9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Loading and unloading

Ÿ   Setup of casting yard

Ÿ    

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

 

Portion A (Land Section)

Ÿ   Site clearance and  erection of water filled barriers as boundary

Ÿ   Timber Scaffolding

Ÿ   Pre-drilling work

Ÿ   Set-up facilities for marine delivery of concrete from land plants

 

Portion C

Ÿ   Land piling

Ÿ   Slewing the tele-communication cable and AA¡¯s COM cable

Ÿ   Tree felling/transplant

Ÿ   Drainage and water main diversion

 

Western Water

Ÿ   Pre-drilling Work

Ÿ   Setting up of silt-curtain

Ÿ   Platform installation for pre©\drilling works and bored piling works

Ÿ   Installation of temporary casings for the piling platform

Ÿ   Installation of permanent casing

Ÿ   Bored piling works

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

9.3         A tentative construction programme is provided in Appendix A.