9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

Marine Viaduct (P0 to P84)

Ÿ   Piling works for the temporary jetty

Ÿ   Beams and deck installation for jetty

Ÿ   Installation of temporary casings

Ÿ   Pile excavation by Reverse Circulation Drilling (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Sonic Test

Ÿ   Installation of permanent casing

Ÿ   Installation of temporary piles for piling platform

Ÿ   Predrilling works

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Formation of piling platform along seawall

Ÿ   Kicker pour for column   

Ÿ   Formation of site access along the top of the existing seawall

Ÿ   Marine landing access establishment work

Ÿ   Drainage and water main diversion

Ÿ   Predrilling works

Ÿ   Concrete surrounding works for slewed telecommunication cables

Ÿ   Trench excavation for slewing of AAHK¡¦s COM cable

Ÿ   Tree felling/transplant work

Ÿ   Pile head excavation / trimming

Ÿ   Pile cap and column construction

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.