1.
This is the 12th monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in January
2014.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
2nd, 8th,
14th, 20th, 24th and 30th January
2014. |
24-hr TSP Monitoring |
2nd, 8th,
14th, 20th, 24th and 30th January
2014. |
Noise Monitoring |
9th, 15th
, 21st and 27th
January 2014 |
Water Quality Monitoring |
2nd, 4th,
6th, 8th, 10th, 13th, 15th,
17th, 20th, 22th, 24th , 28th
and 30th January 2014 |
3rd and 24th
January 2014 |
|
Additional Land-based Dolphin Behaviour
and Movement Monitoring |
(1) 22nd and 27th
January 2014 |
Environmental Site Inspection |
7th, 14th
, 21st and 28th January 2014 |
Archaeological Site Inspection |
(2)N/A |
Remark:
(1) a)
Additional Land-based Dolphin Behaviour and Movement
Monitoring Results in January 2014 will be presented in a separate report.
b) Review Report for
Land-based Dolphin Behaviour and Movement Monitoring
to justify the necessarily of additional Land-based Dolphin Behaviour
and Movement Monitoring has been submitted to EPD / AFCD for advance review in
mid of January 2014. The preliminary reply from AFCD was received in mid
of February 2014.
c) The additional
land-based dolphin behavior and movement monitoring was proposed to be
conducted on 27 and 28 February 2014 in accordance with AFCD’s reply but it
should be subject to Dolphin Specialist’s availability.
(2) No
archaeological site inspection was conducted in the reporting month.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting month is tabulated in Table
II.
Table II Summary Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
1 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
6 |
12 |
0 |
0 |
|
Suspended Solids (SS) |
7 |
14 |
0 |
0 |
1-hour TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Limit Level exceedance
was recorded. One Action Level exceedance for 24-hr
TSP monitoring at AMS1was recorded on 20 January 2014.
6.
According to the investigation, no dust generation works was conducted
at near the monitoring station during the monitoring and observable dust source
from construction activity under Contract No. HY/2011/09. In addition, construction
works from other site and stockpile of dusty materials without proper cover at near
the monitoring station was observed. Therefore, the exceedance
is considered not due to the Contract.
Construction Noise
7.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was
recorded.
Water Quality
8.
All water quality monitoring was conducted as scheduled in the reporting
month. There are seven Action Level and fourteen Limit Level exceedances for suspended solids were recorded. In addition,
there are four Action Level and six Limit Level exceedances
for turbidity were recorded.
9.
According to the investigation, no pollution discharge was observed from
the site. In addition, adverse water quality outside the site boundary was
observed. Sediment plume and floating wastes discharging to the monitoring
stations from the area outside the site boundary was also observed. Routine
marine construction works was conducted as usual and water quality mitigation
measures such as casing and silt curtains were properly implemented. Therefore,
the exceedances are
considered not due to the Contract.
Complaint Log
10.
Two environmental complaints were received in the reporting month.
Notification of Summons and Successful Prosecutions
11.
No notification of summons and successful prosecution was received in
the reporting month.
12.
This report has been developed in compliance with the reporting
requirements for the subsequent monthly EM&A Report as required by the
EM&A Manual for Hong Kong Link Road (EM&A Manual).
13.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading of rebar materials
Marine
Viaduct (P0 to P84)
Construction
of the temporary jetty
Installation
of temporary casings, piling jackets, temporary piles, platform and permanent
casings
Dismantling
of piling jacket
Pile
excavation by Reverse Circulation Drill (RCD) method
Pile
excavation by Kelly method
Inter-face
coring test, full depth coring test and sonic test
Predrilling works
Operation
of floating concrete batching plants
Trimming of
pile head
Grouting
works
Driving of
sheet piling
Land
Viaduct (P85 to P114)
Land piling
and concreting works
Rebar
threading for coupler
Drainage
and water main diversion works
Tree
transplant and maintenance works
Installation
of portal beam
Excavation
works and Earth Lateral Support (ELS)
Pouring of
pile cap and pile head breaking
Formation
works