9.1
Major
site activities for the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading of rebar materials
Marine
Viaduct (P0 to P84)
Piling
works for the temporary jetty
Installation
of temporary casings, jackets, temporary piles, platform and permanent casings
Dismantling
of jacket
Pile
excavation by RCD method
Pile
excavation by Kelly method
Inter-face
Coring Test and Sonic Test
Predrilling works
Operation
of floating concrete batching plants
Erection of
temporary supports for receiving the precast shells
Land
Viaduct (P85 to P114)
Land piling
and concreting works
Construction
of ingress and egresses
Drainage
and water main diversion
Tree
felling/transplant work
Excavation
works and ELS
Pile cap
and column construction
Predrilling works
9.2
The tentative
environmental monitoring schedule for the next month is shown in Appendix D.
9.3
A
tentative construction programme is provided in Appendix A.