9.1
Major
site activities for the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading
Marine
Viaduct (P0 to P84)
Piling
works for the temporary jetty
Installation
of temporary casings
Pile
excavation by RCD method
Pile
excavation by Kelly method
Sonic Test
Installation
of permanent casing
Installation
of temporary piles for piling platform
Predrilling works
Land Viaduct
(P85 to P114)
Land piling
and concreting works
Formation
of piling platform along seawall
Site
clearance
Formation
of site access along the top of the existing seawall
Marine
landing access establishment work
Drainage
and water main diversion
Predrilling works
Concrete
surrounding works for slewed telecommunication cables
Trench
excavation for slewing of AAHK¡¯s COM cable
Tree
felling/transplant work
Pile head
excavation / trimming
Pile cap
and column construction
9.2
The
tentative environmental monitoring schedule for the next month is shown in Appendix D.
9.3
A
tentative construction programme is provided in Appendix A.