Table 7.1           Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

05/02/2014

To avoid the leakage of muddy water to the sea at P93.

Rectification/improvement was observed during the follow-up audit session on 11 February 2014.

11/02/2014

To repair the silt curtain and clear the polystyrene granule at P57.

Rectification/improvement was observed during the follow-up audit session on 18 February 2014.

18/02/2014

To repair the silt curtain at P36.

Rectification/improvement was observed during the follow-up audit session on 28 February 2014.

18/02/2014

Provide sand bag bund at the barge to avoid leaking muddy water to the sea at P36.

Rectification/improvement was observed during the follow-up audit session on 28 February 2014.

18/02/2014

Clear the leakage of muddy water at near the silo at P36.

Rectification/improvement was observed during the follow-up audit session on 28 February 2014.

28/02/2014

Clear the sand materials at the platform at P70.

Rectification/improvement was observed during the follow-up audit session on 5 March 2014.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

05/02/2014

To cover the wastes skip at WA3.

Rectification/improvement was observed during the follow-up audit session on 11 February 2014.

Noise

11/02/2014

Part of the noise barrier was damaged at P18. The Contractor was reminded to repair it before the commencement of construction works during the restricted hours.

Rectification/improvement was observed during the follow-up audit session on 18 February 2014.

18/02/2014

To repair the noise barrier at the silo at P36.

Rectification/improvement was observed during the follow-up audit session on 28 February 2014.

Waste / Chemical Management

05/02/2014

To improve the chemical waste storage area at WA3 in accordance with code of practice on the Packaging, labeling and storage of chemical wastes.

Rectification/improvement was observed during the follow-up audit session on 11 February 2014.

05/02/2014

Clear and avoid the oil leakage at P101.

Rectification/improvement was observed during the follow-up audit session on 11 February 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark:   N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.