7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 7th, 14th, 21st and 31st October 2014 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 31st October 2014. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 7th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 30th September 2014 and next inspection will be conducted in December 2014.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

10/10/2014

Clear the floating rubbish inside the cofferdam at P73.

Rectification/improvement was observed during the follow-up audit session on 21 October 2014.

10/10/2014

Properly maintain the silt curtain at P75 to avoid the gap.

Rectification/improvement was observed during the follow-up audit session on 21 October 2014.

31/10/2014

Clear the broken sand bags at the barge at P27.

Rectification/improvement was observed during the follow-up audit session on 4 November 2014.

Ecology

21/10/2014

Clear the accumulated wastes at near the trees at near P93.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Air Quality

07/10/2014

Provide proper watering for the dry exposed area at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

Noise

21/10/2014

Provide noise emission label for the air compressor at P109.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Waste / Chemical Management

07/10/2014

Clear the accumulated waste at the material skip regularly at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

07/10/2014

Clear the wastes at the sedimentation tank to ensure it function properly at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

07/10/2014

Clear the oil leakage and painting materials at Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

21/10/2014

Clear the general refuse and construction wastes at P98.

Rectification/improvement was observed during the follow-up audit session on 31 October 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

07/10/2014

To display the Environmental Permit at the exit of Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 October 2014.

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 6,588m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.