2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities
(HKBCF) situated at the north eastern waters of the Hong Kong International
Airport, opening a new and direct connection route between Hong Kong, Macao and
the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B)
based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The
environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September
2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning works of
affected existing facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key
Contacts of the Contract
|
Party |
Position |
Position |
Phone No. |
Fax No. |
|
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
|
Mr. Colin Meadows |
3767 5801 |
|||
|
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
|
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
|
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
|
24-hour Hotline |
-- |
6898 6161 |
-- |
|
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10 The major site activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a)
Pile
construction is in progress at P81, P82 & P83 and 4 piles were concreted in
this reporting period.
(b)
Completion
of the remaining 2 predrilling hole at P81.
(c)
Total 97 pours for column were completed with 15
pours in this reporting period; 33 columns was completed
to top level (15 gridlines - P96, P97 and P102 to P114).
(d)
Formation
of piling platform at P81 was completed.
(e)
Pre-bored for sheet pile for cofferdam
construction at P84 commenced.
(f)
Seawall
block coring and breaking at P82L & P83L for bored piling works commenced.
(g)
Portal
P103 was concreted on 26 August 2014.
(h)
Portal
P111 & P113 falsework dismantling is in progress.
(i)
Portal
P104 erection of formwork is in progress.
(j)
Portal
P114 falsework erection is in progress.
(k)
Portal
P108 steel girders, cross beams and planking erection are in progress.
(l)
Portal
P107 and P106 construction of concrete footings for plate girder supports are
in progress
Marine
Viaduct (P0 to P80)
RCD Method:
(a) Construction of the temporary platform for
piling works at P68 was suspended since 10 June 2014.
(b) Piling works at P69 was suspended on 12
July (9 out of 12 piles already completed).
(c) Forming the formation for the temporary
platform for piling works at P75 was suspended on 22 July 2014.
(d) Piling jackets were installed at P17 and
P80.
(e) Piling jackets were dismantled at P79 and
P13.
(f) Pile excavations and casing installation
were in progress at P13, P17, P32, P62, P63, P67, P79 and P80 with 26 nos. piles concreted in
the reporting period.
(g) Inter-face coring tests were carried out
at P58, P59, P62, P63 and P67.
(h) Full
depth coring test was carried at P27.
(i) Sonic tests were carried out
at P58, P59, P62 and P67.
(j) Grouting works were carried out at P77.
Kelly Method:
(i) Installation of
temporary piles were carried out at P1, P3 and P12.
(j) Installation
of platforms were carried out at P3 and P12.
(k) Installation of permanent casing were
carried out at P3 and P12.
(l) Piling platform removal and temporary
pile extraction were carried out at P11, P17 and P18.
(m) Pile excavation by
Kelly method are in progress at P2, D19, P21 and P30
with 13 piles concreted in the reporting period.
(n) Inter-face core tests were carried out
at P17 & P33.
(o) Full depth coring was carried out at P17-L1.
(p) Sonic tests were carried out at P17, P18 & P33.
(q) Toe grouting preparation works were carried out at P4
& P16.
Pilecap Construction:
(a) 10 precast cap
shells were installed at P19, P50, P60, P65 & P66.
(b) Stage 1 concreting was completed at P20L, P37, P38, P41 & P52.
(c) Stage
1 works is in progress at P36.
(d) Stage 2 concreting was completed at P39, P41, P49, P51 & P52.
(e) Stage 2 works is in progress at P20L,
P38 & P52.
(f) Kingpost installation and associated steel welding works for
precast shell installation are in progress at P19, P50, P60, P65
& P66.
(g) Concrete trimming and advanced trimming (inside casing) works
were carried out at P18, P19, P20, P36, P37, P38, P52, P61
& P64.
- P70L: Installation
of sheet-pile completed. Removal of temporary working platform is in progress.
- P70R:
Installation of sheet-pile completed. Installation of shear pin is in progress.
- P71L:
Additional installation of waling strut at 3rd layer completed Dewatering to
the bottom of cofferdam is on-going. Cleaning of concrete plug for casting of
blinding layer is in progress.
- P71R:
Casting of concrete plug completed and curing is in progress.
- P72L:
Installation of sheet-pile completed. Removal of temporary working platform is
in progress.
- P72R:
Installation of waling strut at 2nd layer is in progress.
- P73L:
Excavation is in progress.
- P73R:
Installation of waling strut at 2nd layer substantially completed.
- P74L: Installation of
shear pin completed.
- P74R: Installation of
shear pin is in progress.
- P76: Cutting of bore pile
casing completed. Installation of temporary working platform is in progress.
- P77: Cutting of bore pile
casing completed. Installation of temporary working platform is in progress.
- P78L: Installation of
sheet pile is in progress.
- P78R: Installation of
sheet pile is in progress.
Column Construction
(a) 1st lift works in progress at P39, P40, P42, P43, P44L, P45, P48R
and P49.
(b) 1st lift concrete was poured at P40, P42R, P44, P45 and P49.
(c) 2nd lift works in progress at P45 and P49.
(d) 2nd lift concreting was poured: nil.
(e) Pier head works in progress at: P46 and P48L.
(f) Pier head concrete was poured at P46 and P48L.
(g) Demolishing works at P48-R 1st lift was completed &
reconstruction in progress.
(h) Columns’ insert installation, mobilization and temporary works were
carried out at P51.
Deck Erection
(a) Preparatory works for
segment erection:
- Off-site fabrication of the
first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of all 6 sets of Lifting Frames 2 (LF2).
- Segment Unloading Frame
(SUF) was completed awaiting load test;
- Assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches
have been tested.
- Launching Gantry 1 (LG1) assembly continues
at Portion C with all components on site.
- Assembly and erection of
LF2 continues with 2 frames having been erected at P109 awaiting load test, 2
frames are assembled at RTT and 2 frames are assembled at WA4.
- Trial assembly of Lifting Frames 1 (LF1) has been
commenced in Dongguan with delivery to site will
commence before end of August.
- 8 winches have been delivered
to Hong Kong;
- Preparatory works have
commenced for Segments on Pier (SOP) erection at P47.
- Preparatory works have
commenced for Precast Column erection at P43.
Precast Segment
(a) Progress for mould assembly:
|
Type of Segment |
Number of Segment |
Status |
|
A |
10 |
Completed (including 2
nos. SPO) |
|
B |
1 |
Completed |
|
D |
2 |
Completed |
|
E |
4 |
Completed |
|
CH1 |
2 |
Completed |
|
CH2 |
2 |
Completed |
|
CH3 |
2 |
Completed |
|
CH4 |
2 |
Completed |
|
CH5 |
2 |
Completed |
|
CP (long span SOP) |
3 |
2 CPA complete, CPB in
progress |
|
DT |
1 |
Completed |
(b) 151 segments were cast in this reporting
period.
(c) Cumulative total 967 segments cast.
(d) The first 4 segments were loaded onto a barge
and are awaiting Customs and other necessary clearances.
Precast Concrete Shell Casting
(a)
Summary of precast shell cast in the precast yard:
|
Type of Shell |
Number of Precast Shell Cast in this
reporting period |
Cumulative No. of Precast Shell Completed
(up to 28th of each month) |
|
CP1 |
4 |
41 |
|
CP2 |
2 |
9 |
|
CP4 |
1 |
5 |
Ground Investigations
-
1 drill rig was working during this period on micro
platform and land section.
-
Predrilling works were carried out at P1 & P81 in this
reporting period.
-
3 nos. of pre-drills were completed in this
reporting period. Total 725 piles have completed predrills
(including GI used as predrill).
-
Total 115 gridline (100%) out of 115 were completed
for pre-drilling. Additional predrills are required
for the friction piles at P1 and P7 for SPT tests,
these shall be done from the piling platforms.
-
Total 112 gridlines for first issue of Founding
Level Proposals were submitted. 2 no. was submitted in this reporting period.
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
|
Permit / License
No. |
Valid
Period |
Status |
|
|
From |
To |
||
|
Environmental Permit (EP) |
|||
|
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
|
Consruction Noise Permit (CNP) |
|||
|
WA7: GW-RW0097-14 |
28/02/2014(19:00) |
27/08/2014(23:00) |
Cancelled on 14 July 2014 |
|
Portion A: GW-RS0130-14 |
23/02/2014(19:00) |
22/08/2014(23:00) |
Expired |
|
P81-P82: GW-RS0344-14 |
11/04/2014(00:00) |
10/10/2014 (24:00) |
Valid |
|
P101-P113: GW-RS0485-14 |
21/05/2014(19:00) |
20/11/2014 (06:30) |
Valid |
|
P101-P113: GW-RS0576-14 |
06/06/2014(19:00) |
04/09/2014 (05:30) |
Valid |
|
P0 – P68: GW-RS0652-14 |
27/06/2014(19:00) |
30/09/2014 (24:00) |
Cancelled on 28 August 2014 |
|
P110 – P114: GW-RS0668-14 |
03/07/2014(19:00) |
30/09/2014(07:00) |
Valid |
|
WA4: GW-RW0496-14 |
10/07/2014(19:00) |
01/01/2015(23:00) |
Valid |
|
WA7: GW-RW0509-14 |
14/07/2014(19:00) |
13/01/2015(07:00) |
Valid |
|
P75 – P80: GW-RW0703-14 |
14/07/2014(19:00) |
13/10/2014(07:00) |
Valid |
|
P69 – P74: GW-RW0785-14 |
30/07/2014(00:00) |
29/11/2014(07:00) |
Valid |
|
P81 – P114: GW-RW0812-14 |
05/08/2014(19:00) |
04/11/2014(23:00) |
Valid |
|
Portion A: GW-RW0838-14 |
23/08/2014(19:00) |
22/02/2015(23:00) |
Valid |
|
P0 – P68: GW-RS0855-14 |
27/08/2014(19:00) |
26/11/2014(24:00) |
Valid |
|
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
|
345773 |
N/A |
Receipt acknowledged by EPD |
|
|
Billing Account for Construction Waste Disposal |
|||
|
A/C# 7015341 (Construction
Site) |
11/06/2012 |
N/A |
Valid |
|
A/C#
7015341 (Vessel
Disposal) |
26/05/2014 |
31/08/2014 |
Expired |
|
A/C#
7015341 (Vessel
Disposal) |
11/08/2014 |
30/11/2014 |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
|
Effluent Discharge License under Water Pollution
Control Ordinance |
|||
|
WA6A(DCVJV site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
|
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
|
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
|
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
|
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
|
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
|
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
|
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
|
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
|
Marine Dumping Permit |
|||
|
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/14-125 |
05/02/2014 |
04/08/2014 |
Expired |
|
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D
and Type 2) marine sediment EP/MD/15-064 |
28/07/2014 |
27/08/2014 |
Expired |
|
Dumping of Phase 1, 2a, 2b, 2c and 2d (Type
1-Open Sea Disposal) marine sediment EP/MD/15-078 |
06/08/2014 |
31/01/2015 |
Valid |