2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)    Land piling works are in progress with total 15 and21 nos. of pile concreted in Portion C and Portion A respectively. 6 piles were concreted in this reporting period. All land piling machines are carrying out piling works in Portion A due to  pending  of  existing  drainage,  watermain  and  Communication Cable (COM cable)  of  Airport Authority (AA) division  in Portion C;

(b)  18 pours of column were completed with 6 pours in this reporting period;

(c)  Rebar threading for coupler continues in Portion C;

(d) Hong Kong Airport Authority’s permit for formations of piling platform at P82 & P83 is still pending;

(e)  Tree transplanting was completed and maintenance works commenced.

(f)  Drainage diversion work remains in progress with laying of approximately 60m of  1200mm  diameter  pipe  and  50m  of  1350mm  diameter  pipe.  Excavation works and ELS are in progress;

(g)  Installation of portal beam at P109 is in progress;

(h) Earth Lateral Support (ELS) for pile cap construction at P111 and P112 were completed.  Pouring  of pile  cap  at  P111L  was  completed  and  P111R  are  in  progress.  Pile head breaking at P112 L & R are also in progress;

(i)  Formation work for Portal P110 was commenced.

Marine Viaduct (P0 to P84)

RCD Method:

(j)  Construction of temporary jetty works at P68 is in progress;

(k)  Installation of temporary casings at P55 & P59 is in progress;

(l)  Piling jackets were installed at P14, P22, P56, P57, P72 & P77;

(m)  Permanent casings were installed at P14L, P22L, P56R, P57R, P72R & P77R;

(n)  Pile excavation by RCD method in progress at P14, P22, P55, P56, P57 & P66 with 25 piles concreted in this reporting period;

(o)  Piling jackets were dismantled at P22R, P55L &P66;

(p)  Works  with  cofferdam:  Driving  of  sheet  piling  at  P74  was  commenced;

Temporary platform at P71 was installed.

(q)  Inter-face coring tests were carried out at P46, P47 & P71;

(r)  Full depth coring tests were carried out at P71R-3;

(s)  Sonic tests were carried out at P71 & P73;

(t)  Grouting works were carried out at P47 & P71;

(u)  Barges moved back to Airport Channel on 23 Nov 13.

Kelly Method:

(v)  Installation of temporary piles, platforms and permanent casings at P17, P18, P36 were carried out;

(w)  Piling platform at P20 and P44 were removed;

(x)  Pile excavation by Kelly method in progress at P19,P42, P37, P38, P39 with 17 piles concreted in this reporting period;

(y)  P0 L & R precast shells were installed. Trimming ofpile head is in progress;

(z)   Inter-face  Coring  Test  and  sonic  test  were  carried  out  to  completed  piles  at P20, P40, P48 and P7

Casting Yard / Floating Batching Plant

Progress of the precast concrete segment casting yard:

-  Construction of the two load-out jetties completed;Test and commissioning under process.

-  All gantries (18 nos.) erected; 7 nos. tested and commissioned; 11 nos. under testing and commissioning.

-  Mould  fabrications  are  on-going  with  1  no.  Type  B”,  8  nos.  Type  A” (including  2  no.  SOP’s),  2  nos.  Type  D  moulds  and  1 no.  “Type  CH2”  (long spans)  assembled;  other  “Type  CH”  and  “Type  CP”  mould  fabrication continues at casting yard.

-  Rebar jigs fabrication and installation continues with 18 of 30 nos. completed

-  Rebar and PT material delivery continues

-  A  total  of  64  segments  concreted  in  this reporting  period  and  up  to  end  of the reporting period total 150 segments casted. (y)  The floating concrete batching plant 1602 is in operation with 7 piles concreted;

Casting Yard for Precast Concrete Shell for Pilecap

3 nos. (cumulative 7 nos.) of CP1 precast shells were cast in precast yard and 2 nos. of CP1 precast shells were installed at Pier P0 in this reporting period.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

 

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

WA7: GW-RW0484-13

15/07/2013(23:00)

14/01/2014(07:00)

Valid

WA4: GW-RW0496-13

19/07/2013(19:00)

18/01/2014(23:00)

Valid

P65-P66:GW-RS0865-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

P76-P80:GW-RS0868-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

P69-P70:GW-RS0869-13

02/08/2013(23:00)

01/02/2014(07:00)

Valid

WA7:GW-RW0524-13

27/08/2013(19:00)

27/02/2014(23:00)

Valid

WA4B:GW-RW0550-13

12/08/2013(23:00)

11/02/2014(07:00)

Valid

P69-P70: GW-RS0976-13

16/09/2013(19:00)

15/03/2014(23:00)

Valid

P76-P80: GW-RS0981-13

30/08/2013(19:00)

28/02/2014(23:00)

Valid

P83: GW-RS0956-13

24/08/2013(19:00)

23/02/2014(24:00)

Valid

P46-P64: GW-RS0970-13

27/08/2013(23:00)

26/02/2014(07:00)

Valid

P85-P87 and P103-P113:

GW-RS0994-13

02/09/2013(19:00)

01/03/2014(23:00)

Valid

P0 – P21: GW-RS1108-13

07/10/2013 (23:00)

06/04/2014 (07:00)

Valid

P88 – P102: GW-RS1116-13

08/10/2013 (19:00)

06/04/2014 (23:00)

Valid

P81 – P82: GW-RS1143-13

11/10/2013 (19:00)

10/04/2014 (24:00)

Valid

Waters in Works Area Portion A:

GW-RS1164-13

22/10/2013 (19:00)

23/12/2013 (23:00)

Cancelled on 11/12/2013

P0 – P25: GW-RS1166-13

17/10/2013 (19:00)

16/04/2014 (23:00)

Cancelled on 11/12/2013

P71 – P74: GW-RS1221-13

31/10/2013(19:00)

28/04/2014(23:00)

Valid

P71 – P74: GW-RS1217-13

30/10/2013(23:00)

29/04/2014(07:00)

Valid

P26    P43  and  P51    P68:

GW-RS1234-13

11/11/2013(19:00)

10/05/2014(23:00)

Cancelled on 11/12/2013

P101 – P113: GW-RS1322-13

30/11/2013(19:00)

30/01/2014(23:00)

Valid

P101 – P113: GW-RS1314-13

01/12/2013 (00:00)

31/01/2014 (06:30)

Valid

P1 – P68: GW-RS1415-13

11/12/2013 (19:00)

03/06/2014 (23:00)

Valid

Waters in Works Area Portion A:

GW-RS1416-13

11/12/2013 (19:00)

22/02/2014 (23:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

13/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

01/09/2013

30/11/2013

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-043

05/08/2013

04/02/2014

Valid

Dumping of Phase 1, 2a, 2b, 2c and 2d

(Type 1D and Type 2) marine sediment

EP/MD/14-087

07/11/2013

06/12/2013

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d

(Type 1D and Type 2) marine sediment

EP/MD/14-099

07/12/2013

06/01/2014

Valid