8               ENVIRONMENTAL NON-CONFORMANCE (EXCEEDANCES)

Summary of Exceedances

 

8.1         Summary of exceedance is provided in Appendix L.

8.2         No Action/Limit Level exceedance was recorded for air quality and construction noise.

8.3         All water quality monitoring was conducted as scheduled in the reporting month. There is three Action Level and one Limit Level exceedances for suspended solids were recorded.

8.4         According to the investigation, no pollution discharge was observed from the marine works. The exceedance at the monitoring station which is situated at the upstream of the site and the exceeded results were similar or within the ranges baseline monitoring results. Therefore, the exceedances are considered not due to the Contract.

Summary of Environmental Complaint

8.5         No environmental related complaint was received in the reporting month. The Complaint Log is attached in Appendix P.

Summary of Notification of Summons and Successful Prosecution