1.
This is the 19th monthly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works conducted in August
2014.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting month is listed
in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Month
Parameter(s) |
Date(s) |
1-hr TSP Monitoring |
6th, 12th,
18th , 22nd and 28th
August 2014. |
24-hr TSP Monitoring |
6th, 12th,
18th , 22nd and 28th
August 2014. |
Noise Monitoring |
7th , 13th
, 19th and 25th
August 2014 |
Water Quality Monitoring |
1st, 4th,
6th, 8th, 11th, 13th, 15th,
19th, 21th , 23th, 25th, 27th
and 29th August 2014 |
22nd and 27th August 2014 |
|
Additional Land-based Dolphin Behaviour
and Movement Monitoring |
22nd and 27th August 2014 |
Environmental Site Inspection |
5th, 12th,
19th and 29th August 2014 |
Archaeological Site Inspection |
(1) N/A |
Remark:
(1)
No archaeological site inspection
was conducted in the reporting month.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting month is tabulated in Table
II.
Table II Summary
Table for Events Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
7 |
1 |
0 |
0 |
1-hour TSP Monitoring
4.
All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
5.
All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit Level exceedance was
recorded.
Water Quality
7.
All water quality monitoring was conducted as scheduled in the reporting
month. There are seven Action Level and one Limit Level exceedances
for suspended solids were recorded. No Action/Limit Level exceedance
for dissolved oxygen and turbidity were recorded.
8.
According to the investigation, no pollution discharge was observed from
the site and no marine construction works were conducted in vicinity of
monitoring station in which exceedance was recorded.
In addition, sediment plume due to natural fluctuation of shallow water was
observed. Therefore, the exceedances are considered
not due to the Contract.
Complaint Log
9.
One environmental complaint was received in the reporting month.
Notification of Summons and Successful
Prosecutions
10.
No notification of summons and successful prosecution was received in
the reporting month.
11.
This report has been developed in compliance with the reporting
requirements for the subsequent monthly EM&A Report as required by the
EM&A Manual for Hong Kong Link Road (EM&A Manual).
12.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading of rebar materials
Marine
Viaduct (P0 to P80)
RCD Method:
Piling
works
Installation
of piling jackets
Dismantling
of piling jackets
Pile
excavation and casing installation
Inter-face
tests, full depth coring test and sonic test
Grouting
works
Kelly
Method:
Installation
of temporary piles, platforms permanent casing
Removal of
piling platform and temporary pile extraction
Pile
excavation
Inter-face
tests, full depth coring test and sonic test
Pile Cap
Construction:
Installation
of precast cap shells
Concreting
Kingpost
installation and associated steel welding works
Concreting
trimming
Works with
Cofferdam:
Installation
of waling strut
Installation
of sheet pile
Installation
of temporary working platform
Installation
of shear pin
Installation
of bored pile casing
Excavation
works and casting of concrete plug
Dewatering
works and sealing works
Additional
welding
Column
Construction:
Lifting
works
Lift
concreting
Pier head
works
Pier head
concreting
Column
insert installation, mobilization and temporary works
Deck
Erection:
Lifting
frame fabrication in Dongguan
Modification
works to the
Segment
Unloading Frame (SUF) in Portion C
Delivery
and assembly of
Launching
Gantry 2 and Lifting
Frame 2 at
River Trade Terminal
Winches
delivery and commissioning
Trial
assembly of Lifting Frame 1
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
Pile
construction
Pouring of
column
Piling
platform formation
Steel
fixing works and formwork erection
Blinding
concrete for scaffolding works
Dismantling
of steel bracket system
Erection of
steel bracket system