Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

10/10/2014

Clear the floating rubbish inside the cofferdam at P73.

Rectification/improvement was observed during the follow-up audit session on 21 October 2014.

10/10/2014

Properly maintain the silt curtain at P75 to avoid the gap.

Rectification/improvement was observed during the follow-up audit session on 21 October 2014.

31/10/2014

Clear the broken sand bags at the barge at P27.

Rectification/improvement was observed during the follow-up audit session on 4 November 2014.

Ecology

21/10/2014

Clear the accumulated wastes at near the trees at near P93.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Air Quality

07/10/2014

Provide proper watering for the dry exposed area at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

Noise

21/10/2014

Provide noise emission label for the air compressor at P109.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Waste / Chemical Management

07/10/2014

Clear the accumulated waste at the material skip regularly at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

07/10/2014

Clear the wastes at the sedimentation tank to ensure it function properly at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

07/10/2014

Clear the oil leakage and painting materials at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

21/10/2014

Clear the general refuse and construction wastes at P98.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

07/10/2014

To display the Environmental Permit at the exit of Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.