Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
3rd, 9th,
15th, 21st, 25th and 31st October
2013 |
24-hr TSP Monitoring |
3rd, 9th,
15th, 21st, 25th and 31st October
2013 |
Noise Monitoring |
10th, 16th
, 22nd and 28th
October 2013 |
Water Quality Monitoring |
2nd, 4th,
7th, 9th, 11th, 15th, 17th,
19th, 21st, 23rd, 25th , 28th
and 30th October 2013 |
9th and
18th October 2013 |
|
Additional Land-based Dolphin Behaviour and
Movement Monitoring |
(1) N/A |
Environmental Site Inspection |
2nd, 7th,
16th, 22nd and 29th October 2013 |
Archaeological Site Inspection |
(2)N/A |
Remark:
(1) The additional land-based dolphin behavior and movement
monitoring tentatively scheduled on 30 and 31 October 2013 were not conducted
in the reporting month. In view of the construction activities have no
significant change in the two months, the monitoring in October and November
2013 will be considered/reviewed in the monthly
EM&A report for November 2013.
(2)
No archaeological site inspection was conducted in the reporting month.