7.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures in the Contract site. The
summaries of site audits are attached in Appendix
M.
7.2
Site
audits were conducted on 3rd, 10th, 17th and 27th
September 2013 by ET after the commencement of construction works for the
Contract. A joint site audit with the representative with IEC, ER, the
Contractor and the ET was carried out on 27th September 2013. The
details of observations during site audit can refer to Table 7.1.
7.3
According
to EP condition 4.7 and EM&A Manual, periodic monitoring (every three
months) of construction works shall be conducted to ensure the avoidance of any
impacts on Sha Lo Wan (West) Archaeological Site.
Access to Sha Lo Wan (West) Archaeological site for
works areas and storage of construction equipment is not allowed. The 3rd
inspection to the Sha Lo Wan (West) Archaeological
Site was conducted on 10th September 2013 and next inspection will
be conducted in December 2013. No access to Sha Lo
Wan (West) Archaeological site for works areas and storage of construction
equipment was observed.
7.4
According
to the EIA Study Report, Environmental Permit and the EM&A Manual, the
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. An
updated summary of the EMIS is provided in Appendix
N.
7.5
Regular
marine travel route for marine vessels were implemented properly in accordance with
the submitted plan and relevant records were kept properly.
7.6
Acoustic
decoupling measures for the stationary equipment (generators, winch generators
and air compressors) mounted on boards were adopted according to the approved
Acoustic Decoupling Measures Plan.
7.7
Dolphin
exclusion zone was implemented by ET’s trained dolphin observer in accordance
with EP Condition 3.4. In addition, dolphin exclusion zone and dolphin watching
plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was
implemented by DCVJV’s trained dolphin watcher.
7.8
Spill kits
and booms are ready on site for the event of accidental spillage of oil or
other hazardous chemicals from construction activities including vessels
operating for the Contract.
7.9
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarized
in Table 7.1.
Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and
Recommendations |
Follow-up |
Water Quality |
10/09/2013 |
Clear the residual silt and debris at the
platform at P20. |
Rectification/improvement was observed during
the follow-up audit session on 17 September 2013. |
17/09/2013 |
Review the drainage plan at Portion C to avoid accumulating ponding water. |
Rectification/improvement was observed during
the follow-up audit session on 27 September 2013. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
10/09/2013 |
Properly check the air compressor to avoid
heavy smoke at P47. |
Rectification/improvement was observed during
the follow-up audit session on 17 September 2013. |
27/09/2013 |
Exposed stockpile should be properly
covered by tarpaulin to avoid dust emission. (Portion C) |
Rectification/improvement was observed during
the follow-up audit session on 2 October 2013. |
|
Noise |
10/09/2013 |
Properly implement the acoustic decoupling
measures for the water pump at P0. |
Rectification/improvement was observed during
the follow-up audit session on 17 September 2013. |
17/09/2013 |
Provide the noise label for the air
compressor at Portion C. |
Rectification/improvement was observed during
the follow-up audit session on 27 September 2013. |
|
Waste / Chemical Management |
03/09/2013 |
Clear the oil spillage from the air compressor at Portion C. |
Rectification/improvement was observed during
the follow-up audit session on 10 September 2013. |
03/09/2013 |
Remove the pipe at the drainage channel at Portion C. |
Rectification/improvement was observed during
the follow-up audit session on 10 September 2013. |
|
03/09/2013 |
Remove the chemical container which placed at near the drain at
Portion C. |
Rectification/improvement was observed during
the follow-up audit session on 10 September 2013. |
|
17/09/2013 |
Clear the rubbish at the back of office containers at Portion C. |
Rectification/improvement was observed during
the follow-up audit session on 27 September 2013. |
|
27/09/2013 |
General refuse should be properly disposed of and separated from
C&D waste materials. (Portion C) |
Rectification/improvement was observed during
the follow-up audit session on 2 October 2013. |
|
27/09/2013 |
Fencing and other construction materials should be kept a distance
from tree protection zone. (Portion C) |
Rectification/improvement was observed during
the follow-up audit session on 2 October 2013. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Other(s) |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha
Lo Wan (West) Archaeological Site) |
10/09/2013 |
N/A(1) |
N/A(1) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.
7.10
According
to the Contractor, 8,412m3 inert C&D materials were generated
during the reporting month.
7.11
The
Contractor was advised to minimize the wastes generated through the recycling
or reusing. All mitigation measures stipulated in approved waste management
plan shall be fully implemented.
7.12
The
amount of wastes generated by the activities of the Contract during the
reporting month is shown in Appendix O.