2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each bound
of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning works of
affected existing facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a)
Pile
construction is in progress at P82, P83 & P91 and 6 piles were concreted in
this reporting period.
(b)
Total 82 pours for column were completed with 13
pours in this reporting period; 29 columns was completed
to top level (14 gridlines – P96 & P97, P103 to P114).
(c)
Formation
of piling platform at P82R was completed and formation of
platform at P81 commenced at the end of July.
(d)
Portal
P111 was concreted on 16 July 2014.
(e)
Portal
P113 was concreted on 26 July 2014.
(f)
Portal
P103 & P104 erection of side formwork is in progress.
(g)
Portal
P114 blinding concrete for scaffolding work was cast and erection of the
framework above footpath of Scenic Road is pending the issue of Airport
Authority (AA)’s
Work Permit.
(h)
Dismantling
of steel bracket system for Portal P105 is in progress.
(i)
Erection
of steel girder system for Portal P108, P107 and P106 is pending for approval
of method statement and work permit application.
Marine
Viaduct (P0 to P80)
RCD Method:
(a) Construction
of the temporary platform for piling works at P68 was suspended since 10 June
2014.
(b) Piling
works at P69 was suspended on 12 July (9 out of 12 piles already completed).
(c) Forming
the formation for the temporary for piling P75 was suspended on 22 July 2014.
(d) Piling
jackets were installed at P79 and P32.
(e) Piling
jackets were dismantled at P79 and P26.
(f) Pile
excavations and casing installation are in progress at P11, P26, P32, P62, P67,
P69, and
P79 with 27 nos. piles concreted in the reporting period.
(g) Inter-face
coring tests were carried out at P22, P27, P59 and P76.
(h) No full depth coring test was carried during
the reporting period.
(i) Sonic
tests were carried out at P27, P59, P64, P76 and P77.
(j) Grouting
works were carried out at P61 and P76.
Kelly Method:
(i) Installation
of temporary piles were carried out at P2 and P3.
(j) Installation of platforms were
carried out at P2 and P19D.
(k) Installation of
permanent casing were carried out at P2 and P19D.
(l) Piling platform
removal and temporary pile extraction were carried out at P18b, P18c and P34.
(m) Pile excavation by Kelly method are in progress at P2, P4,
P16, P30, P33 with 10 piles concreted in the reporting period.
(n) Inter-face
core test were carried out at P17.
(o) Full
depth coring was carried out at P17-L1.
(p) Sonic
tests were carried out at P17 & P18.
Pilecap Construction:
(a) 12
precast cap shells were installed at P20, P36, P37, P38, P41 and P52 (8 CP1, 2
CP2 & 2 CP4).
(b) Stage
1 concreting was completed at P39, P49 and P51.
(c) Stage 1 works is in progress at P41 &
P52.
(d) Stage
2 concreting was completed at P42 & P45.
(e) Stage
2 works is in progress at P39 & P49.
(f) Kingpost
installation and associated steel welding works for precast shell installation
are in progress at P19, P36, P50 and P66.
(g) Concrete
trimming and advanced trimming (inside casing) works were carried out at P19,
P20, P35, P51, P52, P60, P61 and P66.
- P70R: Installation of sheet-pile is in
progress.
- P70L: Installation of temporary working
platform is in progress.
- P71L: Additional welding to the cofferdam is in
progress.
- P71R: Excavation works for the concrete plug is
in progress.
- P72L&R: Installation of sheet-pile substantially
completed, preparation works for the installation of struts is in progress.
- P73L: Installation of waling strut at 2nd
layer is in progress;
- P73R: Installation of waling strut at 2nd
layer substantially completed
- P74R: Installation of shear pin is in
progress.
- P78L&R: Cutting of bored pile casing for
the construction of working platform is in progress.
- A derrick barge for the pile cap construction
was mobilized on 20 June 2014, bending of rebar and preparation of formwork is
in progress
Column Construction
(a) 1st lift works : P43 and P44.
(b) 2nd lift works : P46, P47 & P48L.
(c) 2nd lift concreting : P46 & P48L.
(d) Pier head works : P46, P47 & P48L.
(e) Pier head concreting : P47.
(f) Demolishing works at P48-R 1st lift.
(g) Columns’ insert installation, mobilization and temporary works were
carried out at P40 and P45
Deck Erection
(a) Preparatory works for segment erection:
- Off-site fabrication of lifting
frame is substantially completed in Dongguan.
- Segment Unloading Frame
(SUF) is substantially completed with all towers and truss steelwork erected
and the main winch installed
- Delivery and assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches have
been tested.
- Launching Gantry 1 (LG1) assembly re-started
with all components on site.
- Delivery and assembly of Lifting Frames 2 (LF2) continues. 4
frames have been fully delivered and assembled at RTT of which one has been
erected at P109-L. 50% of the remaining 2 frames have been delivered to WA4
with assembly commenced.
- Trial assembly of Lifting Frames 1 (LF1) has commenced in Donguan with delivery to be made as soon as space is freed
up on site for assembly.
- 4 winches have been
delivered with other 4 winches during transit from Europe.
Precast Segment
(a) Progress for mould assembly:
Type of Segment |
Number of Segment |
Status |
A |
10 |
Completed (including 2 nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
1 |
Completed |
CP (long span SOP) |
2 |
Completed |
CH |
3 |
In progress |
DT |
1 |
Completed |
(b) 140 segments were cast in this reporting
period including the first DT segment.
(c) Cumulative total 798 segments cast.
(d) Site clearance of the area for yard extension
is in progress.
Precast Concrete Shell Casting
(a)
Summary of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this
reporting period |
Cumulative No. of Precast Shell Completed
(up to 28th of each month) |
CP1 |
6 |
37 |
CP2 |
3 |
7 |
CP4 |
0 |
3 |
Ground Investigations
-
Up to 4 drilling rigs are working on micro
platforms and jack-up barges.
-
Predrilling works were carried out at P1, P2 & P3 in this
reporting period.
-
7 nos. of pre-drills were completed in this
reporting period including additional holes. Total 722 piles have completed predrills (including GI used as predrill).
-
Total 113 gridline (97%) out of 115 were completed
for pre-drilling.
-
Total 110 gridlines for first issue of Founding
Level Proposals were submitted. 3 no. was submitted in this reporting period.
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit / License
No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit (CNP) |
|||
WA7: GW-RW0960-13 |
14/01/2014 (23:00) |
13/07/2014
(07:00) |
Expired |
WA4: GW-RW0006-14 |
19/01/2014(19:00) |
18/07/2014
(23:00) |
Cancelled on 10 July 2014 |
WA4B : GW-RW0008-14 |
10/01/2014(23:00) |
09/07/2014(07:00) |
Expired |
WA7: GW-RW0097-14 |
28/02/2014(19:00) |
27/08/2014(23:00) |
Valid |
P0-P68: GW-RS0122-14 |
18/02/2014(23:00) |
13/08/2014(07:00) |
Cancelled on 27 June 2014 |
P0-P68: GW-RS0123-14 |
18/02/2014(19:00) |
12/08/2014(23:00) |
Cancelled on 27 June 2014 |
Portion A: GW-RS0130-14 |
23/02/2014(19:00) |
22/08/2014(23:00) |
Valid |
P75-P80: GW-RS0264-14 |
01/04/2014 (19:00) |
27/07/2014 (07:00) |
Cancelled on 14 July 2014 |
P81-P82: GW-RS0344-14 |
11/04/2014(00:00) |
10/10/2014 (24:00) |
Valid |
P101-P113: GW-RS0485-14 |
21/05/2014(19:00) |
20/11/2014 (06:30) |
Valid |
P69-P74: GW-RS0556-14 |
30/05/2014(19:00) |
29/07/2014 (24:00) |
Expired |
P101-P113: GW-RS0576-14 |
06/06/2014(19:00) |
04/09/2014 (05:30) |
Valid |
P81-P114: GW-RS0583-14 |
06/06/2014(19:00) |
29/07/2014 (24:00) |
Expired |
P0 – P68: GW-RS0652-14 |
27/06/2014(19:00) |
30/09/2014 (24:00) |
Valid |
P110 – P114: GW-RS0668-14 |
03/07/2014(19:00) |
30/09/2014(07:00) |
Valid |
WA4: GW-RW0496-14 |
10/07/2014(19:00) |
01/01/2015(23:00) |
Valid |
WA7: GW-RW0509-14 |
14/07/2014(19:00) |
13/01/2015(07:00) |
Valid |
P75 – P80: GW-RW0703-14 |
14/07/2014(19:00) |
13/10/2014(07:00) |
Valid |
P69 – P74: GW-RW0785-14 |
30/07/2014(00:00) |
29/11/2014(07:00) |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste Disposal |
|||
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
A/C#
7015341 (Vessel
Disposal) |
26/05/2014 |
31/08/2014 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-125 |
05/02/2014 |
04/08/2014 |
Valid |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/15-037 |
19/06/2014 |
18/07/2014 |
Expired |
Dumping of dredged sediment of Category L and Category M Passing Biological Screening at 二洲島 南疏浚物臨時性海洋傾倒區 EP/MD/14-133 |
11/07/2014 |
18/07/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/15-064 |
28/07/2014 |
27/08/2014 |
Valid |