2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning works of
affected existing facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land Viaduct (P81
to Eastern Abutment at SHT) and Preparation Works
(a) All land
piling machines are carrying out piling works in Portion A and P114L due to
pending the completion of diversion of existing drainage & watermain and Communication Cable (COM cable) of Airport
Authority (AA) in Portion C;
(b) Piling work for P84 started;
(c) Pile
P114R rock excavation was completed with founding level inspected. Rebar cage
installation and concreting will be carried out after completion of Pile P114L due to space constraint;
(d) Pre-drilling at P106L started;
(e)
31 pours of column were completed with 4 pours in this reporting period;
(f)
Rebar threading for coupler continues in Portion C;
(g) Hong Kong Airport Authority’s permit
for the construction of the carriageway diversion at P82 & P83 was received
and site set up works started;
(h) Hong Kong Airport Authority’s permit for
formations of piling platform at P82 & P83 is still pending for approval;
(i) Tree transplanting was completed and its
maintenance works are on-going;
(j)
Drainage diversion works mostly completed;
(k) Water pipes laying for water main
diversion were mostly completed. Connection to existing water main pipe and
testing is pending for
AAHK’s permit;
(l) Waling of
ELS for pile cap
construction at P111-L&R were removed upon completion of pile cap and
backfilled up to the top level of the pile cap;
(m)
Wailing of ELS and backfill at P112 started;
(n)
All side formwork and wing slab soffit for Portal P109 were completed.
Steel fixing is in progress;
(o)
At portal P110, side formwork and wing slab soffit formwork were
completed. Steel fixing for bottom mat and side bars are in progress.
Marine Viaduct (P0 to P84)
RCD Method:
(a)
Construction of temporary jetty for piling works atP68 remains in
progress;
(b) Piling jackets were installed at P61,
P28L, P64 & P72L;
(c)
Piling jackets were dismantled at P22, P56 & P72R;
(d)
Permanent casings were installed or
spliced at P14R, P57L, P59, P61, P70, P76R & P72R;
(e) Pile excavations are in progress at P14,
P22, P57, P59, P61, P70, P72, P76 & P77 with 25 piles concreted in the
reporting period;
(f)
Inter-face coring tests were carried out at P50, P66 & P73;
(g)
Full depth coring tests was carried out at P50;
(h)
Sonic tests were carried out at P51, P65 & P66;
(i) Grouting works were carried out at P50
& P65;
Kelly Method:
(j)
Installation of temporary piles were carried
out atP30, P31 & P32;
(k)
Installation of platforms were carried out at
P17, P31, P33 & P34;
(l)
Installation of permanent casing were carried
out at P33 & P34;
(m) Piling platform removal and
temporary pile extraction were carried out
at
P19,
P37, P39, P40 & P42;
(n)
Pile excavation by Kelly method are in progress
at P16, P18, P19, P37 & P39;
(o)
Pile excavation by Kelly method are in progress at P18, P19, P35 & P36 with 13
piles concreted in the reporting period;
(p)
Friction test pile at P16: load test were carried out from 24 – 28 Feb
14;
(q)
Inter-face core test were carried out at P20, P37, P39, P40, P42, P45, P49 & P78;
(r) Full depth coring tests for P37-L3
and P42-R1 are in progress;
(s) Sonic tests were carried out at
P20, P44 & P49.
Pilecap Construction:
(t) P0 - stage 2 concreting for pile cap was
completed;
(u) P46 - Installation of precast shells
and waterproofing works were completed. Pile trimming works are in progress;
(v) P47 –
Installation of precast shells and 1st stage concreting were completed.
Reinforcement fixing for 2nd stage concreting is in progress;
(w)
P48 – Installation of precast shells were completed;
(x) Preparation works for
the installation of
the precast shells for
pilecap construction at P44 are in progress;
(y) Advanced concrete breaking works (pile head trimming) at
P20, P43 & P49 are in progress whereas the works in
P65 has been commenced;
(z) Works with cofferdam: Driving of
sheet piling at P71 in progress; erection of temporary working platform for
sheet piling at P73R in progress.
Column
Construction
(a) P0-L&R steel fixing to the columns are
in progress. Concreting is scheduled on March 2014 and 5 March 2014 for P0-R
and P0-L respectively.
Deck
Erection
(b)
Preparatory
works for erection equipment are underway:
-
Lifting
Frame LF2-1 fabrication commenced in Dongguan;
-
Modification
for P109 Loading Installation commenced at Portion C.
Precast
Segment
(a) Progress of the precast concrete
segment casting yard:
-
Test and commissioning of the two load-out jetties are in progress;
- All gantries, in total of 18 nos., were
erected. 7nos. gantries were tested and commissioned and the remaining 11 nos.
gantries are under processing;
-
Mould assembly for 1 no. Type B, 10nos. Type A (including 2 no. SOP’s), 2nos. Type D, 4nos. Type E (with 3 checked by survey), 1
no. Type CH2 (long spans) were assembled. Other Type CH and Type CP
mould fabrication continues at the casting yard;
-
Rebar jigs fabrication and installation continues with 24 of 30 nos. (18
in Line No. 2 and 6 in Line No. 6) completed;
- Rebar and PT material delivery continues;
-
A total of
22 segments were cast in
this reporting period and
up to end
of the reporting period
total 191 segments cast.
Precast
Concrete Shell Casting
(b) 2 nos.
(cumulative 12 nos.) of
CP1 precast shells and
no (cumulative 1
no.) CP4 precast shell were cast in the reporting period.
Status of Environmental Licences, Notification
and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
P76-P80:GW-RS0868-13 |
02/08/2013(23:00) |
01/02/2014(07:00) |
Expired |
WA7:GW-RW0524-13 |
27/08/2013(19:00) |
27/02/2014(23:00) |
Expired |
WA4B:GW-RW0550-13 |
12/08/2013(23:00) |
11/02/2014(07:00) |
Cancelled on 10 January
2014 |
P69-P70: GW-RS0976-13 |
16/09/2013(19:00) |
15/03/2014(23:00) |
Valid |
P76-P80: GW-RS0981-13 |
30/08/2013(19:00) |
28/02/2014(23:00) |
Cancelled on 27 January
2014 |
P83: GW-RS0956-13 |
24/08/2013(19:00) |
23/02/2014(24:00) |
Expired |
P85-P87 and P103-P113: GW-RS0994-13 |
02/09/2013(19:00) |
01/03/2014(23:00) |
Valid |
P88 – P102: GW-RS1116-13 |
08/10/2013 (19:00) |
06/04/2014 (23:00) |
Valid |
P81 – P82: GW-RS1143-13 |
11/10/2013 (19:00) |
10/04/2014 (24:00) |
Valid |
P71 – P74: GW-RS1221-13 |
31/10/2013(19:00) |
28/04/2014(23:00) |
Valid |
P71 – P74: GW-RS1217-13 |
30/10/2013(23:00) |
29/04/2014(07:00) |
Valid |
P101 – P113: GW-RS1322-13 |
30/11/2013(19:00) |
30/01/2014(23:00) |
Valid |
P101 – P113: GW-RS1314-13 |
01/12/2013 (00:00) |
31/01/2014
(06:30) |
Expired |
Waters in Works Area
Portion A: GW-RS1416-13 |
11/12/2013 (19:00) |
22/02/2014
(23:00) |
Expired |
WA7: GW-RW0960-13 |
14/01/2014 (23:00) |
13/06/2014
(07:00) |
Valid |
WA4: GW-RW0006-14 |
19/01/2014(19:00) |
18/07/2014
(23:00) |
Valid |
P0 – P68: GW-RS0029-14 |
14/01/2014 (19:00) |
13/03/2014
(23:00) |
Valid |
P0 –
P28 and P57 –
67: GW-RS0026-14 |
14/01/2014(23:00) |
05/07/2014(07:00) |
Valid |
WA4B : GW-RW0008-14 |
10/01/2014(23:00) |
09/07/2014(07:00) |
Valid |
P76-P80: GW-RS0048-14 |
01/02/2014(23:00) |
27/07/2014(07:00) |
Valid |
P75-P80: GW-RS0054-14 |
27/01/2014(19:00) |
26/07/2014(23:00) |
Valid |
WA7: GW-RW0097-14 |
28/02/2014(19:00) |
27/08/2014(23:00) |
Valid |
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
A/C#
7016948 (Vessel
Disposal) |
01/12/2013 |
28/02/2014 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-043 |
05/08/2013 |
04/02/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment EP/MD/14-113 |
10/01/2014 |
09/02/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-12 |
05/02/2014 |
04/08/2014 |
Valid |