7.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures in the Contract site. The
summaries of site audits are attached in Appendix
M.
7.2
Site
audits were conducted on 5th, 11th, 18th and 28th
February 2014 by ET after the commencement of construction works for the
Contract. A joint site audit with the representative with IEC, ER, the
Contractor and the ET was carried out on 28th February 2014. The
details of observations during site audit can refer to Table 7.1.
7.3
According
to EP condition 4.7 and EM&A Manual, periodic monitoring (every three
months) of construction works shall be conducted to ensure the avoidance of any
impacts on Sha Lo Wan (West) Archaeological Site.
Access to Sha Lo Wan (West) Archaeological site for
works areas and storage of construction equipment is not allowed. The 4th
inspection to the Sha Lo Wan (West) Archaeological
Site was conducted on 30th December 2013 and next inspection will be
conducted in March 2014.
7.4
According
to the EIA Study Report, Environmental Permit and the EM&A Manual, the
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. An
updated summary of the EMIS is provided in Appendix
N.
7.5
Regular
marine travel route for marine vessels were implemented properly in accordance
with the submitted plan and relevant records were kept properly.
7.6
Acoustic
decoupling measures for the stationary equipment (generators, winch generators
and air compressors) mounted on boards were adopted according to the submitted
Acoustic Decoupling Measures Plan.
7.7
Dolphin
exclusion zone and dolphin watching plan according to EM&A Manual, Section
10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin
watcher.
7.8
Spill
kits and booms are ready on site for the event of accidental spillage of oil or
other hazardous chemicals from construction activities including vessels
operating for the Contract.
7.9
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarized
in Table 7.1.
Table
7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and
Recommendations |
Follow-up |
Water Quality |
05/02/2014 |
To avoid the leakage of muddy water to the sea at P93. |
Rectification/improvement was observed during
the follow-up audit session on 11 February 2014. |
11/02/2014 |
To repair the silt curtain and clear the polystyrene granule at P57. |
Rectification/improvement was observed during
the follow-up audit session on 18 February 2014. |
|
18/02/2014 |
To repair the silt curtain at P36. |
Rectification/improvement was observed during
the follow-up audit session on 28 February 2014. |
|
18/02/2014 |
Provide sand bag bund at the barge to avoid leaking muddy water to
the sea at P36. |
Rectification/improvement was observed during
the follow-up audit session on 28 February 2014. |
|
18/02/2014 |
Clear the leakage of muddy water at near the silo at P36. |
Rectification/improvement was observed during
the follow-up audit session on 28 February 2014. |
|
28/02/2014 |
Clear the sand materials at the platform at P70. |
Rectification/improvement was observed during
the follow-up audit session on 5 March 2014. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
05/02/2014 |
To cover the wastes skip at WA3. |
Rectification/improvement was observed during
the follow-up audit session on 11 February 2014. |
Noise |
11/02/2014 |
Part of the noise barrier was damaged at
P18. The Contractor was reminded to repair it before the commencement of
construction works during the restricted hours. |
Rectification/improvement was observed during
the follow-up audit session on 18 February 2014. |
18/02/2014 |
To repair the noise barrier at the silo at
P36. |
Rectification/improvement was observed during
the follow-up audit session on 28 February 2014. |
|
Waste / Chemical Management |
05/02/2014 |
To improve the chemical waste storage area at WA3 in accordance with
code of practice on the Packaging, labeling and
storage of chemical wastes. |
Rectification/improvement was observed during
the follow-up audit session on 11 February 2014. |
05/02/2014 |
Clear and avoid the oil leakage at P101. |
Rectification/improvement was observed during
the follow-up audit session on 11 February 2014. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha
Lo Wan (West) Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1)
- No major environmental deficiency was identified during the site
inspection in the reporting month.
N/A(2)
No archaeological site inspection was conducted in the reporting month.
7.10
According
to the Contractor, 2,152m3 inert C&D materials were generated
during the reporting month.
7.11
The
Contractor was advised to minimize the wastes generated through the recycling
or reusing. All mitigation measures stipulated in approved waste management
plan shall be fully implemented.
7.12
The
amount of wastes generated by the activities of the Contract during the
reporting month is shown in Appendix O.