Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
07/05/2014 |
Silt curtain has observed damage and not
deployed properly at near P106 and P107. The Contractor was reminded to
replace the damage silt curtain as soon as possible. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
13/05/2014 |
Clear the deposited soil at the public road
at near P107. (Portion C) |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
13/05/2014 |
Properly deploy the silt curtain to ensure
it function effectively at P106, P107, P98 and P101. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
13/05/2014 |
Clear the floating wastes within the silt
curtain at P101. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
20/05/2014 |
To check the silt curtain and avoid the gap
at the silt curtain at P68. |
Rectification/improvement
was observed during the follow-up audit session on 30 May 2014. |
|
20/05/2014 |
Clear the deposited waste materials at the
platform at P73. |
Rectification/improvement
was observed during the follow-up audit session on 30 May 2014. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
07/05/2014 |
Clear the soil at the public road at Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
13/05/2014 |
Clear the deposited soil at the public road
at near P107. (Portion C) |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
30/05/2014 |
Dust generation was observed from the
trimming works at P45. The Contractor was reminded to provide sufficient dust
mitigation measures properly. |
Rectification/improvement
was observed during the follow-up audit session on 3 June 2014. |
|
Noise |
13/05/2014 |
Provide noise emission labels for the
hand-held breaker at P94. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
30/05/2014 |
To close the panel of air compressor at
P45. |
Rectification/improvement
was observed during the follow-up audit session on 3 June 2014. |
|
30/05/2014 |
To check and provide noise emission label
for the hand-held breakers at P45. |
Rectification/improvement
was observed during the follow-up audit session on 3 June 2014. |
|
Waste /
Chemical Management |
07/05/2014 |
Clear the oil spillage at the site entrance
of Portion C. |
Rectification/improvement
was observed during the follow-up audit session on 13 May 2014. |
07/05/2014 |
To remove the construction materials and
provide fencing for protecting the trees at Portion A and C. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
13/05/2014 |
To seal the hole of drip tray and review
the size of drip tray for placing the oil pump at near P108 (Portion C). |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
13/05/2014 |
Clear the accumulated waste at the waste
skip at near P107. (Portion C) |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
13/05/2014 |
To remove the construction materials at
near the tree and provide tree protection zone at P105 and P106. |
Rectification/improvement
was observed during the follow-up audit session on 20 May 2014. |
|
20/05/2014 |
Clear the accumulated wastes at barge of
P47. |
Rectification/improvement
was observed during the follow-up audit session on 30 May 2014. |
|
30/05/2014 |
Clear the waste materials at the platform
at P72. |
Rectification/improvement
was observed during the follow-up audit session on 3 June 2014. |
|
Landscape
& Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West)
Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1)
- No major environmental deficiency was identified during the site
inspection in the reporting month.
N/A(2)
No archaeological site inspection was conducted in the reporting month.