Table 7.1           Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

07/01/2014

Properly deploy the silt curtain at P104 to P107.

Rectification/improvement was observed during the follow-up audit session on 14 January 2014.

07/01/2014

To deploy the silt curtain during the cofferdam construction at P74.

Rectification/improvement was observed during the follow-up audit session on 14 January 2014.

21/01/2014

Properly deploy the silt curtain at near P107.

Follow-up action was needed for the item.

21/01/2014

To remove the equipment away from the marine water at near P81.

Rectification/improvement was observed during the follow-up audit session on 28 January 2014.

28/01/2014

Properly deploy the silt curtain at near P107 and the gap at the silt curtain should be avoided.

Rectification/improvement was observed during the follow-up audit session on 5 February 2014.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

14/01/2014

Properly cover the waste skip to avoid the wastes blown by wind.

Rectification/improvement was observed during the follow-up audit session on 21 January 2014.

21/01/2014

Properly cover the stockpiles of soil at Portion C.

Follow-up action was needed for the item.

28/01/2014

Properly cover the stockpiles of soil at Portion C.

Rectification/improvement was observed during the follow-up audit session on 5 February 2014.

Noise

07/01/2014

Provide acoustic decoupling measures for the generator at P74.

Rectification/improvement was observed during the follow-up audit session on 28 January 2014.

Waste / Chemical Management

07/01/2014

Provide drip tray for the generator at P0.

Rectification/improvement was observed during the follow-up audit session on 14 January 2014.

07/01/2014

To seal the hole of the drip tray and clear the oil leakage at P0.

Rectification/improvement was observed during the follow-up audit session on 14 January 2014.

21/01/2014

Clear the oil leakage at near the generator and threading machine at Portion C.

Follow-up action was needed for the item.

21/01/2014

Provide drip tray for the oil containers at P104.

Rectification/improvement was observed during the follow-up audit session on 28 January 2014.

28/01/2014

To remove the construction materials at near the trees at Portion C and Portion A (P103).

Rectification/improvement was observed during the follow-up audit session on 5 February 2014.

28/01/2014

Clear the oil leakage at near the threading machine at Portion C.

Rectification/improvement was observed during the follow-up audit session on 5 February 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

14/01/2014

To replace the incomplete Construction Noise Permit at WA4.

Rectification/improvement was observed during the follow-up audit session on 21 January 2014.

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark:   N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.