2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct with
single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS), provisioning
of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land
Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works
(a) Land piling
works are in progress with total 15 and21 nos. of pile concreted in Portion C
and Portion A respectively. 6 piles were concreted in this reporting period.
All land piling machines are carrying out piling works in Portion A due to pending of
existing drainage, watermain and
Communication Cable (COM cable)
of Airport Authority (AA)
division in Portion C;
(b) 18 pours of column were completed with 6
pours in this reporting period;
(c)
Rebar threading for coupler continues in Portion C;
(d) Hong Kong Airport Authority’s permit
for formations of piling platform at P82 & P83 is still pending;
(e)
Tree transplanting was completed and maintenance works commenced.
(f)
Drainage diversion work remains in progress with laying of approximately
60m of 1200mm diameter pipe and
50m of 1350mm diameter pipe. Excavation works and ELS are in
progress;
(g)
Installation of portal beam at P109 is in progress;
(h) Earth Lateral Support (ELS) for pile
cap construction at P111 and P112 were completed. Pouring of pile cap
at P111L was
completed and P111R are
in progress. Pile head breaking at P112 L & R are
also in progress;
(i) Formation work for Portal P110 was
commenced.
Marine Viaduct (P0 to P84)
RCD Method:
(j)
Construction of temporary jetty works at P68 is in progress;
(k) Installation of temporary casings at P55
& P59 is in progress;
(l)
Piling jackets were installed at P14, P22, P56, P57, P72
& P77;
(m)
Permanent casings were installed at P14L, P22L, P56R, P57R, P72R & P77R;
(n)
Pile excavation by RCD method in progress at P14, P22, P55, P56, P57 & P66 with 25 piles concreted in this reporting
period;
(o) Piling jackets were dismantled at P22R,
P55L &P66;
(p)
Works with cofferdam: Driving of
sheet piling at
P74 was commenced;
Temporary platform at P71 was installed.
(q)
Inter-face coring tests were carried out at P46, P47 & P71;
(r)
Full depth coring tests were carried out at P71R-3;
(s)
Sonic tests were carried out at P71 & P73;
(t)
Grouting works were carried out at P47 & P71;
(u)
Barges moved back to Airport Channel on 23 Nov 13.
Kelly Method:
(v)
Installation of temporary piles, platforms and permanent casings at P17,
P18, P36 were carried out;
(w)
Piling platform at P20 and P44 were removed;
(x)
Pile excavation by Kelly method in progress at P19,P42,
P37, P38, P39 with 17 piles concreted in this reporting period;
(y) P0 L & R precast shells were
installed. Trimming ofpile head is in progress;
(z) Inter-face Coring Test and
sonic test were carried out
to completed piles at P20, P40, P48 and P7
Casting
Yard / Floating Batching Plant
Progress of the precast concrete segment
casting yard:
-
Construction of the two load-out jetties completed;Test and commissioning under process.
- All
gantries (18 nos.) erected; 7 nos. tested and commissioned; 11 nos. under
testing and commissioning.
- Mould fabrications are
on-going with 1
no. “Type “B”, 8
nos. “Type A” (including 2
no. SOP’s), 2 nos. Type D moulds and
1 no. “Type CH2” (long spans) assembled; other “Type CH”
and “Type CP”
mould fabrication continues
at casting yard.
- Rebar
jigs fabrication and installation continues with 18 of 30 nos. completed
- Rebar
and PT material delivery continues
-
A total of
64 segments concreted in
this reporting period and
up to end
of the reporting period total 150 segments casted. (y) The floating concrete batching plant
1602 is in operation with 7 piles concreted;
Casting
Yard for Precast Concrete Shell for Pilecap
3 nos. (cumulative 7 nos.) of CP1 precast
shells were cast in precast yard and 2 nos. of CP1 precast shells were
installed at Pier P0 in this reporting period.
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental protection
for this Contract is presented in Table 2.2.
Table 2.2 Status of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
WA7: GW-RW0484-13 |
15/07/2013(23:00) |
14/01/2014(07:00) |
Valid |
WA4: GW-RW0496-13 |
19/07/2013(19:00) |
18/01/2014(23:00) |
Valid |
P65-P66:GW-RS0865-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Valid |
P76-P80:GW-RS0868-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Valid |
P69-P70:GW-RS0869-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Valid |
WA7:GW-RW0524-13 |
27/08/2013(19:00) |
27/02/2014(23:00) |
Valid |
WA4B:GW-RW0550-13 |
12/08/2013(23:00) |
11/02/2014(07:00) |
Valid |
P69-P70: GW-RS0976-13 |
16/09/2013(19:00) |
15/03/2014(23:00) |
Valid |
P76-P80: GW-RS0981-13 |
30/08/2013(19:00) |
28/02/2014(23:00) |
Valid |
P83: GW-RS0956-13 |
24/08/2013(19:00) |
23/02/2014(24:00) |
Valid |
P46-P64: GW-RS0970-13 |
27/08/2013(23:00) |
26/02/2014(07:00) |
Valid |
P85-P87 and P103-P113: GW-RS0994-13 |
02/09/2013(19:00) |
01/03/2014(23:00) |
Valid |
P0 – P21: GW-RS1108-13 |
07/10/2013 (23:00) |
06/04/2014 (07:00) |
Valid |
P88 – P102: GW-RS1116-13 |
08/10/2013 (19:00) |
06/04/2014 (23:00) |
Valid |
P81 – P82: GW-RS1143-13 |
11/10/2013 (19:00) |
10/04/2014 (24:00) |
Valid |
Waters in Works Area
Portion A: GW-RS1164-13 |
22/10/2013 (19:00) |
23/12/2013 (23:00) |
Cancelled on 11/12/2013 |
P0 – P25: GW-RS1166-13 |
17/10/2013 (19:00) |
16/04/2014 (23:00) |
Cancelled on 11/12/2013 |
P71 – P74: GW-RS1221-13 |
31/10/2013(19:00) |
28/04/2014(23:00) |
Valid |
P71 – P74: GW-RS1217-13 |
30/10/2013(23:00) |
29/04/2014(07:00) |
Valid |
P26 –
P43 and P51 –
P68: GW-RS1234-13 |
11/11/2013(19:00) |
10/05/2014(23:00) |
Cancelled on 11/12/2013 |
P101 – P113: GW-RS1322-13 |
30/11/2013(19:00) |
30/01/2014(23:00) |
Valid |
P101 – P113: GW-RS1314-13 |
01/12/2013 (00:00) |
31/01/2014
(06:30) |
Valid |
P1 – P68: GW-RS1415-13 |
11/12/2013 (19:00) |
03/06/2014
(23:00) |
Valid |
Waters in Works Area
Portion A: GW-RS1416-13 |
11/12/2013 (19:00) |
22/02/2014
(23:00) |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
13/06/2012 |
N/A |
Valid |
A/C#
7016948 (Vessel
Disposal) |
01/09/2013 |
30/11/2013 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-043 |
05/08/2013 |
04/02/2014 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment EP/MD/14-087 |
07/11/2013 |
06/12/2013 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment EP/MD/14-099 |
07/12/2013 |
06/01/2014 |
Valid |