2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P81 to Eastern Abutment at SHT) and Preparation Works

(a)      All  land  piling  machines  are  carrying  out  piling  works  in  Portion  A  and  P114R due to pending the completion of diversion of existing drainage & watermain in Portion C.

(b)     Piling works for P84 are in progress.

(c)      Pile P114R completed.

(d)     Predrilling at P108L carried out in this reporting period.

(e)      40 pours for column were completed with 9 pours in this reporting period, 12 columns completed to top level (3 gridlines).

(f)      Rebar threading for coupler continues in Portion C.

(g)     Carriageway diversion at P82 & P83 is in progress.

(h)   Airport Authority (AA)’s permit for formations of piling platform at P82 & P83 is still pending for approval.

(i)     Trees maintenance works are on-going.

(j)       Drainage diversion works completed and remaining backfilling of abandoned pipe to be completed.

(k)     Water  main  diversion  completed  and  remaining  backfilling  of  abandoned  pipe  to  be completed.

(l)       Sheet piles for pile cap construction at P111-L&R will be removed after completion of column construction.

(m)   Portal P109 was concreted on 26 March 2014 and Portal P110 steel fixing and tendon ducts are in progress.

(n)     Portal P112 falsework erection is in progress.


Marine Viaduct (P0 to P84)

RCD Method:

(a)  Construction of temporary jetty for piling works atP68 is in progress.

(b)  Piling jackets were installed at P27, P29, P58R & P77L.

(c)  Piling jackets were dismantled at P14R, P56L, P57L & P61.

(d)  Pile excavations and casing installation are in progress at P28, P58, P59, P61, P64, P70, P72 & P77 with 27 piles concreted in the reporting period.

(e)  Inter-face coring tests were carried out at P51, P52 & P56.

(f)  Full depth coring tests was carried out at P50.

(g)  Sonic tests were carried out at P51, P52, P56, P57 & P59.

(h)  Grouting works were carried out at P50, P51 & P56.

Kelly Method:

(i)  Installation of temporary piles were carried out atP4, P29, P30, P31 & P32.

(j)  Installation of platforms were carried out at P17, P30, P31 & P33.

(k) Installation of permanent casing were carried out at P16, P17, P30, P33 & P34.

(l) Piling platform removal and temporary pile extraction were carried out at P19, P35 & P36.

(m)  Pile excavation by Kelly method are in progress at P17, P18, P34, P35, P36, & P41 with 18 piles concreted in the reporting period.

(n)  Inter-face core test were carried out at P19, P34, P35, P36 & P38.

(o)  Full depth coring tests for P42-R1 are in progress.

(p)  Sonic tests were carried out at P20, P39, P40, P42, P45 & P78.

Pilecap Construction:

(a)  4 nos. precast cap shells were installed at P43 andP44.

(b)  Waterproofing and stage 1 reinforced concrete works were carried out at P46, P48, P43 & P44.

(c)  Stage 1 concreting was completed at P46, P48.

(d)  Stage 2 reinforced concrete works were carried out at P47 & P48.

(e)  Stage 2 concreting was completed at P47.

(f)  Kingpost  installation  for  precast  cap  and  associated  steel  welding  works  were  carried out at P20, P65, P44.

(g)  Concrete  trimming  and  advanced  trimming  (inside  casing)  works  were  carried  out  at P20, P44, P43, P49, P46, P65, P40, P66 and P45.

(h)   Works with cofferdam:

- Driving of sheet piling and drilling for shear pin were completed at P71L.

- Driving of sheet piling were completed and drilling for shear pin is in progress at P71R.

- Driving of sheet piling at P73 is in progress.

 

Column Construction

(a)    P0-L&R columns were cast on 4 March 2014.

(b)   P47 steel fixing was completed and formwork installation commenced.

 

Deck Erection

(a)   Preparatory works for erection equipment are underway:

- Lifting Frame LF2-1 fabrication continues in Dongguan.

- Modification for P109 Loading gantry continues at Portion C.

Precast Segment

(a)   Progress of the precast concrete segment casting yard:

- Test and commissioning of the two load-out jetties are completed.

-  All gantries, in total of 18 nos., were erected, tested and commissioned.

-  Mould assembly for 1 no. Type B, 10 nos. Type A (including 2 no. SOP’s), 2 nos. Type D, 4 nos. Type E, 2 no. Type CH2, 1 no. Type CH3 and 1 no. of CP (long span field segments and SOP) were assembled.  Other Type CH and Type CP mould fabrication continues at the casting yard.

-  Rebar jigs fabrication and installation continues with 29 of 30 nos. (6 in Line No. 1, 17 in Line No. 2, and 6 in Line No. 6) completed.

-  Rebar and PT material delivery continues.

-  A total of 84 segments were cast in this reporting period and up to end of the reporting period total 275 segments cast.

Precast Concrete Shell Casting

(a) 4 nos. CP1 (cumulative 16 nos.) precast shells and 1 no. CP4 (cumulative 2 nos.) precast shell were cast in the reporting period.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

P69-P70: GW-RS0976-13

16/09/2013(19:00)

15/03/2014(23:00)

Expired

P85-P87 and P103-P113:

GW-RS0994-13

02/09/2013(19:00)

01/03/2014(23:00)

Expired

P88 – P102: GW-RS1116-13

08/10/2013 (19:00)

06/04/2014 (23:00)

Cancelled on 11 March 2014

P81 – P82: GW-RS1143-13

11/10/2013 (19:00)

10/04/2014 (24:00)

Valid

P71 – P74: GW-RS1221-13

31/10/2013(19:00)

28/04/2014(23:00)

Valid

P71 – P74: GW-RS1217-13

30/10/2013(23:00)

29/04/2014(07:00)

Cancelled on 18 March 2014

WA7: GW-RW0960-13

14/01/2014 (23:00)

13/06/2014 (07:00)

Valid

WA4: GW-RW0006-14

19/01/2014(19:00)

18/07/2014 (23:00)

Valid

P0 – P68: GW-RS0029-14

14/01/2014 (19:00)

13/03/2014 (23:00)

Cancelled on 18 February 2014

P0    P28  and  P57    67:

GW-RS0026-14

14/01/2014(23:00)

05/07/2014(07:00)

Cancelled on 18 February 2014

WA4B : GW-RW0008-14

10/01/2014(23:00)

09/07/2014(07:00)

Valid

P76-P80: GW-RS0048-14

01/02/2014(23:00)

27/07/2014(07:00)

Valid

P75-P80: GW-RS0054-14

27/01/2014(19:00)

26/07/2014(23:00)

Valid

WA7: GW-RW0097-14

28/02/2014(19:00)

27/08/2014(23:00)

Valid

P0-P68: GW-RS0122-14

18/02/2014(23:00)

13/08/2014(07:00)

Valid

P0-P68: GW-RS0123-14

18/02/2014(19:00)

12/08/2014(23:00)

Valid

Portion A: GW-RS0130-14

23/02/2014(19:00)

22/08/2014(23:00)

Valid

P101-P113: GW-RS0127-14

26/02/2014(19:00)

30/04/2014(23:00)

Valid

P101-P113:GW-RS0121-14

27/02/2014(00:00)

01/05/2014(06:30)

Valid

P85-P87 and P103-P113:

GW-RS0137-14

02/03/2014(19:00)

01/09/2014(23:00)

Cancelled on 11 March 2014

P69-P70: GW-RS0172-14

16/03/2014(19:00)

15/09/2014(23:00)

Valid

P81-P114: GW-RS0187-14

11/03/2014(19:00)

10/09/2014(23:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7015341      

(Vessel Disposal)

17/02/2014

31/05/2014

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-125

05/02/2014

04/08/2014

Valid

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment

EP/MD/14-134

19/02/2014

18/03/2014

Expired