2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      Pile construction is in progress at P81, P82 & P83 and 4 piles were concreted in this reporting period.

(b)     Completion of the remaining 2 predrilling hole at P81.

(c)      Total 97 pours for column were completed with 15 pours in this reporting period; 33 columns was completed to top level (15 gridlines - P96, P97 and P102 to P114).

(d)     Formation of piling platform at P81 was completed.

(e)      Pre-bored for sheet pile for cofferdam construction at P84 commenced.

(f)      Seawall block coring and breaking at P82L & P83L for bored piling works commenced.

(g)     Portal P103 was concreted on 26 August 2014.

(h)     Portal P111 & P113 falsework dismantling is in progress.

(i)       Portal P104 erection of formwork is in progress.

(j)       Portal P114 falsework erection is in progress.

(k)     Portal P108 steel girders, cross beams and planking erection are in progress.

(l)       Portal P107 and P106 construction of concrete footings for plate girder supports are in progress

 

Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of the temporary platform for piling works at P68 was suspended since 10 June 2014.

(b)  Piling works at P69 was suspended on 12 July (9 out of 12 piles already completed).

(c)  Forming the formation for the temporary platform for piling works at P75 was suspended on 22 July 2014.

(d)  Piling jackets were installed at P17 and P80.

(e)  Piling jackets were dismantled at P79 and P13.

(f)  Pile excavations and casing installation were in progress at P13, P17, P32, P62, P63, P67, P79 and P80  with 26 nos. piles concreted in the reporting period.

(g)  Inter-face coring tests were carried out at P58, P59, P62, P63 and P67.

(h)   Full depth coring test was carried at P27.

(i)    Sonic tests were carried out at P58, P59, P62 and P67.

(j)    Grouting works were carried out at P77.

 

Kelly Method:

(i)    Installation of temporary piles were carried out at P1, P3 and P12.

(j)    Installation of platforms were carried out at P3 and P12.

(k)   Installation of permanent casing were carried out at P3 and P12.

(l)  Piling platform removal and temporary pile extraction were carried out at P11, P17 and P18.

(m) Pile excavation by Kelly method are in progress at P2, D19, P21 and P30 with 13 piles concreted in the reporting period.

(n)  Inter-face core tests were carried out at P17 & P33.

(o)   Full depth coring was carried out at P17-L1.

(p)   Sonic tests were carried out at P17, P18 & P33.

(q)   Toe grouting preparation works were carried out at P4 & P16.

Pilecap Construction:

(a)  10 precast cap shells were installed at P19, P50, P60, P65 & P66.

(b)   Stage 1 concreting was completed at P20L, P37, P38, P41 & P52.

(c)  Stage 1 works is in progress at P36.

(d) Stage 2 concreting was completed at P39, P41, P49, P51 & P52.

(e)  Stage 2 works is in progress at P20L, P38 & P52.

(f)   Kingpost installation and associated steel welding works for precast shell installation are in progress at P19, P50, P60, P65 & P66.

(g)   Concrete trimming and advanced trimming (inside casing) works were carried out at P18, P19, P20, P36, P37, P38, P52, P61 & P64.

(h)  Submerged pilecap works with cofferdam:

-         P70L: Installation of sheet-pile completed. Removal of temporary working platform is in progress.

-         P70R: Installation of sheet-pile completed. Installation of shear pin is in progress.

-         P71L: Additional installation of waling strut at 3rd layer completed Dewatering to the bottom of cofferdam is on-going. Cleaning of concrete plug for casting of blinding layer is in progress.

-                     P71R: Casting of concrete plug completed and curing is in progress.

-         P72L: Installation of sheet-pile completed. Removal of temporary working platform is in progress.

-        P72R: Installation of waling strut at 2nd layer is in progress.

-         P73L: Excavation is in progress.

-                     P73R: Installation of waling strut at 2nd layer substantially completed.

-         P74L: Installation of shear pin completed.

-         P74R: Installation of shear pin is in progress.

-         P76: Cutting of bore pile casing completed. Installation of temporary working platform is in progress.

-         P77: Cutting of bore pile casing completed. Installation of temporary working platform is in progress.

-         P78L: Installation of sheet pile is in progress.

-         P78R: Installation of sheet pile is in progress.

 

Column Construction

(a)    1st lift works in progress at P39, P40, P42, P43, P44L, P45, P48R and P49.

(b)   1st lift concrete was poured at P40, P42R, P44, P45 and P49.

(c)    2nd lift works in progress at P45 and P49.

(d)   2nd lift concreting was poured: nil.

(e)    Pier head works in progress at: P46 and P48L.

(f)    Pier head concrete was poured at P46 and P48L.

(g)   Demolishing works at P48-R 1st lift was completed & reconstruction in progress.

(h)   Columns’ insert installation, mobilization and temporary works were carried out at P51.

 

Deck Erection

(a)   Preparatory works for segment erection:

-         Off-site fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of all 6 sets of Lifting Frames 2 (LF2).

-         Segment Unloading Frame (SUF) was completed awaiting load test;

-         Assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches have been tested.

-         Launching Gantry 1 (LG1) assembly continues at Portion C with all components on site.

-         Assembly and erection of LF2 continues with 2 frames having been erected at P109 awaiting load test, 2 frames are assembled at RTT and 2 frames are assembled at WA4.

-         Trial assembly of Lifting Frames 1 (LF1) has been commenced in Dongguan with delivery to site will commence before end of August.

-         8 winches have been delivered to Hong Kong;

-         Preparatory works have commenced for Segments on Pier (SOP) erection at P47.

-         Preparatory works have commenced for Precast Column erection at P43.

Precast Segment

(a)   Progress for mould assembly:

Type of Segment

Number of Segment

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

3

2 CPA complete, CPB in progress

DT

1

Completed

(b)  151 segments were cast in this reporting period.

(c) Cumulative total 967 segments cast.

(d)  The first 4 segments were loaded onto a barge and are awaiting Customs and other necessary clearances.

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

4

41

CP2

2

9

CP4

1

5

 

Ground Investigations

-       1 drill rig was working during this period on micro platform and land section.

-       Predrilling works were carried out at P1 & P81 in this reporting period.

-       3 nos. of pre-drills were completed in this reporting period. Total 725 piles have completed predrills (including GI used as predrill).

-       Total 115 gridline (100%) out of 115 were completed for pre-drilling. Additional predrills are required for the friction piles at P1 and P7 for SPT tests, these shall be done from the piling platforms.

-       Total 112 gridlines for first issue of Founding Level Proposals were submitted. 2 no. was submitted in this reporting period.

Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

WA7: GW-RW0097-14

28/02/2014(19:00)

27/08/2014(23:00)

Cancelled on 14 July 2014

Portion A: GW-RS0130-14

23/02/2014(19:00)

22/08/2014(23:00)

Expired

P81-P82: GW-RS0344-14

11/04/2014(00:00)

10/10/2014 (24:00)

Valid

P101-P113: GW-RS0485-14

21/05/2014(19:00)

20/11/2014 (06:30)

Valid

P101-P113: GW-RS0576-14

06/06/2014(19:00)

04/09/2014 (05:30)

Valid

P0 – P68: GW-RS0652-14

27/06/2014(19:00)

30/09/2014 (24:00)

Cancelled on 28 August 2014

P110 – P114: GW-RS0668-14

03/07/2014(19:00)

30/09/2014(07:00)

Valid

WA4: GW-RW0496-14 

10/07/2014(19:00)

01/01/2015(23:00)

Valid

WA7: GW-RW0509-14

14/07/2014(19:00)

13/01/2015(07:00)

Valid

P75 – P80: GW-RW0703-14

14/07/2014(19:00)

13/10/2014(07:00)

Valid

P69 – P74: GW-RW0785-14

30/07/2014(00:00)

29/11/2014(07:00)

Valid

P81 – P114: GW-RW0812-14

05/08/2014(19:00)

04/11/2014(23:00)

Valid

Portion A: GW-RW0838-14

23/08/2014(19:00)

22/02/2015(23:00)

Valid

P0 – P68: GW-RS0855-14

27/08/2014(19:00)

26/11/2014(24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7015341      

(Vessel Disposal)

26/05/2014

31/08/2014

Expired

A/C# 7015341      

(Vessel Disposal)

11/08/2014

30/11/2014

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/14-125

05/02/2014

04/08/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment

EP/MD/15-064

28/07/2014

27/08/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/15-078

06/08/2014

31/01/2015

Valid