2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

 

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)  Land piling works are in progress with total 15 and 13 no. of pile concreted in Portion C and Portion A respectively. 7 piles were concreted in this reporting period. All land piling machines are carrying out piling works in Portion A due to pending of existing drainage, watermain and Communication Cable (COM cable) of Airport Authority (AA) division in Portion C;

(b)  Stage 1 formations of piling platform along seawall (P92 to P107) were completed in this reporting period. 8 other platforms (P84 to P91) were filled up to level of +3mPD;

(c)  12 pours of column were completed with 5 pours in this reporting period;

(d)  Rebar threading for coupler continues in Portion C;

(e)  Tree felling in Portion A & C was completed for areas currently having site works. Further approved tree felling will be carried out as required in nextstage;

(f)  Hong Kong Airport Authority’s permit for AA COM cables slewing still pending;

(g)  Drainage diversion work remains in progress with approximately 30m of 1200mm diameter pipe and 10m of 1350mm diameter pipe laid in November. Excavation works and Earth Lateral Support (ELS) continues;

(h)  Construction of ingresses & egresses along Portion A was completed and in operation;

(i)  ELS for pile cap construction at P111L was completed. Pile head breaking is in progress. ELS for P111R & P112L are also in progress;

Marine Viaduct (P0 to P84)

(j)  Jetty works at P69-P70 were completed;

(k)  Installation of temporary casings at P57 is in progress;

(l)  Piling Jacket were installed at P14, P22, P55, P56 & P66;

(m)  Permanent casing were installed at P14L, P22R, P55R, P56R & P66;

(n)  Pile excavation by RCD method in progress at P14, P22, P51, P54, P55, P56, P65 & P66 with 17 piles concreted in this reporting period;

(o)  Jackets were dismantled at P46, P51, P54L & P65;

(p)  Inter-face Coring Tests were carried out at P46, P53, P54 & P71;

(q)  Sonic Tests were carried out at P71L;

(r)  All barges moved out from Airport Channel on 7 November 2013 due to expiry of permit;

(s)  Installation of temporary piles, platforms and permanent casings for Kelly method carried out at P16, P17, P18, P38 and P39;

(t)  Piling platform at P0, P16, P40 and P44 were removed;

(u)  Pile excavation by Kelly method in progress at P19, P20, P38, P40, P41 and P42 carried out with 12 piles concreted in this reporting period;

(v)  Remedial works to piles at P0 completed and erection of temporary supports for receiving the precast shells in progress;

(w)  Inter-face Coring Test and Sonic Testing were carried out to completed piles at P20, P44 and P74;

Casting Yard / Floating Batching Plant

(x)  Progress of the precast concrete segment casting yard:

-     Construction of the two load-out jetties completed; Test and commissioning to be conducted in December.

-    All gantries (18 nos.) erected; 7 nos. tested and commissioned; 11 nos. to be tested and commissioned in December.

-   Mould fabrications are on-going with 1 no. “Type “B”, 8 nos. “Type A” (including 2 no. SOP’s) and 2 nos. Type D moulds assembled; “Type CH” (long spans) and “Type CP” mould fabrication continues at casting yard with first CH2 type fabricated.

-     Rebar jigs fabrication and installation continues with 18 of 30 nos. completed

-     Rebar and Prestress Tendon (PT) material delivery continues

-    A total of 41 segments concreted in this reporting period and up to end of the reporting period total 86 segments casted;

(y)  The floating concrete batching plant 1602 is in operation with 7 piles concreted;

(z)  Barge 1601 commenced its operation on 14 November with total 3 piles concreted.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

 

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

WA3B: GW-RS0499-13

15/05/2013 (00:00)

14/11/2013 (24:00)

Expired

P71-P73: GW-RS0636-13

17/06/2013(19:00)

16/12/2013(23:00)

Cancelled

WA7: GW-RW0484-13

15/07/2013(23:00)

14/01/2014(07:00)

Valid

WA4: GW-RW0496-13

19/07/2013(19:00)

18/01/2014(23:00)

Valid

P65-P66:GW-RS0865-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

P76-P80:GW-RS0868-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

P69-P70:GW-RS0869-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

WA7:GW-RW0524-13

27/08/2013(19:00)

27/02/2014(23:00)

Valid

WA4B:GW-RW0550-13

12/08/2013(23:00)

11/02/2014(07:00)

Valid

P69-P70: GW-RS0976-13

16/09/2013(19:00)

15/03/2014(23:00)

Valid

P76-P80: GW-RS0981-13

30/08/2013(19:00)

28/02/2014(23:00)

Valid

P83: GW-RS0956-13

24/08/2013(19:00)

23/02/2014(24:00)

Valid

P46-P64: GW-RS0970-13

27/08/2013(23:00)

26/02/2014(07:00)

Valid

P65-P66: GW-RS0967-13

27/08/2013(19:00)

26/02/2014(23:00)

Cancelled

P38-P54: GW-RS0986-13

02/09/2013(19:00)

01/03/2014(23:00)

Cancelled

P85-P87 and P103-P113:

GW-RS0994-13

02/09/2013(19:00)

01/03/2014(23:00)

Valid

P0 – P21: GW-RS1108-13

07/10/2013 (23:00)

06/04/2014 (07:00)

Valid

P88 – P102: GW-RS1116-13

08/10/2013 (19:00)

06/04/2014 (23:00)

Valid

P81 – P82: GW-RS1143-13

11/10/2013 (19:00)

10/04/2014 (24:00)

Valid

Waters in Works Area Portion A:

GW-RS1164-13

22/10/2013 (19:00)

23/12/2013 (23:00)

Valid

P0 – P25: GW-RS1166-13

17/10/2013 (19:00)

16/04/2014 (23:00)

Valid

P71 – P74: GW-RS1221-13

31/10/2013(19:00)

28/04/2014(23:00)

Valid

P71 – P74: GW-RS1217-13

30/10/2013(23:00)

29/04/2014(07:00)

Valid

P26    P43  and  P51    P68:

GW-RS1234-13

11/11/2013(19:00)

10/05/2014(23:00)

Valid

P101 – P113: GW-RS1322-13

30/11/2013(19:00)

30/01/2014(23:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

13/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

01/09/2013

30/11/2013

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-043

05/08/2013

04/02/2014

Valid

Dumping of Phase 1, 2a, 2b, 2c and 2d

(Type 1D and Type 2) marine sediment

EP/MD/14-070

07/10/2013

06/11/2013

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d

(Type 1D and Type 2) marine sediment

EP/MD/14-087

07/11/2013

06/12/2013

Valid