Table 7.1           Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

02/09/2014

To clear the dusty materials at the ro-ro barge at P63.

Rectification/improvement was observed during the follow-up audit session on 10 September 2014.

10/09/2014

Properly deploy the silt curtain at P98.

Rectification/improvement was observed during the follow-up audit session on 17 September 2014.

10/09/2014

Provide sedimentation facilities for the muddy water from wheel washing at the exit near P92.

Rectification/improvement was observed during the follow-up audit session on 17 September 2014.

26/09/2014

To repair the silt curtain which has sunk into the water at P71

Rectification/improvement was observed during the follow-up audit session on 30 September 2014.

Ecology

10/09/2014

To remove the construction waste/materials at near the tress at P102, P100 and 92.

Rectification/improvement was observed during the follow-up audit session on 17 September 2014.

Air Quality

02/09/2014

Properly check the exhaust of concrete pump to avoid dark smoke emission.

Rectification/improvement was observed during the follow-up audit session on 10 September 2014.

10/09/2014

Provide water spray for the surface of ro-ro barge to avoid dust generation at southeast Quay.

Rectification/improvement was observed during the follow-up audit session on 17 September 2014.

Noise

02/09/2014

Provide acoustic decoupling measure for the air compressor at barge at P64.

Rectification/improvement was observed during the follow-up audit session on 10 September 2014.

Waste / Chemical Management

02/09/2014

To plug the drip tray for chemical containers at P47.

Rectification/improvement was observed during the follow-up audit session on 10 September 2014.

10/09/2014

Clear the oil leakage as chemical waste and repair the equipment properly at P100.

Rectification/improvement was observed during the follow-up audit session on 17 September 2014.

17/09/2014

To properly seal the holes of the drip tray for generator at pier 43 and 47.

Rectification/improvement was observed during the follow-up audit session on 26 September 2014.

30/9/2014

Provide oil absorbing sheets at underneath of the wire on the barge at P43 to avoid oil spillage.

Rectification/improvement was observed during the follow-up audit session on 7 October 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

30/09/2014

N/A(1)

N/A(1)

Remark:      N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.