7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 5th, 11th, 18th and 28th March 2014 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, ER, the Contractor and the ET was carried out on 28th March 2014. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 5th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 21st March 2014 and next inspection will be conducted in June 2014. No access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment was observed.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to the submitted Acoustic Decoupling Measures Plan.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1           Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

11/03/2014

Clear the waste materials and debris at the barge at P28.

Rectification/improvement was observed during the follow-up audit session on 18 March 2014.

11/03/2014

Provide mitigation measures to avoid the leakage of muddy water to the sea at platform at P28.

Rectification/improvement was observed during the follow-up audit session on 18 March 2014.

18/03/2014

Properly deploy the silt curtain at P106 and P98.

Rectification/improvement was observed during the follow-up audit session on 28 March 2014.

28/03/2014

Properly store the construction material to avoid it getting to the sea at P48.

Rectification/improvement was observed during the follow-up audit session on 1 April 2014.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

N/A(1)

N/A(1)

N/A(1)

Noise

28/03/2014

Provide noise emission labels for the breaker and air compressor at P39.

Rectification/improvement was observed during the follow-up audit session on 1 April 2014.

Waste / Chemical Management

05/03/2014

To clear and avoid the oil leakage from the equipment to the unpaved area at WA7.

Rectification/improvement was observed during the follow-up audit session on 11 March 2014.

05/03/2014

Clear the wastes at the drainage channel at WA7.

Rectification/improvement was observed during the follow-up audit session on 11 March 2014.

11/03/2014

To seal the hole of the drip tray at P75.

Rectification/improvement was observed during the follow-up audit session on 18 March 2014.

18/03/2014

Clear the general refuse at construction sites near the containers and site entrance of Portion C.

Rectification/improvement was observed during the follow-up audit session on 28 March 2014.

18/03/2014

To plug the hole of drip tray at Portion C.

Rectification/improvement was observed during the follow-up audit session on 28 March 2014.

18/03/2014

Provide drip tray for the oil container at P101.

Rectification/improvement was observed during the follow-up audit session on 28 March 2014.

28/03/2014

Clear and avoid oil leakage from the pump for diesel oil at P39.

Rectification/improvement was observed during the follow-up audit session on 1 April 2014.

28/03/2014

Provide drip tray for the oil containers at the barge of P48.

Rectification/improvement was observed during the follow-up audit session on 1 April 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

18/03/2014

To update the CNP which displays at the site entrance of Portion C

Rectification/improvement was observed during the follow-up audit session on 28 March 2014.

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

21/03/2014

N/A(1)

N/A(1)

Remark:      N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 2,376m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.