2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and
EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013
respectively. The environmental Permit (Permit No. EP-352/2009/C) was then
issued on 5 September 2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway
in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main
Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract
No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street lightings,
traffic aids and sign gantries, marine navigational aids, ship impact
protection system, water mains and fire hydrants, lightning protection system,
structural health monitoring and maintenance management system (SHM&MMS),
supervisory control and data acquisition (SCADA) system, as well as operation
and maintenance provisions of viaducts, provisioning of facilities for
installation of traffic control and surveillance system (TCSS), provisioning of
facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup & Partners
Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land
Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works
(a) All land piling machines are
carrying out piling works in
Portion A due
to pending the completion of
diversion of existing drainage & watermain and the commencement of COM cable of AA
division in Portion C;
(b)
P114 area site formation for piling works was completed. Pile P114R was
excavated to rock head and drilling of rock socket is in progress;
(c) AA
COM cable slewing was
completed and backfilled. Piling equipment for Pile P113C was
mobilized on site and pile excavation started;
(d) 27 pours of column were completed with
9 pours in this reporting period;
(e)
Rebar threading for coupler continues in Portion C;
(f)
AAHK’s permit for
the construction of
the carriageway diversion and formations of piling platform at P82
& P83 is still pending for approval;
(g)
Tree transplanting was completed and its maintenance works are on-going.
(h) Drainage diversion works remains in
progress. Most pipes were laid
except some pipes at manhole connection. MH2, MH3 & MH4 were completed.
Backfilling was partially completed;
(i) Waling of
ELS for pile cap construction at P111 L & R and
P112 L & R were removed upon completion of pile
cap and backfilled up to the top level of the pile cap.
(j)
The erection of the supporting false work (brackets and
main carrier beams) for the portal beam construction at
P109 was completed. Erection of side formwork for the portal
and kickers are in progress;
(k)
Formation work for Portal P110 was in progress.
Marine Viaduct (P0 to P84)
RCD Method:
(a)
Construction of temporary jetty for piling works atP68 is in progress;
(b) Piling jackets were installed at P14R,
P56L, P57L, P76R;
(c)
Permanent casings were installed at P14R, P55R, P56L, P59L, P59R & P77R;
(d)
Pile excavations are in progress at P14, P22, P55, P56, P57, P59, P72 & P77;
(e) Piling jackets were dismantled at P14L,
P55R, P57R & P73L;
(f)
Inter-face coring tests were carried out at P46, P50, P51, P65, P66 & P73;
(g)
No Full depth coring tests was carried out in this reporting period;
(h)
Sonic tests were carried out at P46, P50, P65
& P73;
(i) Grouting works were carried out at P46
& P73;
Kelly Method:
(j)
Installation of temporary piles were carried out atP16 (friction test
pile), P17, P18, P32, P33, P34, P35 & P36;
(k)
Installation of platforms were carried out at
P16, P17, P18, P35 & P36;
(l)
Installation of permanent
casing were carried out at P16, P18, P35 & P36;
(m) Piling platform removal and
temporary pile extraction were carried out
at P20, P38, P40 & P44;
(n)
Pile excavation by Kelly method are in progress
at P16, P18, P19, P37 & P39;
(o)
Trial water cracking and trial shaft grouting at P18-L5 was completed;
(p)
Inter-face core test were carried out at P20, P37, P42, P45 & P49;
(q)
Sonic tests were carried out at P20, P44 & P49.
Pilecap Construction:
(r) P0-L&R precast shells waterproofing
works and stage one reinforced concrete works was completed. Stage two
reinforced concrete works is in progress. Casting is scheduled to complete
before end of January 2014;
(s) Installation of precast shells at P47
and P48 were completed. Waterproofing and stage 1 reinforced concrete works is
in progress;
(t)
Preparation work for
the installation of
the precast shells for
pilecap construction at P46 is in progress;
(u)
Advanced concrete breaking works inside the permanent steel casing at
P20 and P44 has commenced;
(v) Works with cofferdam: Driving of sheet
piling at P74 was carried out; driving of sheet piling at P71 was commenced.
Precast
Segment
(w) Progress of the precast concrete
segment casting yard:
-
Test and commissioning of the two load-out jetties are in progress;
- All gantries in total of 18 nos. were
erected. 7 nos. gantries were tested and commissioned and the remaining 11 nos.
gantries areunder processing;
-
Mould fabrications for 1 no. Type B, 10 nos.
Type A(including 2 no. SOP’s), 2
nos. Type D, 1 no. Type DT, 4 nos. Type E, and
1 no. Type CH2 (long spans) were assembled. Other Type CH and Type CP mould
fabrication continues at the casting yard;
-
Rebar jigs fabrication and
installation continues with 18
of 30 nos. completed;
-
Rebar and PT material delivery continues;
-
A total of 13 segments were cast in this reporting period and up to end
of the reporting period total 169 segments cast.
Precast
Concrete Shell Casting and Installation
(x) 3 nos. (cumulative 10 nos.) of CP1 precast shells and 1 no. (cumulative
1 no.) of CP4 precast shell were cast in precast yard.
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
WA7: GW-RW0484-13 |
15/07/2013(23:00) |
14/01/2014(07:00) |
Expired |
WA4: GW-RW0496-13 |
19/07/2013(19:00) |
18/01/2014(23:00) |
Expired |
P65-P66:GW-RS0865-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Cancelled on 14/01/2014 |
P76-P80:GW-RS0868-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Valid |
P69-P70:GW-RS0869-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Cancelled on 14/01/2014 |
WA7:GW-RW0524-13 |
27/08/2013(19:00) |
27/02/2014(23:00) |
Valid |
WA4B:GW-RW0550-13 |
12/08/2013(23:00) |
11/02/2014(07:00) |
Valid |
P69-P70: GW-RS0976-13 |
16/09/2013(19:00) |
15/03/2014(23:00) |
Valid |
P76-P80: GW-RS0981-13 |
30/08/2013(19:00) |
28/02/2014(23:00) |
Valid |
P83: GW-RS0956-13 |
24/08/2013(19:00) |
23/02/2014(24:00) |
Valid |
P46-P64: GW-RS0970-13 |
27/08/2013(23:00) |
26/02/2014(07:00) |
Cancelled on 14/01/2014 |
P85-P87 and P103-P113: GW-RS0994-13 |
02/09/2013(19:00) |
01/03/2014(23:00) |
Valid |
P0 – P21: GW-RS1108-13 |
07/10/2013 (23:00) |
06/04/2014 (07:00) |
Cancelled on 14/01/2014 |
P88 – P102: GW-RS1116-13 |
08/10/2013 (19:00) |
06/04/2014 (23:00) |
Valid |
P81 – P82: GW-RS1143-13 |
11/10/2013 (19:00) |
10/04/2014 (24:00) |
Valid |
P71 – P74: GW-RS1221-13 |
31/10/2013(19:00) |
28/04/2014(23:00) |
Valid |
P71 – P74: GW-RS1217-13 |
30/10/2013(23:00) |
29/04/2014(07:00) |
Valid |
P101 – P113: GW-RS1322-13 |
30/11/2013(19:00) |
30/01/2014(23:00) |
Valid |
P101 – P113: GW-RS1314-13 |
01/12/2013 (00:00) |
31/01/2014
(06:30) |
Valid |
P1 – P68: GW-RS1415-13 |
11/12/2013 (19:00) |
03/06/2014
(23:00) |
Cancelled on 14/01/2014 |
Waters in Works Area
Portion A: GW-RS1416-13 |
11/12/2013 (19:00) |
22/02/2014
(23:00) |
Valid |
WA7: GW-RW0960-13 |
14/01/2014 (23:00) |
13/06/2014
(07:00) |
Valid |
WA4: GW-RW0006-14 |
19/01/2014(19:00) |
18/07/2014
(23:00) |
Valid |
P0 – P68: GW-RS0029-14 |
14/01/2014 (19:00) |
13/03/2014
(23:00) |
Valid |
P0 –
P28 and P57 –
67: GW-RS0026-14 |
14/01/2014(23:00) |
05/07/2014(07:00) |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
A/C#
7016948 (Vessel
Disposal) |
01/12/2013 |
28/02/2014 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-043 |
05/08/2013 |
04/02/2014 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment EP/MD/14-099 |
07/12/2013 |
06/01/2014 |
Expired |
Dumping of Category L and M) marine sediment EP/MD/14-090 |
03/01/2014 |
18/01/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment EP/MD/14-113 |
10/01/2014 |
09/02/2014 |
Valid |