2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication cables/equipments
and reprovisioning works of affected existing
facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land Viaduct (P85
to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Drainage
and water main diversion in Portion C was completed, backfilling to the abandon
pipes in progress;Piling
works for P84 are in progress.
(b) CLKSR
narrowing was completed.
(c) One set of
piling machine has been mobilized back to Portion C to start the piling of
P108R. Remaining land piling machines are carrying out piling works in Portion
A.
(d) Pile
excavations and casing installation are in progress at P84, P85, P86, P87, P88
& P89 with 6 piles concreted in the reporting period.
(e) 49 pours
for column were completed with 7 pours in this reporting period, 16 columns
completed to top level (6 gridlines - P105, P109 to P113).
(f) Construction
of the temporary carriageway for diversion at P82 & P83 is in progress.
(g) Airport
Authority (AA)’s permit for formations of piling platform at P82 & P83
received and works are in progress.
(h) Sheet piles
for pile cap construction at P111-L&R removed and area backfilled for
portal scaffolding erection.
(i) Temporary
drainage diversion for the 700mm U-channel near P114R was installed.
(j) Portal P110
was concreted on 8 April 2014.
(k) Portal P112
falsework erection was completed and formwork
erection is in progress.
(l) Portal P105
steel bracket system was erected on 4, 10 to 12 April 2014. Falsework
erection on steel bracket support is in progress.
(m) Portal P111
blinding slab was cast and erection of falsework is
in progress.
(n) Dismantling
of formwork and the falsework system for Portal P109
is in progress.
Marine Viaduct (P0 to P84)
RCD Method:
(a)
Construction of temporary platform for piling works at P68 is in
progress.
(b) Piling jackets were installed at P13,
P27, P29, P58L, P60 &P76L.
(c)
Piling jackets were dismantled at P58R, P59 & P72.
(d) Pile excavations and casing
installation are in progress at P27, P28, P29, P58, P60, P64, P69, P70, P72
& P77 with 33 piles concreted in the reporting period.
(e) Inter-face coring tests were carried out
at P52, P53 & P72.
(f)
No full depth coring tests was carried in this reporting period.
(g)
Sonic tests were carried out at P52, P56 & P72.
(h)
Grouting works were carried out at P51 & P52.
Kelly Method:
(i) Installation of temporary piles were carried out at P4, P21 & P31.
(j)
Installation of platforms were carried out at
P4, P30 & P31.
(k) Installation of permanent casing were carried out at P4, P16, P30 & P31.
(l) Piling platform removal and temporary
pile extraction were carried out at P19, P20, P35, P36, P39
& P42.
(m) Pile excavation by Kelly method are in
progress at P17, P18, P33, P34 & P41 with 23 piles concreted in the
reporting period.
(n)
Inter-face core test were carried out at P19, P35 & P41.
(o) Full depth coring test for P19-L3 was
completed.
(p)
Sonic tests were carried out at P19, P20, P38, & P41.
Pilecap Construction:
(a)
No precast cap shell was installed in this reporting period.
(b) Stage 1 reinforced concrete and
waterproofing works were carried out and completed at P43 & P44.
(c)
Stage 2 concreting was completed at P46 & P48.
(d) Kingpost installation and associated
steel welding works for precast shell installation are in progress at P20, P40,
P44 & P49.
(e)
Concrete trimming and advanced trimming (inside casing) works were
carried out at P38, P39, P40, P42, P43, P45, P49, P50, P51, P65
& P66.
(f)
Works with cofferdam.
-
P71L: Installation of waling strut at 1st layer was completed
and installation of waling strut at 2nd layer is in progress;
Drilling for shear pin is in progress.
-
P73: Driving of sheet piling was completed and installation of access
platform is in progress.
Column
Construction
(a)
P47
L&R: 1st lift columns were cast in this reporting period.
(b)
Column
insert installation, mobilization and temporary works at P47, P48 & P46 are
in progress.
(c)
1st
lift construction: P46, P47 & P48.
(d)
2nd
lift construction: P47.
(e)
3rd
lift construction (Pier Head): Nil
Deck
Erection
(a) Preparatory
works for segment erection:
- Lifting Frame LF2-1 fabrication continues in Dongguan.
- Modification work to the Segment Unloading Frame
continues at Portion C.
-
Construction of the footing for the Segment Unloading Frame at the Southeast
Quay commenced.
-
Delivery and assembly of LG2 commenced at RTT.
Precast
Segment
(a) Progress
of the precast concrete segment casting yard:
- Mould assembly for 1 no. Type
B, 10 nos. Type A (including 2 no. SOP’s), 2 nos.
Type D, 4 nos. Type E, 2 no. Type CH2, 1 no. Type CH3 and 1 no. of CP (long
span field segments and SOP) were assembled. Other Type CH and Type CP mould
fabrication continues at the casting yard.
- Rebar jigs fabrication and installation continues
with 29 of 30 nos. (6 in Line No. 1, 17 in Line No. 2, and 6 in Line No. 6
completed).
- A total of 118 segments were cast in this
reporting period and up to end of the reporting period total 395 segments cast.
Precast
Concrete Shell Casting
(a)
Summary of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this
reporting period |
Cumulative No. of Precast Shell Completed
(up to 28th of each month) |
CP1 |
6 |
22 |
CP2 |
1 |
1 |
CP4 |
1 |
2 |
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
P81 – P82: GW-RS1143-13 |
11/10/2013 (19:00) |
10/04/2014 (24:00) |
Expired |
P71 – P74: GW-RS1221-13 |
31/10/2013(19:00) |
28/04/2014(23:00) |
Expired |
WA7: GW-RW0960-13 |
14/01/2014 (23:00) |
13/06/2014
(07:00) |
Valid |
WA4: GW-RW0006-14 |
19/01/2014(19:00) |
18/07/2014
(23:00) |
Valid |
WA4B : GW-RW0008-14 |
10/01/2014(23:00) |
09/07/2014(07:00) |
Valid |
P76-P80: GW-RS0048-14 |
01/02/2014(23:00) |
27/07/2014(07:00) |
Cancelled on 1 April 2014 |
P75-P80: GW-RS0054-14 |
27/01/2014(19:00) |
26/07/2014(23:00) |
Cancelled on 1 April 2014 |
WA7: GW-RW0097-14 |
28/02/2014(19:00) |
27/08/2014(23:00) |
Valid |
P0-P68: GW-RS0122-14 |
18/02/2014(23:00) |
13/08/2014(07:00) |
Valid |
P0-P68: GW-RS0123-14 |
18/02/2014(19:00) |
12/08/2014(23:00) |
Valid |
Portion A: GW-RS0130-14 |
23/02/2014(19:00) |
22/08/2014(23:00) |
Valid |
P101-P113: GW-RS0127-14 |
26/02/2014(19:00) |
30/04/2014(23:00) |
Valid |
P101-P113:GW-RS0121-14 |
27/02/2014(00:00) |
01/05/2014(06:30) |
Valid |
P69-P70: GW-RS0172-14 |
16/03/2014(19:00) |
15/09/2014(23:00) |
Valid |
P81-P114: GW-RS0187-14 |
11/03/2014(19:00) |
10/09/2014(23:00) |
Valid |
P75-P80: GW-RS0264-14 |
01/04/2014 (19:00) |
27/07/2014 (07:00) |
Valid |
P81-P82: GW-RS0344-14 |
11/04/2014(00:00) |
10/10/2014 (24:00) |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
A/C#
7015341 (Vessel
Disposal) |
17/02/2014 |
31/05/2014 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-125 |
05/02/2014 |
04/08/2014 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/14-151 |
21/03/2014 |
20/04/2014 |
Expired |