8               ENVIRONMENTAL NON-CONFORMANCE (EXCEEDANCES)

Summary of Exceedances

 

8.1         Summary of exceedance is provided in Appendix L.

8.2         No Action/Limit Level exceedance was recorded for air quality and construction noise.

8.3         All water quality monitoring was conducted as scheduled in the reporting month. There are five Action Level and three Limit Level exceedances for suspended solids were recorded. One Action Level exceedance for turbidity was recorded.

 

8.4         According to the investigation, no pollution discharge was observed from the site. In addition, no marine construction works were conducted in vicinity of monitoring station in which exceedances were recorded. Therefore, the exceedances are considered not due to the Contract.

Summary of Environmental Complaint

8.5         No environmental related complaint was received in the reporting month. The Complaint Log is attached in Appendix P.

Summary of Notification of Summons and Successful Prosecution

8.6         There was no prosecution or notification of summons received since the Contract commencement.