8.1
Summary
of exceedance is provided in Appendix L.
8.2
No
Action/Limit Level exceedance was recorded for air
quality, construction noise and underwater noise.
8.3
All
water quality monitoring was conducted as scheduled in the reporting month. There
are three Action Level and one Limit Level exceedances for suspended solids were recorded.
8.4
According
to the investigation, no pollution discharge from the marine works and no exceedances were recorded at the impact stations (i.e. IS1
to IS4) which are close to construction site. Therefore, all exceedances are considered not due to the Contract.
8.5
One environmental
related complaint was received in the reporting month. The Complaint Log is
attached in Appendix P.
8.6
There
was no prosecution or notification of summons received since the Contract commencement.