Table 7.1 Observations
and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
04/11/2014 |
Muddy water was
observed directly discharges into the sea at P84. The Contractor was reminded
to provide sedimentation tank to treat the muddy water before discharging
out. |
Rectification/improvement
was observed during the follow-up audit session on 3 December 2014. |
04/11/2014 |
Muddy water was also
observed directly discharges into the public gullies at P81 – P82. The
Contractor was reminded to provide proper mitigation measures to rectify
deficiency as soon as possible. |
Rectification/improvement
was observed during the follow-up audit session on 11 November 2014. |
|
04/11/2014 |
Concrete wastewater
was observed pumping out from the cofferdam into the sea at P73. The
Contractor was reminded to ensure all discharge from site comply with WPCO. |
Rectification/improvement
was observed during the follow-up audit session on 11 November 2014. |
|
11/11/2014 |
Muddy water was pumped
to the excavation pit before discharging to the sea at P84. The Contractor
was reminded to check this discharging procedure whether comply with WPCO. |
Rectification/improvement
was observed during the follow-up audit session on 3 December 2014. |
|
18/11/2014 |
Concrete debris was
observed at the deck of roro barges. The Contractor was reminded to clear it
as soon as possible. |
Rectification/improvement
was observed during the follow-up audit session on 28 November 2014. |
|
18/11/2014 |
Clear the accumulated
concrete waste at the waste skip properly (Kam Shun 338). |
Rectification/improvement
was observed during the follow-up audit session on 28 November 2014. |
|
28/11/2014 |
To avoid the gap at the
silt curtain at P71. |
Rectification/improvement
was observed during the follow-up audit session on 3 December 2014. |
|
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air Quality |
18/11/2014 |
Regular check the sprinkler
system for dust suppression at floating concrete plant to ensure it can
function properly. |
Rectification/improvement
was observed during the follow-up audit session on 28 November 2014. |
Noise |
04/11/2014 |
Provide noise emission
label for the hand held breaker at P73. |
Rectification/improvement
was observed during the follow-up audit session on 11 November 2014. |
Waste / Chemical Management |
11/11/2014 |
Properly clear
construction materials / wastes at near the trees at P89, P94 and P102. |
Rectification/improvement
was observed during the follow-up audit session on 18 November 2014. |
28/11/2014 |
Properly clear the
general refuse at the edge of barge at P71. |
Rectification/improvement
was observed during the follow-up audit session on 3 December 2014. |
|
28/11/2014 |
To plug the outlet of
drip tray at P71. |
Rectification/improvement
was observed during the follow-up audit session on 3 December 2014. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
N/A(2) |
N/A(2) |
N/A(2) |
Remark: N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.
N/A(2) No
archaeological site inspection was conducted in the reporting month.