Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
1st, 7th,
13th, 19th, 23rd and 29th August
2013 |
24-hr TSP Monitoring |
1st, 7th,
13th, 19th, 23rd and 29th August
2013 |
Noise Monitoring |
8th, 15th
, 20th and 26th August 2013 |
Water Quality Monitoring |
3rd, 5th,
7th, 9th, 12th, 16th, 19th,
21st, 23rd, 26th, 28th and 31st August 2013 |
21st and 26th
August 2013 |
|
Construction-phase underwater Noise Monitoring |
(1)N/A |
Dolphin Behaviour
Monitoring |
(1)N/A |
Land-based Dolphin Behaviour
and Movement Monitoring |
(1)(2)N/A |
Environmental Site Inspection |
6th, 13th,
20th and 29th August 2013 |
Archaeological Site Inspection |
(3)N/A |
Remark:
(1)30days of construction-phase underwater noise monitoring, dolphin
behavior monitoring and land-based dolphin behavior and movement monitoring
have been completed in July 2013 according to EM&A Manual for HKLR. Results
analysis is being undertaken and the final results will be provided in a separate report in September 2013 tentatively.
(2)No additional Land-based Dolphin Behaviour and Movement Monitoring were conducted in August
2013 as the results analysis has not finished.
(3) No archaeological site inspection was conducted in the reporting month.