EXECUTIVE SUMMARY

Introduction

1.              This is the 14th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in March 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

Parameter(s)

Date(s)

1-hr TSP Monitoring

5th, 11th, 17th, 21st and 27th March 2014.

24-hr TSP Monitoring

5th, 11th, 17th, 21st and 27th March 2014.

Noise Monitoring

6th, 12th , 18st  and 24th March 2014

Water Quality Monitoring

1st, 3th, 5th, 7th, 10th, 12th, 14th, 17th, 19th, 21st, 24th , 27th, 29th and 31st March 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

12th  and 26th March 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

14th and 19th March 2014

Environmental Site Inspection

5th, 11th , 18th and 28th March 2014

Archaeological Site Inspection

21st March 2014


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

13

4

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are thirteen Action Level and four Limit Level exceedances for suspended solids were recorded. No Action/Limit Level exceedances for dissolved oxygen and turbidity were recorded.

8.              According to the investigation, no pollution discharge was observed from the site. In addition, sediment plume due to natural fluctuation of shallow water and discharging from the area outside the site boundary to the monitoring station were observed. In addition, some of the exceeded results were similar or within the ranges baseline monitoring results. Therefore, the exceedances are considered not due to the Contract.

Complaint Log

 

9.              Two environmental complaints were received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P80)

Ÿ   Construction of the temporary jetty

Ÿ   Installation of temporary casings, piling jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of piling jacket

Ÿ   Piling platform removal works

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face coring test, full depth coring test, sonic test, friction test and load test

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Trimming of pile head

Ÿ   Grouting works

Ÿ   Concreting for pile cap

Ÿ   Driving of sheet piling

Ÿ   Trial water cracking and trial shaft grouting

Ÿ   Installation of recast shells and waterproofing works

Ÿ   Advanced concrete breaking works inside the permanent steel casing

Ÿ   Steel fixing to the column

 

Land Viaduct (P81 to P114)

Ÿ   Land piling and concreting works

Ÿ   Rebar threading for coupler

Ÿ   Drainage and water main diversion works

Ÿ   Backfilling

Ÿ   Tree transplant and maintenance works

Ÿ   Installation of portal beam

Ÿ   Excavation works and Earth Lateral Support (ELS)

Ÿ   Pouring of pile cap and pile head breaking

Ÿ   Formation works

Ÿ   Pours of column

Ÿ   Erection of side formwork for the portal and kickers

Ÿ   Road diversion works

Ÿ   Pre-drilling works, pile cap, column and portal construction

Ÿ   Side formwork and wing slab soffit formwork

Ÿ   Waling of ELS and backfill

Ÿ   Steel fixing for bottom mat and side bars