9.1
Major site activities for the coming reporting month will include:
WA4
Fabrication of rebar cages
Fabrication of temporary piling platforms
WA7
Fabrication of rebar cages
Loading and Unloading
Marine
Viaduct (P0 to P84)
Piling works for the temporary jetty
Beams and deck installation for jetty
Installation of temporary casings
Pile excavation by Reverse Circulation
Drilling (RCD)
method
Pile excavation by Kelly method
Sonic Test
Installation of permanent casing
Installation of temporary piles for piling
platform
Predrilling
works
Land
Viaduct (P85 to P114)
Land piling and concreting works
Formation of piling platform along seawall
Kicker pour for column
Formation of site access along the top of the
existing seawall
Marine landing access establishment work
Drainage and water main diversion
Predrilling
works
Concrete surrounding works for slewed telecommunication
cables
Trench excavation for slewing of AAHK¡¦s COM
cable
Tree felling/transplant work
Pile head excavation / trimming
Pile cap and column construction
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.