This is the 6th monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in July
2013.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
4th, 10th,
16th, 22th and 26th July 2013 |
24-hr TSP Monitoring |
4th, 10th,
16th, 22th and 26th July 2013 |
Noise Monitoring |
2nd, 8th,
17th , 23rd and 29th July 2013 |
Water Quality Monitoring |
2nd, 4th,
6th, 8th, 10th, 12th, 15th,
17th, 19th, 22th, 24th, 26th,
29th and 31st July 2013 |
5th and 10th
July 2013 |
|
(1)Construction-phase underwater Noise Monitoring |
11th, 12th,
15th, 16th, 17th, 18th, 19th,
22nd, 23rd and 24th July 2013 |
(1)Dolphin Behaviour
Monitoring |
8th, 9th,
10th, 11th, 12th, 13th, 15th,
17th, 18th, 19th, 23rd, 24th
and 29th July 2013 |
(1)Land-based Dolphin Behaviour
and Movement Monitoring |
9th, 11th,
12th, 15th, 16th, 17th, 18th,
22nd, 23rd, 24th, 25th and 26th
July 2013 |
Environmental Site Inspection |
2nd, 9th,
16th, 23th and 30th July 2013 |
Archaeological Site Inspection |
(2)N/A |
Remark: (1)Dolphin-related monitoring was conducted in the reporting
month. According to the EM&A Manual for HKLR, the dolphin-related
monitoring was conducted during the bored piling activities which presented in Appendix A.
(2) No archaeological site inspection was
conducted in the reporting month.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting month is tabulated in Table
II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
3 |
1 |
0 |
0 |
|
Undewater Noise |
RMS sound
pressure level re 1µPa |
0 |
0 |
0 |
0 |
1-hour TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was
recorded.
Construction
Underwater Noise
7.
All construction underwater noise monitoring was conducted as scheduled
in the reporting month. No Action/Limit Level exceedance
was recorded.
Water Quality
8.
All water quality monitoring was conducted as scheduled in the reporting
month. There are three Action Level and one Limit Level exceedances
for suspended solids were recorded.
9.
According to the investigation, no pollution discharge from the marine
works and no exceedances
were recorded at the impact stations (i.e. IS1 to IS4) which are close to
construction site.
Therefore, all exceedances are considered not due to
the Contract.
Complaint Log
10.
One environmental complaint was received in the reporting month.
Notification of Summons and Successful
Prosecutions
11.
No notification of summons and successful prosecution was received in
the reporting month.
12.
This report has been developed in compliance with the reporting requirements
for the subsequent monthly EM&A Report as required by the EM&A Manual
for Hong Kong Link Road (EM&A Manual).
13.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading
Portion A (Land Section)
Site
formation and clearance
Slewing the
tele-communication cable and Airport Authority
(AA)’s COM cable
Set up of
barriers
Laying
piling platforms.
Pre-drilling
work
Portion C
Land piling
Tree
felling/transplant
Water main
diversion
Airport
Channel
Piling jacket and
permanent casing
Pile
excavation by Reverse Circulation Drilling (RCD) method
Pile
excavation by Kelly method
Piling works
for temporary jetty
Installation
of permanent casing
Setting up
of silt-curtain
Western
Water
Pre-drilling
Work
Setting up
of silt-curtain
Platform
installation for pre-drilling works and bored piling works
Installation
of temporary casings for the piling platform
Installation
of permanent casing
Bored
piling works
Piling
Jacket and permanent casing