2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      Pile construction is in progress at grid line P83, P84, P90 & P91 and 4 piles were concreted in this reporting period.

(b)     Total 65 pours for column were completed with 8 pours in this reporting period; 22 columns was completed to top level (9 gridlines - P103 to P105 and P109 to P114 complete).

(c)      Construction of the temporary carriageway for road diversion at P82 & P83 is completed.

(d)     Formation of piling platform at P83 and P91 were completed and platform at P82 is in progress.

(e)      Portal P111 steel fixing is in progress.

(f)      Portal P113 side formwork erection is in progress.

(g)     Portal P105 was cast on 13 Jun 2014.

(h)     Portal P114 blinding concrete for scaffolding work was cast and pending for Airport Authority (AA)’s Work Permit for portal construction.

(i)       Dismantling of steel bracket system for Portal P109 is in progress.

(j)       Erection of steel bracket system for Portal P103 and P104 is in progress.

 

Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of temporary platform for piling works at P68 is on hold.

(b)  Piling jackets were installed at P62, P63, P67.

(c)  Piling jackets were dismantled at P29.

(d)  Pile excavations and casing installation are in progress at P11, P13, P24, P25, P26, P62, P63, P69, P79  with 8 nos. piles concreted in the reporting period.

(e)  Inter-face coring tests were carried out at P14, P22, P60, P61, P64, P77.

(f)   Full depth coring tests was carried at P14 & P64.

(g)  Sonic tests were carried out at P14, P54, P60, P61, P77.

(h)  Grouting works were carried out at P53, P60 & P70.

Kelly Method:

(i)  Installation of temporary piles were carried out at P2, P12 & P19(D).

(j)  Installation of platforms were carried out at P11 & P19(D).

(k) Installation of permanent casing were carried out at P21.

(l)  Piling platform removal and temporary pile extraction were carried out at P18 P34 & P41.

(m) Pile excavation by Kelly method are in progress at P4, P16 with 5 piles concreted in the reporting period.

(n)  Inter-face core test were carried out at P17.

(o) No Full depth coring at P34-R1.

(p) Sonic tests were carried out at P19 & P19.

Pilecap Construction:

(a)  4 precast cap shells were installed at P39 & P51.

(b)   Stage 1 concreting was completed at P40, P42 & P45.

(c)  Stage 1 works in progress at P39, P40, P42, P45 & P51.

(d) Stage 2 concreting was completed at P40 & P43.

(e)  Stage 2 works in progress at P40, P43 & P45.

(f)   Kingpost installation and associated steel welding works for precast shell installation are in progress at P37, P38, P39, P41, P49, P51 & P52 in the reporting period.

(g)   Concrete trimming and advanced trimming (inside casing) works were carried out at P19, P36, P37, P38, P39, P42, P45, P49 & P52 in the reporting period.

(h)  Submerged pilecap works with cofferdam:

-  P70L&R: Installation of temporary working platform is in progress.

-  P71L: Excavation works and casting of concrete plug were completed. Dewatering works and sealing works are in progress.

-  P71R: Installation of waling strut was completed. Excavation works is in progress.

- P72L&R: Installation of temporary working platform was completed. Installation of sheet-pile is in progress.

-  P73L: Installation of waling strut at 2nd layer is in progress.

- P73R: Installation of waling strut at 1st layer is in progress; and

- P74R: Proof drilling to locate the level of rockhead and pre-boring to overcome obstruction was carried out in the reporting period.

 

Column Construction

(a)    1st lift works: P44.

(b)   2nd lift works: P46, P47 & P48.

(c)    2nd lift concreting: P46 & P48L.

(d)   Pier head works: P46, P47 & P48-L.

(e)    Concrete remedial at P48-R 1st lift.

(f)    Columns insert installation, mobilization and temporary works were carried out at P40.

 

Deck Erection

(a)   Preparatory works for segment erection:

- Off-site fabrication of lifting frame continues in Dongguan.

- Modification works to the Segment Unloading Frame (SUF) is 90% completed at Portion C and assembly commenced.

- Pouring of the footing foundation for the Segment Unloading Frame at the Southeast Quay was completed and initial sections of towers erected.

- Delivery and assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT), winches have been tested.

- Delivery and assembly of Lifting Frames 2 (LF2) continues at RTT, winches delivery and commissioning has commenced.

 

Precast Segment

(a)   Progress for mould assembly:

Type of Segment

Number of Segment

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

1

Completed

CP (long span SOP)

2

Completed

CH

3

In progress

DT

1

In progress

 

(b)  Rebar jigs fabrication and installation with 30 out of 30 nos. completed (6 in Line No. 1, 18 in Line No. 2 and 6 in Line No. 6)

(c) A total of 122 segments were cast in this reporting period which including 3 no. Segments on Pier (SOP) of long-span segment and up to end of the reporting period total 558 segments cast

(d)  Site clearance of the area for yard extension in progress

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

4

31

CP2

1

4

CP4

1

3

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

WA7: GW-RW0960-13

14/01/2014 (23:00)

13/07/2014 (07:00)

Valid

WA4: GW-RW0006-14

19/01/2014(19:00)

18/07/2014 (23:00)

Valid

WA4B : GW-RW0008-14

10/01/2014(23:00)

09/07/2014(07:00)

Valid

WA7: GW-RW0097-14

28/02/2014(19:00)

27/08/2014(23:00)

Valid

P0-P68: GW-RS0122-14

18/02/2014(23:00)

13/08/2014(07:00)

Valid

P0-P68: GW-RS0123-14

18/02/2014(19:00)

12/08/2014(23:00)

Valid

Portion A: GW-RS0130-14

23/02/2014(19:00)

22/08/2014(23:00)

Valid

P81-P114: GW-RS0187-14

11/03/2014(19:00)

10/09/2014(23:00)

Cancelled on 6 June 2014

P75-P80: GW-RS0264-14

01/04/2014 (19:00)

27/07/2014 (07:00)

Valid

P81-P82: GW-RS0344-14

11/04/2014(00:00)

10/10/2014 (24:00)

Valid

P101-P113: GW-RS0485-14

21/05/2014(19:00)

20/11/2014 (06:30)

Valid

P69-P74: GW-RS0556-14

30/05/2014(19:00)

29/07/2014 (24:00)

Valid

P101-P113: GW-RS0576-14

06/06/2014(19:00)

04/09/2014 (05:30)

Valid

P81-P114: GW-RS0583-14

06/06/2014(19:00)

29/07/2014 (24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7015341      

(Vessel Disposal)

26/05/2014

31/08/2014

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-125

05/02/2014

04/08/2014

Valid

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment

EP/MD/15-009

09/05/2014

08/06/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment

EP/MD/15-037

19/06/2014

18/07/2014

Valid