Table I Summary Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
5th, 11th,
17th, 21st and 27th February 2014. |
24-hr TSP Monitoring |
5th, 11th,
17th, 21st and 27th February 2014. |
Noise Monitoring |
6th, 12th
, 18st and 24th
February 2014 |
Water Quality Monitoring |
1st, 4th,
6th, 8th, 11th, 13th, 15th,
17th, 19th, 21st, 25th and 27th February 2014 |
24th and 26th February 2014 |
|
Environmental Site Inspection |
5th, 11th
, 18th and 28th February 2014 |
Archaeological Site Inspection |
N/A |
Remark:
(1)
Due to the short
notice given to Dolphin Specialist after receiving preliminary reply on Review Report for Land-based Dolphin Behaviour and
Movement Monitoring from AFCD in mid of February 2014, additional
land-based dolphin behaviour and movement monitoring
could not be arranged on 27 and 28 February 2014.
(2)
No
archaeological site inspection was conducted in the reporting month.