Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
4/06/2013 |
Clear the discarded leaves at the temporary drainage channel at
Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 11 June 2013. |
11/06/2013 |
Clear the sand and silt at the deck of barge at P71. |
Rectification/improvement
was observed during the follow-up audit session on 18 June 2013. |
|
18/06/2013 |
Clear the stagnant water for the material skip at Portion C and the
drip tray at WA4. |
Rectification/improvement
was observed during the follow-up audit session on 28 June 2013. |
|
28/06/2013 |
To seal the gap at the platform at Pier 74 to avoid leakage of muddy
water to the sea. |
Rectification/improvement
was observed during the follow-up audit session on 2 July 2013. |
|
Ecology |
N/A |
N/A |
N/A |
Air Quality |
11/06/2013 |
Properly check the generator at P71 to avoid emitting dark smoke. |
Rectification/improvement
was observed during the follow-up audit session on 18 June 2013. |
28/06/2013 |
To check the air compressor at Pier 73 to avoid emitting dark smoke. |
Rectification/improvement
was observed during the follow-up audit session on 2 July 2013. |
|
Noise |
N/A |
N/A |
N/A |
Waste /
Chemical Management |
11/06/2013 |
Provide the plug for the drip tray at P71. |
Rectification/improvement
was observed during the follow-up audit session on 18 June 2013. |
28/06/2013 |
To implement acoustic decoupling measures for the
air compressor at Pier 74. |
Rectification/improvement
was observed during the follow-up audit session on 2 July 2013. |
|
Landscape
& Visual Impact |
N/A |
N/A |
N/A |
Permits/Licences |
4/06/2013 |
To display the Environmental Permit conspicuously at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 11 June 2013. |
Other(s) |
N/A |
N/A |
N/A |
Cultural Heritage (Sha Lo Wan (West)
Archaeological Site) |
N/A |
N/A(1) |
N/A |
Remark: N/A - No major environmental
deficiency was identified during the site inspection in the reporting month.