2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P81 to Eastern Abutment at SHT) and Preparation Works

(a)    All land piling machines are carrying out piling works in Portion A and P114L due to pending the completion of diversion of existing drainage & watermain and Communication Cable (COM cable) of Airport Authority (AA) in Portion C;

(b)  Piling work for P84 started;

(c)  Pile P114R rock excavation was completed with founding level inspected. Rebar cage installation and concreting will be carried out after completion of Pile P114L due to space constraint;

(d)  Pre-drilling at P106L started;

(e)  31 pours of column were completed with 4 pours in this reporting period;

(f)  Rebar threading for coupler continues in Portion C;

(g) Hong Kong Airport Authority’s permit for the construction of the carriageway diversion at P82 & P83 was received and site set up works started;

(h)  Hong Kong Airport Authority’s permit for formations of piling platform at P82 & P83 is still pending for approval;

(i)  Tree transplanting was completed and its maintenance works are on-going;

(j)  Drainage diversion works mostly completed;

(k)  Water pipes laying for water main diversion were mostly completed. Connection  to existing  water  main  pipe  and  testing  is  pending  for  AAHK’s permit;

(l)   Waling  of  ELS  for  pile  cap  construction  at  P111-L&R  were  removed  upon completion of pile cap and backfilled up to the top level of the pile cap;

(m)  Wailing of ELS and backfill at P112 started;

(n)  All side formwork and wing slab soffit for Portal P109 were completed. Steel fixing is in progress;

(o)  At portal P110, side formwork and wing slab soffit formwork were completed. Steel fixing for bottom mat and side bars are in progress.

 

Marine Viaduct (P0 to P84)

RCD Method:

(a)  Construction of temporary jetty for piling works atP68 remains in progress;

(b)  Piling jackets were installed at P61, P28L, P64 & P72L;

(c)  Piling jackets were dismantled at P22, P56 & P72R;

(d)  Permanent  casings  were  installed  or  spliced  at  P14R,  P57L,  P59,  P61,  P70, P76R & P72R;

(e)  Pile excavations are in progress at P14, P22, P57, P59, P61, P70, P72, P76 & P77 with 25 piles concreted in the reporting period;

(f)  Inter-face coring tests were carried out at P50, P66 & P73;

(g)  Full depth coring tests was carried out at P50;

(h)  Sonic tests were carried out at P51, P65 & P66;

(i)  Grouting works were carried out at P50 & P65;

Kelly Method:

(j)  Installation of temporary piles were carried out atP30, P31 & P32;

(k)  Installation of platforms were carried out at P17, P31, P33 & P34;

(l)  Installation of permanent casing were carried out at P33 & P34;

(m) Piling  platform  removal  and  temporary  pile  extraction  were  carried  out  at

P19, P37, P39, P40 & P42;

(n)  Pile excavation by Kelly method are in progress at P16, P18, P19, P37 & P39;

(o)  Pile excavation by Kelly method are in progress at  P18, P19, P35 & P36 with 13 piles concreted in the reporting period;

(p)  Friction test pile at P16: load test were carried out from 24 – 28 Feb 14;

(q)  Inter-face core test were carried out at P20, P37,  P39, P40, P42, P45, P49 & P78;

(r)   Full depth coring tests for P37-L3 and P42-R1 are in progress;

(s)   Sonic tests were carried out at P20, P44 & P49.

Pilecap Construction:

(t)  P0 - stage 2 concreting for pile cap was completed;

(u) P46 - Installation of precast shells and waterproofing works were completed. Pile trimming works are in progress;

(v) P47 – Installation of precast shells and 1st stage concreting were completed. Reinforcement fixing for 2nd stage concreting is in progress;

(w)  P48 – Installation of precast shells were completed;

(x)  Preparation  works  for  the  installation  of  the  precast  shells  for  pilecap construction at P44 are in progress;

(y)   Advanced  concrete  breaking  works  (pile  head  trimming)  at  P20,  P43  &  P49 are in progress whereas the works in P65 has been commenced;

(z)   Works with cofferdam: Driving of sheet piling at P71 in progress; erection of temporary working platform for sheet piling at P73R in progress.

 

Column Construction

(a)     P0-L&R steel fixing to the columns are in progress. Concreting is scheduled on March 2014 and 5 March 2014 for P0-R and P0-L respectively.

 

Deck Erection

(b)   Preparatory works for erection equipment are underway:

-          Lifting Frame LF2-1 fabrication commenced in Dongguan;

-          Modification for P109 Loading Installation commenced at Portion C.

 

Precast Segment

(a) Progress of the precast concrete segment casting yard:

-  Test and commissioning of the two load-out jetties are in progress;

- All gantries, in total of 18 nos., were erected. 7nos. gantries were tested and commissioned and the remaining 11 nos. gantries are under processing;  

-  Mould assembly for 1 no. Type B, 10nos. Type A (including 2 no. SOP’s), 2nos. Type D, 4nos. Type E (with 3 checked by survey), 1 no. Type CH2 (long spans) were assembled. Other Type CH and Type CP mould fabrication continues at the casting yard;

-  Rebar jigs fabrication and installation continues with 24 of 30 nos. (18 in Line No. 2 and 6 in Line No. 6) completed;  

-  Rebar and PT material delivery continues;

-  A  total  of  22  segments  were  cast  in  this  reporting  period  and  up  to  end  of  the reporting period total 191 segments cast.

 

Precast Concrete Shell Casting

(b) 2 nos. (cumulative 12  nos.)  of  CP1  precast  shells  and  no  (cumulative  1  no.) CP4 precast shell were cast in the reporting period.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

 

 

Table 2.2        Status of Environmental Licences, Notification and Permits

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

P76-P80:GW-RS0868-13

02/08/2013(23:00)

01/02/2014(07:00)

Expired

WA7:GW-RW0524-13

27/08/2013(19:00)

27/02/2014(23:00)

Expired

WA4B:GW-RW0550-13

12/08/2013(23:00)

11/02/2014(07:00)

Cancelled on 10 January 2014

P69-P70: GW-RS0976-13

16/09/2013(19:00)

15/03/2014(23:00)

Valid

P76-P80: GW-RS0981-13

30/08/2013(19:00)

28/02/2014(23:00)

Cancelled on 27 January 2014

P83: GW-RS0956-13

24/08/2013(19:00)

23/02/2014(24:00)

Expired

P85-P87 and P103-P113:

GW-RS0994-13

02/09/2013(19:00)

01/03/2014(23:00)

Valid

P88 – P102: GW-RS1116-13

08/10/2013 (19:00)

06/04/2014 (23:00)

Valid

P81 – P82: GW-RS1143-13

11/10/2013 (19:00)

10/04/2014 (24:00)

Valid

P71 – P74: GW-RS1221-13

31/10/2013(19:00)

28/04/2014(23:00)

Valid

P71 – P74: GW-RS1217-13

30/10/2013(23:00)

29/04/2014(07:00)

Valid

P101 – P113: GW-RS1322-13

30/11/2013(19:00)

30/01/2014(23:00)

Valid

P101 – P113: GW-RS1314-13

01/12/2013 (00:00)

31/01/2014 (06:30)

Expired

Waters in Works Area Portion A:

GW-RS1416-13

11/12/2013 (19:00)

22/02/2014 (23:00)

Expired

WA7: GW-RW0960-13

14/01/2014 (23:00)

13/06/2014 (07:00)

Valid

WA4: GW-RW0006-14

19/01/2014(19:00)

18/07/2014 (23:00)

Valid

P0 – P68: GW-RS0029-14

14/01/2014 (19:00)

13/03/2014 (23:00)

Valid

P0    P28  and  P57    67:

GW-RS0026-14

14/01/2014(23:00)

05/07/2014(07:00)

Valid

WA4B : GW-RW0008-14

10/01/2014(23:00)

09/07/2014(07:00)

Valid

P76-P80: GW-RS0048-14

01/02/2014(23:00)

27/07/2014(07:00)

Valid

P75-P80: GW-RS0054-14

27/01/2014(19:00)

26/07/2014(23:00)

Valid

WA7: GW-RW0097-14

28/02/2014(19:00)

27/08/2014(23:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

01/12/2013

28/02/2014

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-043

05/08/2013

04/02/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d

(Type 1D and Type 2) marine sediment

EP/MD/14-113

10/01/2014

09/02/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-12

05/02/2014

04/08/2014

Valid