality Monitoring

3rd, 5th, 7th, 10th, 13th, 15th, 17th, 19th, 21st, 24th, 26th and 28th June 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

6th and 17th June 2013

Construction-phase underwater Noise Monitoring

N/A

Dolphin Behaviour Monitoring

N/A

Land-based Dolphin Behaviour and Movement Monitoring

N/A

Environmental Site Inspection

4th, 11th, 18th and 28th June 2013

Archaeological Site Inspection

18th June 2013

Remark:    N/A: No monitoring was conducted in the reporting month as no underwater sockets into rock can be carried out for marine bored piles in West Lantau in May and June in accordance with EP Condition 3.1.

    


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

0

0

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Complaint Log

 

8.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

9.              No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

10.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

11.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Loading and unloading

Ÿ   Setup of casting yard

Ÿ    

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

 

Portion A (Land Section)

Ÿ   Site clearance and  erection of water filled barriers as boundary

Ÿ   Timber Scaffolding

Ÿ   Pre-drilling work

Ÿ   Set-up facilities for marine delivery of concrete from land plants

 

Portion C

Ÿ   Land piling

Ÿ   Slewing the tele-communication cable and AA’s COM cable

Ÿ   Tree felling/transplant

Ÿ   Drainage and water main diversion

 

Western Water

Ÿ   Pre-drilling Work

Ÿ   Setting up of silt-curtain

Ÿ   Platform installation for pre‐drilling works and bored piling works

Ÿ   Installation of temporary casings for the piling platform

Ÿ   Installation of permanent casing

Ÿ   Bored piling works