Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
4th, 10th,
16th, 22th and 26th July 2013 |
24-hr TSP Monitoring |
4th, 10th,
16th, 22th and 26th July 2013 |
Noise Monitoring |
2nd, 8th,
17th , 23rd and 29th July 2013 |
Water Quality Monitoring |
2nd, 4th,
6th, 8th, 10th, 12th, 15th,
17th, 19th, 22th, 24th, 26th,
29th and 31st July 2013 |
5th and 10th
July 2013 |
|
(1)Construction-phase underwater Noise Monitoring |
11th, 12th,
15th, 16th, 17th, 18th, 19th,
22nd, 23rd and 24th July 2013 |
(1)Dolphin Behaviour
Monitoring |
8th, 9th,
10th, 11th, 12th, 13th, 15th,
17th, 18th, 19th, 23rd, 24th
and 29th July 2013 |
(1)Land-based Dolphin Behaviour
and Movement Monitoring |
9th, 11th,
12th, 15th, 16th, 17th, 18th,
22nd, 23rd, 24th, 25th and 26th
July 2013 |
Environmental Site Inspection |
2nd, 9th,
16th, 23th and 30th July 2013 |
Archaeological Site Inspection |
(2)N/A |
Remark: (1)Dolphin-related monitoring was conducted in the reporting
month. According to the EM&A Manual for HKLR, the dolphin-related
monitoring was conducted during the bored piling activities which presented in Appendix A.
(2) No archaeological site inspection was
conducted in the reporting month.