8.1
Summary
of exceedance is provided in Appendix L.
8.2
No
Action/Limit Level exceedance was recorded for air
quality and construction noise.
8.3
All
water quality monitoring was conducted as scheduled in the reporting month. There
are five Action Level and one Limit Level exceedances for suspended solids were recorded. In addition,
there are six Action Level and one Limit Level exceedances
for turbidity were recorded. No Action/Limit Level exceedance
for dissolved oxygen was recorded.
8.4
According
to the investigation, no pollution discharge was observed from the site. In
addition, some of the exceeded results were similar or within the ranges
baseline monitoring results and sediment plume which is considered due to the
movement of vessel was observed. Therefore, the exceedances
are considered not due to the Contract.
8.5
Three environmental
related complaints were received in the reporting month. The Complaint Log is
attached in Appendix P.
8.6
There
was no prosecution or notification of summons received since the Contract commencement.