EXECUTIVE SUMMARY

Introduction

1.              This is the 7th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in August 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

1st, 7th, 13th, 19th, 23rd and 29th August 2013

24-hr TSP Monitoring

1st, 7th, 13th, 19th, 23rd and 29th August 2013

Noise Monitoring

8th, 15th , 20th and 26th August 2013

Water Quality Monitoring

3rd, 5th, 7th, 9th, 12th, 16th, 19th, 21st, 23rd, 26th, 28th  and 31st August 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

21st and 26th August 2013

Construction-phase underwater Noise Monitoring

(1)N/A

Dolphin Behaviour Monitoring

(1)N/A

Land-based Dolphin Behaviour and Movement Monitoring

(1)(2)N/A

Environmental Site Inspection

6th, 13th, 20th and 29th August 2013

Archaeological Site Inspection

(3)N/A

          Remark: (1)30days of construction-phase underwater noise monitoring, dolphin behavior monitoring and land-based dolphin behavior and movement monitoring have been completed in July 2013 according to EM&A Manual for HKLR. Results analysis is being undertaken and the final results will be provided in a separate report in September 2013 tentatively.

(2)No additional Land-based Dolphin Behaviour and Movement Monitoring were conducted in August 2013 as the results analysis has not finished.

              (3) No archaeological site inspection was conducted in the reporting month.


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

1

2

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There is one Action Level and two Limit Level exceedances for suspended solids were recorded.

8.              According to the investigation, no pollution discharge from the marine works. All exceedances are considered not due to the Contract as sediment plume due to natural fluctuation of shallow water was observed and water quality mitigation measures such as casing and silt curtains were properly implemented.

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

 

Land Viaduct (P85 to P114)

Ÿ   Set up of water treatment system

Ÿ   Set up of piling platforms

Ÿ   Set up of barriers

Ÿ   Site clearance

Ÿ   Forming of site access

Ÿ   Marine landing access establishment work

Ÿ   Land piling

Ÿ   Slewing  the  tele-communication cable and AA’s COM cable

Ÿ   Tree felling/transplant

Ÿ   Drainage  and  water  main diversion

Ÿ   Pre-drilling work

 

Marine Viaduct (P0 to P84)

Ÿ   Piling works for temporary jetty

Ÿ   Installation of piling jacket

Ÿ   Installation of permanent casings

Ÿ   Installation of temporary casings

Ÿ   Pile excavation by Reverse Circulation Drilling (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Pre-drilling Work

Ÿ   Setting up of silt-curtain

Ÿ   Platform installation for pre-drilling works and bored piling works