2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A
and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013
respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued
on 5 September 2013.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
|
Party |
Position |
Position |
Phone
No. |
Fax
No. |
|
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
|
Mr. Colin Meadows |
3767 5801 |
|||
|
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
|
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
|
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
|
24-hour Hotline |
-- |
6898 6161 |
-- |
|
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P81 to P82 and 4 piles were concreted in this reporting
period.
(b) Total 122 pours
for column were completed with 12 pours
in this reporting period; 44 columns
was completed to top level (21
gridlines - P93 and P95 to P114).
(c) Pre-bored for sheet
pile for cofferdam construction at P84 was
completed. Excavation and waling installation is in progress.
(d) Pre-bored for sheet pile for
cofferdam construction at P83R commenced.
(e) Sewage diversion at P83 commenced.
(f) Portal P103 was concreted on 26
August 2014. Dismantling of steel girders and brackets was completed.
(g) Portal P111 & P113 falsework dismantling was completed. Dismantling of falsework is in progress.
(h) Portal P114 was concreted on 28
October 2014.
(i) Portal P108 was concreted on 25
October 2014.
(j) Portal P107 and P106 erection of
formwork is in progress.
(k) Portal P102 erection of side
formwork is in progress.
(l) Portal P101 erection of side
formwork is in progress.
(m) Portal P97 erection of cross
beams is in progress.
(n) Portal P100 erection of falsework and girders is in progress.
(o) Portal P99 foundation work for falsework supports is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction
of the temporary platform for piling works at P68 was suspended since 10 June
2014. The Contractor removed the rockfill platform
followed the SO instruction.
(b) Piling works
at P69 was suspended on 12 July 2014 (9 out of 12 piles already completed).
(c) Remobilization for P75’s works started on 25 September 2014. Excavation
by grabbing and chiseling is in progress.
(d) Piling
jackets were installed at P5, P9, P10, P18 and P23.
(e) Piling
jackets were dismantled at P13, P15, P20, P25, P32, P63, P67 and P80.
(f) Pile
excavations and casing installation were in progress at P5, P9, P15, P18, P20,
P23, P31 and P80 with 20 nos. piles concreted in the reporting period.
(g) Inter-face
coring tests were carried out at P31, P32, P55, P56, P79 and P80.
(h) No Full depth coring test was carried during the reporting period.
(i) Sonic tests were carried out at P28, P31, P32, P55, P56 and P80.
(j) Grouting works were carried out
at P14, P27, P28, P29, P32, P54, P58 and P67.
Kelly Method:
(k) Installation of temporary piles were carried out at P2 and P7.
(l) Installation of platforms were carried out at P7.
(m) Installation
of permanent casing were carried out at P7.
(n) Piling platform
removal and temporary pile extraction were carried out at P2 and P30.
(o) Pile excavation by Kelly method are in progress at P1, P2, P3, P7
& P12 and 8 piles concreted in the reporting period.
(p) All end bearing
piles by Kelly Method has been completed.
(q) Inter-face core tests were carried out at
P21.
(r) Full depth coring was carried out at P30-R1.
(s) No sonic tests were carried out
in this reporting period.
(t) Toe grouting works were carried
out at P4 and P16.
Disposal
(a)
2 trips of inert
materials & 1 trip of inert materials to TM38 & HKLR03 Project
respectively, 3 trips of Type I materials & 1 trip of Type II materials
were disposed to HK open sea mud pits. 3 trips of marine mud to Cross Border
were disposed.
Pilecap
Construction:
(a) 6 precast cap shells were installed at P18, P62 & P63.
(b) Stage 1 concreting was completed
at P19, P33, P34, P35, P61 & P64.
(c) Stage 1
works is in progress at P19, P33, P34, P35, P61, P62
& P64.
(d) Stage 2 concreting was completed
at P19, P60, P65 & P66.
(e) Stage 2
works is in progress at P19, P34, P35, P60, P61, P64, P65
& P66.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P18, P29, P62, P63
& P67.
(g) Concrete trimming and advanced
trimming (inside casing) works were carried out at P17, P27, P28, P29, P59, P63 & P67.
- P70L: Excavation is in progress.
- P70R: Excavation is in progress.
- P71L: Concreting works of pile cap was
completed on 6-Oct-14.
- P71R: Additional concrete plug and 3rd
layer of waling & strut were completed. Dewatering, cleaning and drainage
works before casting of blinding layer is in progress.
- P72L: Installation of waling strut at 2nd
layer is substantially completed. Additional grouting works was carried out.
- P72R:
Excavation is substantially completed. Sheet pile cleaning by divers is in
progress;
- P73L:
Installation of 3rd layer of waling & strut was completed. Dewatering,
cleaning and drainage works before casting of blinding layer is in progress;
- P73R:
Concrete Plug was casted on 10-Oct-14. Installation of 3rd layer of waling
& strut was completed. Dewatering is in progress;
- P74L:
Installation of 2nd layer of waling & strut in progress;
- P74R:
Installation of shear pin was completed;
- P76L:
Installation of temporary working platform was completed;
- P76R:
Installation of sheet pile is in progress;
- P77L:
Installation of sheet pile is in progress;
- P77R:
Installation of sheet pile is in progress;
- P78L:
Installation of 1st & 2nd waling & strut were completed;
- P78R:
Installation of 1st & 2nd waling & strut were completed.
In-situ Column
Construction
(a) 1st lift works is in progress at P36, P37, P38 and P66.
(b) 1st lift concrete was poured at P37 & P38.
(c) 2nd lift works is in progress at P48-R, P51 and P52.
(d) 2nd lift concreting was poured: P48-R, P51 and P52.
(e) Pier head works is in progress at: P45, P48-R and P52.
(f) Pier head concreting : Nil in this reporting
period.
Precast Column
Erection
(g) The initial Precast Column sections have been installed and concreted on
P43 and P44. The 2nd batch of precast column delivery is in progress.
In-situ Double Blade
Column Construction
(h) 1st lift works is in progress at P20 and P71;
Deck Erection
(a) Setting up of Equipment:
- Off-site fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of
all 6 sets of Lifting
Frames 2 (LF2), Steelwork for the 4th
set of Lifting Frames is under fabrication with some deliveries having
commenced.
- Segment Unloading Frame (SUF) is fully operational;
- Assembly of Launching
Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches have been tested.
- Launching Gantry 1 (LG1) assembly continues
at Portion C with all components on site, Lower
Cross Beam (LCB)’s erected and the first 50m section of truss erected.
- An accident occurred with the collapse of the 4th set of LF2
at Pier P109R on the morning of 19th October 2014. All works on LF2
at P109 have been suspended pending for Labour Department Investigation.
- A total of 10 segments have been erected on
P109, 4 segments on P110 and 4 SOP segments on P47. Segments on Pier (SOP) segments
for P46 are on site awaiting erection after completion of temporary works.
Precast Segment
(a) Progress for mould assembly:
|
Type of Segment |
Number of Segment |
Status |
|
A |
10 |
Completed (including 2 nos. SPO) |
|
B |
1 |
Completed |
|
D |
2 |
Completed |
|
E |
4 |
Completed |
|
CH1 |
2 |
Completed |
|
CH2 |
2 |
Completed |
|
CH3 |
2 |
Completed |
|
CH4 |
2 |
Completed |
|
CH5 |
2 |
Completed |
|
CP (long span SOP) |
3 |
2 CPA complete, CPB in progress |
|
DT |
1 |
Completed |
|
E/EV |
2 |
Under fabrication |
(b) 119 segments were cast in this reporting
period.
(c) Cumulative
total 1176 segments cast.
(d) 48 segments have been delivered to site.
(e) Piling works have commenced for the precast yard extension for both
additional moulds and segment storage.
(f) Transportation of segments to an off-yard storage at nearby area in Zhongshan has commenced.
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
|
Type of Shell |
Number of
Precast Shell Cast in this reporting period |
Cumulative No.
of Precast Shell Completed (up to 28th of each month) |
|
CP1 |
5 |
50 |
|
CP2 |
Completed |
12 |
|
CP4 |
2 |
8 |
|
CP5 |
0 |
2 |
|
CP1 |
5 |
50 |
Ground Investigations
- 4 drill rigs were mobilized for
additional predrilling works at P2 (compensation pile), P7 (additional SPT’s)
and D18 (pile moved).
- 5 nos. of
additional pre-drills were
completed in this reporting period. All 725 piles have completed predrills (including GI
used as predrill).
- Total 115
gridline (100%) out of
115 were completed for pre-drilling. Additional predrills are required for the
friction piles at P1 and P7 for SPT tests and these shall be carried out on the
piling platforms.
- Total 115
gridlines for first issue of Founding Level Proposals were submitted. 2 no. was submitted in this reporting period.
Status of Environmental Licences, Notification and Permits
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
|
Permit
/ License No. |
Valid
Period |
Status |
|
|
From |
To |
||
|
Environmental Permit (EP) |
|||
|
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
|
Consruction Noise Permit
(CNP) |
|||
|
P81-P82: GW-RS0344-14 |
11/04/2014 (00:00) |
10/10/2014 (24:00) |
Expired |
|
P101-P113: GW-RS0485-14 |
21/05/2014 (19:00) |
20/11/2014 (06:30) |
Valid |
|
WA4: GW-RW0496-14 |
10/07/2014 (19:00) |
01/01/2015 (23:00) |
Valid |
|
WA7: GW-RW0509-14 |
14/07/2014 (19:00) |
13/01/2015 (07:00) |
Valid |
|
P69 – P74: GW-RW0785-14 |
30/07/2014 (00:00) |
29/11/2014 (07:00) |
Valid |
|
P81 – P114: GW-RW0812-14 |
05/08/2014 (19:00) |
04/11/2014 (23:00) |
Valid |
|
Portion A: GW-RW0838-14 |
23/08/2014 (19:00) |
22/02/2015 (23:00) |
Valid |
|
P0 – P68: GW-RS0855-14 |
27/08/2014 (19:00) |
26/11/2014 (24:00) |
Valid |
|
P101 – P113: GW-RS0903-14 |
05/09/2014 (19:00) |
04/12/2014 (05:30) |
Valid |
|
P75 – P80: GW-RS0924-14 |
10/09/2014 (19:00) |
09/12/2014 (24:00) |
Valid |
|
P81 – P82: GW-RS1064-14 |
11/10/2014 (00:00) |
10/04/2015 (24:00) |
Valid |
|
P110 – P114: GW-RS1126-14 |
16/10/2014 (19:00) |
30/11/2014 (07:00) |
Valid |
|
P0 – P68: GW-RS1163-14 |
23/10/2014 (19:00) |
22/01/2015 (24:00) |
Valid |
|
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
|
345773 |
N/A |
Receipt acknowledged by EPD |
|
|
Billing Account for Construction Waste
Disposal |
|||
|
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
|
A/C# 7015341 (Vessel Disposal) |
11/08/2014 |
30/11/2014 |
Valid |
|
Registration of Chemical Waste Producer |
|||
|
WPN 5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
|
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
|
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
|
WA6B (SOR site office): WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
|
WA3: WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
|
Portion C: WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
|
Portion A: WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
|
WA4B: WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
|
WA7: WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
|
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
|
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
|
Marine Dumping Permit |
|||
|
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1-Open Sea Disposal) marine sediment EP/MD/15-078 |
06/08/2014 |
31/01/2015 |
Valid |
|
Cross-border dumping of dredged sediment
of Category L and Category Mp at Erchau Island in China EP/MD/15-081 |
10/09/2014 |
09/10/2014 |
Expired |
|
Dumping of
Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment at the South
of The Brothers EP/MD/15-119 |
01/10/2014 |
31/10/2014 |
Valid |
|
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-127 |
10/10/2014 |
09/11/2014 |
Valid |