EXECUTIVE SUMMARY

Introduction

1.              This is the 16th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in May 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

5th, 9th, 15th, 21st, 27th and 30th May 2014.

24-hr TSP Monitoring

5th, 9th, 15th, 21st, 27th and 30th May 2014.

Noise Monitoring

7th , 16th , 22nd and 28th May 2014

Water Quality Monitoring

2nd, 5th, 7th, 10th, 12th, 14th, 16th, 19th, 21st, 23rd , 26th, 28th and 30th May 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

7th  and 20th May 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

19th and 27th May 2014

Environmental Site Inspection

7th , 13th, 20th and 30th May 2014

Archaeological Site Inspection

(1)  N/A

             Remark:        (1)   No archaeological site inspection was conducted in the reporting month.


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

6

1

0

0

Suspended Solids (SS)

5

1

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There are five Action Level and one Limit Level exceedances for suspended solids were recorded. In addition, there are six Action Level and one Limit Level exceedances for turbidity were recorded. No Action/Limit Level exceedance for dissolved oxygen was recorded.

8.              According to the investigation, no pollution discharge was observed from the site. In addition, some of the exceeded results were similar or within the ranges baseline monitoring results and sediment plume which is considered due to the movement of vessel was observed. Therefore, the exceedances are considered not due to the Contract.

Complaint Log

 

9.              Three environmental complaints were received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P80)

Ÿ   Construction of the temporary jetty

Ÿ   Installation of temporary casings, piling jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of piling jacket

Ÿ   Piling platform removal works

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face coring test, full depth coring test, sonic test, friction test

Ÿ   and load test   

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Trimming of pile head

Ÿ   Grouting works

Ÿ   Concreting for pile cap

Ÿ   Driving of sheet piling

Ÿ   Trial water cracking and trial shaft grouting

Ÿ   Installation of recast shells and waterproofing works

Ÿ   Advanced concrete breaking works inside the permanent steel casing

Ÿ   Steel fixing to the column and formwork installation

Ÿ   Kingpost installation for precast cap and associated steel welding works

 

Land Viaduct (P81 to P114)

Ÿ   Land piling and concreting works

Ÿ   Rebar threading for coupler

Ÿ   Backfilling

Ÿ   Tree transplant and maintenance works

Ÿ   Installation of portal beam

Ÿ   Excavation works and Earth Lateral Support (ELS)

Ÿ   Pouring of pile cap and pile head breaking

Ÿ   Formation works

Ÿ   Pours of column

Ÿ   Erection of side formwork for the portal and kickers

Ÿ   Road diversion works

Ÿ   Pre-drilling works, pile cap, column and portal construction

Ÿ   Side formwork and wing slab soffit formwork

Ÿ   Waling of ELS and backfill

Ÿ   Steel fixing for bottom mat and side bars

Ÿ   Carriageway diversion

Ÿ   Tendon ducts

Ÿ   Falsework erection

Ÿ   Temporary carriageway for diversion at P82 & P83