Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

3rd, 7th, 13th, 19th, 25th and 28th June 2013

24-hr TSP Monitoring

3rd, 7th, 13th, 19th, 25th and 28th June 2013

Noise Monitoring

4th, 10th, 20th and 26th June 2013

Water Quality Monitoring

3rd, 5th, 7th, 10th, 13th, 15th, 17th, 19th, 21st, 24th, 26th and 28th June 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

6th and 17th June 2013

Construction-phase underwater Noise Monitoring

N/A

Dolphin Behaviour Monitoring

N/A

Land-based Dolphin Behaviour and Movement Monitoring

N/A

Environmental Site Inspection

4th, 11th, 18th and 28th June 2013

Archaeological Site Inspection

18th June 2013

Remark:    N/A: No monitoring was conducted in the reporting month as no underwater sockets into rock can be carried out for marine bored piles in West Lantau in May and June in accordance with EP Condition 3.1.