EXECUTIVE SUMMARY

Introduction

1.              This is the 17th monthly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in June 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting month is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

5th, 11th, 17th, 23rd and 27th June 2014.

24-hr TSP Monitoring

5th, 11th, 17th, 23rd and 27th June 2014.

Noise Monitoring

6th , 12th , 18th and 24th June 2014

Water Quality Monitoring

3rd, 5th, 7th, 9th, 11th, 13th, 16th, 18th, 20th, 23rd , 25th, 27th and 30th June 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

6th  and 9th June 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

3rd and 6th June 2014

Environmental Site Inspection

3rd , 10th, 17th and 27th June 2014

Archaeological Site Inspection

26th June 2014


Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting month is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Month

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

1

0

0

0

 

1-hour TSP Monitoring

 

4.              All 1-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

24-hour TSP Monitoring

 

5.              All 24-hour TSP monitoring was conducted as scheduled in the reporting month.  No Action/Limit Level exceedance was recorded.

 

Construction Noise

 

6.              All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Water Quality

 

7.              All water quality monitoring was conducted as scheduled in the reporting month. There is one Action Level and no Limit Level exceedances for suspended solids were recorded. No Action/Limit Level exceedance for dissolved oxygen and turbidity were recorded.

8.              According to the investigation, no pollution discharge was observed from the site. In addition, the exceeded result was similar or within the ranges baseline monitoring results. Therefore, the exceedances are considered not due to the Contract.

Complaint Log

 

9.              No environmental complaint was received in the reporting month.

Notification of Summons and Successful Prosecutions

 

10.          No notification of summons and successful prosecution was received in the reporting month.

Reporting Changes

 

11.          This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

12.          Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P80)

Reverse Circulation Drill (RCD) Method:

Ÿ   Construction of temporary platform for piling works Concreting for pile cap

Ÿ   Installation of piling jackets

Ÿ   Dismantling of piling jackets

Ÿ   Pile excavation and casing installation

Ÿ   Inter-face tests, full depth coring test and sonic test

Ÿ   Grouting works

 

Kelly Method:

Ÿ   Installation of temporary piles, platforms permanent casing

Ÿ   Removal of piling platform and temporary pile extraction

Ÿ   Pile excavation

Ÿ   Inter-face tests, full depth coring test and sonic test

 

 

 

Pile Cap Construction:

Ÿ   Installation of precast cap shells

Ÿ   Concreting

Ÿ   Rebar fixing

Ÿ   Kingpost installation and associated steel welding works

Ÿ   Concreting trimming

 

Works with Cofferdam:

Ÿ   Installation of waling strut

Ÿ   Installation of shear pin

Ÿ   Installation of temporary working platform

 

Column Construction:

Ÿ   Casing of lift columns

Ÿ   Column insert installation, mobilization and temporary works

 

Deck Erection:

Ÿ   Lifting frame fabrication in Dongguan

Ÿ   Modification works to the Segment Unloading Frame (SUF) in Portion C

Ÿ   Pouring of the footing for the Segment Unloading Frame at the Southeast Quay

Ÿ   Delivery and assembly of Launching Gantry 2 and Lifting Frame at River Trade Terminal

 

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

Ÿ   Drainage and water main diversion and backfill

Ÿ   Pile construction

Ÿ   Pouring of column

Ÿ   Construction of temporary carriageway for road diversion

Ÿ   Piling platform erection

Ÿ   Portal side formwork erection and

Ÿ   Portal falsework erection and soffit formwork

Ÿ   Bearing installation and steel fixing works

Ÿ   Concreting works

Ÿ   Dismantling of falsework system