EXECUTIVE SUMMARY

Introduction

1.              This is the 8th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in September 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th September 2013

24-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th September 2013

Noise Monitoring

5th, 11th , 17th, 23rd and 30th September 2013

Water Quality Monitoring

2nd, 4th, 6th, 9th, 11th, 14th, 16th, 18th, 21st, 23rd, 25th , 28th and 30th September 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

11th and 19th September 2013

(1)Additional Land-based Dolphin Behaviour and Movement Monitoring

28th and 30th September 2013

Environmental Site Inspection

3rd, 10th, 17th and 27th September 2013

Archaeological Site Inspection

10th  September 2013

          Remark: (1) Additional Land-based Dolphin Behaviour and Movement Monitoring Results will be presented in a separate report as the results analysis has not finished.

(2) Land-based Dolphin Behaviour and Movement Monitoring will be conducted on 30 and 31 October 2013 according to the original approved methodology paper.  A revised proposal prepared by the Dolphin Specialist, Dr. Samuel Hung was submitted on 2 October 2013.  EPD and AFCD subsequently provided advisory comments on this revised proposal on 7 October 2013.  A finalized proposal for the Land-based Dolphin Behaviour and Movement Monitoring will be submitted for approval in due course.


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

3

1

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There is three Action Level and one Limit Level exceedances for suspended solids were recorded.

8.              According to the investigation, no pollution discharge was observed from the marine works. The exceedances at the monitoring station which is situated at the upstream of the site and the exceeded results were similar or within the ranges baseline monitoring results. Therefore, the exceedances are considered not due to the Contract.

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

 

Marine Viaduct (P0 to P84)

Ÿ   Piling works for the temporary jetty

Ÿ   Installation of temporary casings

Ÿ   Pile excavation by Reverse Circulation Drilling (RCD)  method

Ÿ   Pile excavation by Kelly method

Ÿ   Sonic Test

Ÿ   Installation of permanent casing

Ÿ   Installation of temporary piles for piling platform

Ÿ   Predrilling works

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Formation of piling platform along seawall

Ÿ   Site clearance

Ÿ   Formation of site access along the top of the existing seawall

Ÿ   Marine landing access establishment work

Ÿ   Drainage and water main diversion

Ÿ   Predrilling works

Ÿ   Concrete surrounding works for slewed telecommunication cables

Ÿ   Trench excavation for slewing of AAHK’s COM cable

Ÿ   Tree felling/transplant work

Ÿ   Pile head excavation / trimming

Ÿ   Pile cap and column construction