Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
02/07/2013 |
To review the sedimentation process of the surface runoff at Portion
C. |
Rectification/improvement
was observed during the follow-up audit session on 9 July 2013. |
09/07/2013 |
To clear the water at wheel washing bay at
Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 16 July 2013. |
|
09/07/2013 |
To clear the sand and silt settled at the drain
at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 16 July 2013. |
|
16/07/2013 |
To clear the sediment at the deck of flap-top
work barge at P50. |
Rectification/improvement
was observed during the follow-up audit session on 23 July 2013. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
16/07/2013 |
To check the air compressor at P50 to avoid emitting grey smoke. |
Rectification/improvement
was observed during the follow-up audit session on 23 July 2013. |
Noise |
16/07/2013 |
To close the door of air compressor which is in operation
at P50. |
Rectification/improvement
was observed during the follow-up audit session on 23 July 2013. |
Waste /
Chemical Management |
23/07/2013 |
To seal the hole of the drip tray near the office
containers at Portion C. |
Follow-up
action was needed for the item. |
23/07/2013 |
To remove the construction materials which were
placed at near the tree at Portion C. |
Follow-up
action was needed for the item. |
|
23/07/2013 |
Clear the deposit silt and sediment at the site
exit and drainage channel at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 30 July 2013. |
|
23/07/2013 |
Clear the oil stain at near the Pontoon at WA4. |
Rectification/improvement
was observed during the follow-up audit session on 30 July 2013. |
|
30/07/2013 |
To remove the construction materials which were
placed at near the tree at Portion C. |
Follow-up
action was needed for the item. |
|
30/07/2013 |
Clear the deposit silt and sediment at the
drainage channel at Portion C. |
Follow-up
action was needed for the item. |
|
30/07/2013 |
To seal the hole of the drip tray near the office
containers at Portion C. |
Follow-up
action was needed for the item. |
|
Landscape
& Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Other(s) |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West)
Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1)
- No major environmental deficiency was identified during the site
inspection in the reporting month.
N/A(2)
No archaeological site inspection was conducted in the reporting month.