EXECUTIVE SUMMARY

Introduction

1.              This is the 11th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in December 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th December 2013

24-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th December 2013

Noise Monitoring

5th, 11th , 17th , 23rd  and 30th December 2013

Water Quality Monitoring

2nd, 4th, 6th, 9th, 11th, 13th, 16th, 18th, 20th, 24th, 26th , 28th and 30th December 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

3rd and 20th December 2013

Additional Land-based Dolphin Behaviour and Movement Monitoring

(1) N/A

Environmental Site Inspection

3rd, 10th, 17th , 24th and 31st December 2013

Archaeological Site Inspection

30th December 2013

          Remark: (1) In view of the construction activities have no significant change in the reporting month, the additional land-based dolphin behavior and movement monitoring was not conducted in December 2013. The review report for Land-based Dolphin Behaviour and Movement Monitoring has been submitted to DCVJV on 7 January 2014.

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

 

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

2

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

4

6

0

0

Suspended Solids (SS)

24

12

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Limit Level exceedance was recorded. Two Action Level exceedances for 24-hr TSP monitoring at AMS1were recorded on 10 and 27 December 2013.

6.              According to the investigation, no dust generation works was conducted at near the monitoring station during the monitoring and observable dust source from construction activity under Contract No. HY/2011/09. In addition, construction works from other site and stockpile of dusty materials without proper cover at near the monitoring station was observed. Therefore, the exceedance is considered not due to the Contract.

 

Construction Noise

 

7.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

 

 

Water Quality

 

8.              All water quality monitoring was conducted as scheduled in the reporting month. There are twenty-four Action Level and twelve Limit Level exceedances for suspended solids were recorded. In addition, there are four Action Level and six Limit Level exceedances for turbidity were recorded.

9.              According to the investigation, no pollution discharge was observed from the site. In addition, sediment plume discharging to the monitoring stations from the area outside the site boundary and localized plume in the monitoring area were observed. Therefore, the exceedances are considered not due to the Contract.

Complaint Log

 

10.          No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

11.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

12.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

13.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

Marine Viaduct (P0 to P84)

Ÿ   Piling works for the temporary jetty

Ÿ   Installation of temporary casings, jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of jacket

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face Coring Test and Sonic Test

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Erection of temporary supports for receiving the precast shells

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Construction of ingress and egresses

Ÿ   Drainage and water main diversion

Ÿ   Tree felling/transplant work

Ÿ   Excavation works and Earth Lateral Support (ELS)

Ÿ   Pile cap and column construction

Ÿ   Predrilling works