2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning works of
affected existing facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent
Environmental Checker (IEC) and Environmental Project Office (ENPO) for the
Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a)
Pile construction is in progress at grid line P83,
P84, P90 & P91 and 4 piles were concreted in this reporting period.
(b)
Total 65 pours for column were completed with 8
pours in this reporting period; 22 columns was completed
to top level (9 gridlines - P103 to P105 and P109 to P114 complete).
(c)
Construction of the temporary carriageway for road
diversion at P82 & P83 is completed.
(d)
Formation of piling platform at P83 and P91 were
completed and platform at P82 is in progress.
(e)
Portal P111 steel fixing is in progress.
(f)
Portal P113 side formwork erection is in progress.
(g)
Portal P105 was cast on 13 Jun 2014.
(h)
Portal P114 blinding concrete for scaffolding work
was cast and pending for Airport Authority (AA)’s Work Permit for portal construction.
(i)
Dismantling of steel bracket system for Portal P109
is in progress.
(j)
Erection of steel bracket system for Portal P103
and P104 is in progress.
Marine
Viaduct (P0 to P80)
RCD Method:
(a) Construction of
temporary platform for piling works at P68 is on hold.
(b) Piling jackets were
installed at P62, P63, P67.
(c) Piling jackets were
dismantled at P29.
(d) Pile excavations and
casing installation are in progress at P11, P13, P24, P25, P26, P62, P63, P69, P79 with 8 nos. piles
concreted in the reporting period.
(e) Inter-face coring tests
were carried out at P14, P22, P60, P61, P64, P77.
(f) Full depth coring tests was carried at
P14 & P64.
(g) Sonic tests were carried
out at P14, P54, P60, P61, P77.
(h) Grouting works were
carried out at P53, P60 & P70.
Kelly Method:
(i)
Installation of temporary piles were carried out at P2, P12 &
P19(D).
(j) Installation of
platforms were carried out at P11 & P19(D).
(k) Installation of permanent casing were
carried out at P21.
(l) Piling platform removal
and temporary pile extraction were carried out at P18 P34 & P41.
(m) Pile excavation by Kelly method are in
progress at P4, P16 with 5 piles concreted in the reporting period.
(n) Inter-face core test
were carried out at P17.
(o) No Full depth coring at P34-R1.
(p) Sonic tests were carried out at P19 & P19.
Pilecap Construction:
(a) 4 precast cap shells
were installed at P39 & P51.
(b) Stage 1 concreting
was completed at P40, P42 & P45.
(c) Stage 1 works in
progress at P39, P40, P42, P45 & P51.
(d) Stage 2 concreting was
completed at P40 & P43.
(e) Stage 2 works in
progress at P40, P43 & P45.
(f) Kingpost installation
and associated steel welding works for precast shell installation are in
progress at P37, P38, P39, P41, P49, P51 & P52 in
the reporting period.
(g) Concrete trimming and
advanced trimming (inside casing) works were carried out at P19, P36, P37, P38,
P39, P42, P45, P49 & P52 in the reporting period.
- P70L&R: Installation
of temporary working platform is in progress.
- P71L: Excavation works and
casting of concrete plug were completed. Dewatering works and sealing works are
in progress.
- P71R: Installation of
waling strut was completed. Excavation works is in progress.
- P72L&R: Installation of temporary working platform was completed.
Installation of sheet-pile is in progress.
- P73L: Installation of
waling strut at 2nd layer is in progress.
- P73R: Installation of waling
strut at 1st layer is in progress; and
- P74R: Proof drilling to locate the level of rockhead
and pre-boring to overcome obstruction was carried out in the reporting period.
Column Construction
(a) 1st lift works: P44.
(b) 2nd lift works: P46, P47 & P48.
(c) 2nd lift concreting: P46 & P48L.
(d) Pier head works: P46, P47 & P48-L.
(e) Concrete remedial at P48-R 1st lift.
(f) Columns insert installation, mobilization and temporary works were
carried out at P40.
Deck Erection
(a) Preparatory works for segment erection:
- Off-site fabrication of lifting frame continues in Dongguan.
- Modification works to the Segment Unloading Frame (SUF) is 90%
completed at Portion C and assembly commenced.
- Pouring of the footing foundation for the Segment Unloading Frame at
the Southeast Quay was completed and initial sections of towers erected.
- Delivery and assembly of Launching Gantry 2 (LG2) continues at River
Trade Terminal (RTT), winches have been tested.
- Delivery and assembly of Lifting Frames 2 (LF2) continues at RTT,
winches delivery and commissioning has commenced.
Precast Segment
(a) Progress for mould assembly:
Type of Segment |
Number of Segment |
Status |
A |
10 |
Completed (including 2
nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
1 |
Completed |
CP (long span SOP) |
2 |
Completed |
CH |
3 |
In progress |
DT |
1 |
In progress |
(b) Rebar jigs fabrication
and installation with 30 out of 30 nos. completed (6 in Line No. 1, 18 in Line
No. 2 and 6 in Line No. 6)
(c) A total of 122 segments were cast in
this reporting period which including 3 no. Segments on Pier (SOP) of long-span
segment and up to end of the reporting period total 558 segments cast
(d) Site clearance of the
area for yard extension in progress
Precast Concrete Shell Casting
(a)
Summary of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this
reporting period |
Cumulative No. of Precast Shell Completed
(up to 28th of each month) |
CP1 |
4 |
31 |
CP2 |
1 |
4 |
CP4 |
1 |
3 |
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
WA7: GW-RW0960-13 |
14/01/2014 (23:00) |
13/07/2014
(07:00) |
Valid |
WA4: GW-RW0006-14 |
19/01/2014(19:00) |
18/07/2014
(23:00) |
Valid |
WA4B : GW-RW0008-14 |
10/01/2014(23:00) |
09/07/2014(07:00) |
Valid |
WA7: GW-RW0097-14 |
28/02/2014(19:00) |
27/08/2014(23:00) |
Valid |
P0-P68: GW-RS0122-14 |
18/02/2014(23:00) |
13/08/2014(07:00) |
Valid |
P0-P68: GW-RS0123-14 |
18/02/2014(19:00) |
12/08/2014(23:00) |
Valid |
Portion A: GW-RS0130-14 |
23/02/2014(19:00) |
22/08/2014(23:00) |
Valid |
P81-P114: GW-RS0187-14 |
11/03/2014(19:00) |
10/09/2014(23:00) |
Cancelled on 6 June
2014 |
P75-P80: GW-RS0264-14 |
01/04/2014 (19:00) |
27/07/2014 (07:00) |
Valid |
P81-P82: GW-RS0344-14 |
11/04/2014(00:00) |
10/10/2014 (24:00) |
Valid |
P101-P113: GW-RS0485-14 |
21/05/2014(19:00) |
20/11/2014 (06:30) |
Valid |
P69-P74: GW-RS0556-14 |
30/05/2014(19:00) |
29/07/2014 (24:00) |
Valid |
P101-P113: GW-RS0576-14 |
06/06/2014(19:00) |
04/09/2014 (05:30) |
Valid |
P81-P114: GW-RS0583-14 |
06/06/2014(19:00) |
29/07/2014 (24:00) |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
A/C#
7015341 (Vessel
Disposal) |
26/05/2014 |
31/08/2014 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-125 |
05/02/2014 |
04/08/2014 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/15-009 |
09/05/2014 |
08/06/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/15-037 |
19/06/2014 |
18/07/2014 |
Valid |