9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

Marine Viaduct (P0 to P84)

Ÿ   Piling works for the temporary jetty

Ÿ   Installation of temporary casings, jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of jacket

Ÿ   Pile excavation by RCD method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face Coring Test and Sonic Test

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Erection of temporary supports for receiving the precast shells

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Construction of ingress and egresses

Ÿ   Drainage and water main diversion

Ÿ   Tree felling/transplant work

Ÿ   Excavation works and ELS

Ÿ   Pile cap and column construction

Ÿ   Predrilling works

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.