2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Position

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Month

2.10     The major site activities undertaken in the reporting month included:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      Pile construction is in progress at P82 to P83 and 4 piles were concreted in this reporting period.

(b)     Total 139 pours for column were completed with 17 pours in this reporting period; 51 columns were completed to top level (25 gridlines - P90 to P114).

(c)      P84L water plugging and rebar fixing are in progress, P84R excavation is in progress.

(d)     Pre-bored for sheet pile for cofferdam construction at P83R was completed.

(e)      Pre-bored for sheet pile for cofferdam construction at P81R commenced.

(f)      Sewage diversion at P83 is in progress.

(g)     P83L piling work commenced.

(h)     Portal P107 and P106 were concreted on 17 and 21 November 2014 respectively. Dismantling of side formwork is in progress.

(i)       Portal P104 dismantling of steel bracket system was completed.

(j)       Portal P108 dismantling of falsework and steel bracket system is in progress.

(k)     Portal P114 dismantling of formwork was completed, temporary supporting jacks and nailing to be installed before falsework removal.

(l)       Portal P102 steel fixing is in progress and will be concreted on 29 November 2014.

(m)   Portal P101 steel fixing is in progress.

(n)     Portal P97 formwork erection was completed and steel fixing will be commenced.

(o)     Portal P98 erection of steel bracket system is in progress.

(p)     Portal P100 erection of formwork is in progress.

(q)     Portal P99 erection of falsework and steel beam supports are in progress.

(r)       Portal P96 portal foundation work is in progress.


Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of the temporary platform for piling works at P68 was suspended since 10 June 2014.

(b) Piling works at P69 was suspended on 12 July 2014 (9 out of 12 piles already completed).

(c) Remobilization for P75’s works started on 25 September 2014. Excavation by backhoe on flat top barge is on going.

(d)  Piling jackets were installed at P8.

(e)  Piling jackets were dismantled at P23 and D20.

(f)  Pile excavations and casing installation are in progress at P5, P9, P10 and P23 with 13 nos. piles concreted in the reporting period.

(g)  Inter-face coring tests were carried out at P23, P24, P25, P26 and P79.

(h)        Full depth coring test was carried at P79.

(i)    Sonic tests were carried out at P22, P24, P25, P26 and P79.

(j)    Grouting works were carried out at P53 and P79.

 

Kelly Method:

(k) Re-installation of platform was carried out at P2.

(l)         Installation of permanent casing was carried out at P2R1a.

(m)        Piling platform removal and temporary pile extraction were carried out at P16, P31 & P32.

(n)  Pile excavation by Kelly method is in progress at P1, & P7 and 9 piles concreted in the reporting period.

(o) All end-bearing piles by Kelly Method have been completed.

(p)  Inter-face core tests were carried out at P12 & P21.

(q) Full depth coring was carried out at P12-R3 & P30-R1.

(r) Sonic tests were carried out at P2, P3, P12, P19-L & P21.

(s)   Toe grouting works were carried out at P2 & P3.


Disposal from Marine Works

(a)    The disposals in this reporting period are shown in below table.

Disposal Location

No of Trip

Type of Materials

TM38

3

Inert Materials

TMCLK

2

Inert Materials

HK Open Sea Mud Pits

1

Type II Materials

Cross Boundary Disposal

5

Marine Mud

Pilecap Construction:

(a)  10 precast cap shells were installed at P27, P28, P29, P63 & P67.

(b)   Stage 1 concreting was completed at P18, P29, P62, P63 & P67.

(c)  Stage 1 works is in progress at P18, P29, P62, P63, P67 & P68.

(d) Stage 2 concreting was completed at P18L, P33, P34, P35, P61, P62 & P64.

(e)  Stage 2 works is in progress at P18L&R, P29, P33, P34, P35, P61, P62, P63 & P64.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P17, P27, P28, P30, P32 & P59.

(g) Concrete trimming and advanced trimming (inside casing) works were carried out at P14, P16, P17, P27, P28, P29, P30, P32, P53, P58, P59, P63, & P67.

(h)  Submerged pilecap works with cofferdam:

 

Pier Location

Side

Progress

P70

L

Excavation completed;

Concrete plug was casted on 18-Nov-14

R

Excavation, concrete plug and blinding layering completed;

Trimming of pile head concrete in progress

P71

L

Concreting works of pile cap completed on 6-Oct-14

R

Trimming of pile head concrete completed;

Cleaning works before formwork and steel fixing works in progress

P72

L

Excavation works in progress

R

Concrete plug completed;

Dewatering for Installation of 3rd layer of waling in progress

P73

L

Installation of formwork and steel fixing for pile cap is in progress;

R

Trimming of pile head concrete is in progress;

P74

L

Excavation works in progress

R

Excavation works in progress

P76

L

Installation of sheet pile completed;

Removal of temporary working platform in progress;

R

Installation of sheet pile completed;

Installation of shear pin to be started

P77

L

Installation of 1st waling & strut in progress

R

Installation of sheet pile completed.

Removal of temporary working platform in progress;

P78

L

Excavation works is in progress

R

Excavation works is in progress

 

In-situ Column Construction

(a)    1st lift works is in progress at P34, P35, P36, P60, P65 & P66.

(b)   1st lift concrete was poured at P35, P36, P60 & P65.

(c)    2nd lift works is in progress :  N/A.

(d)   2nd lift concreting was poured: N/A.

(e)    Pier head works is in progress at: P45, P48-R, P49, P52, P60, P65 & P66.

(f)    Pier head concreting in progress at P45, P48-R & P52.

 

Precast Column Erection

(g)   P39 – Base unit (1 of 3) installed.

(h)   P40 – Base unit (1 of 3) installed.

(i)     P41 – All units installed.

(j)     P43 – All units installed.

(k)   P44 – All units installed and prestressed tendon installation completed.

 

In-situ Double Blade Column Construction

(l)     1st lift works is in progress at P19.

(m) 2nd lift works is in progress at P20.

(n)   1st lift works is in progress at P71.

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

Segment Unloading Frame (SUF)

Fully operational

Lifting Frames 1 (LF1)

Assembly of the first set of LF1 is on-going at WA4 but is hampered by lack of available area;

 

Steelwork for the 4th set of Lifting Frames is under fabrication with some deliveries commenced;

Lifting Frames 2 (LF2)

LF2 at P109-P110R has been removed

 

Launching Gantry 1 (LG1)

LG1 assembly continues at Portion C with all components on site;

 

Lower Cross Beam (LCB)’s and elements 3 – 14 of the main trusses erected

Launching Gantry 2 (LG2)

Loading out of barges with LG2 components at River Trade Terminal (RTT) has commenced with assembly imminent at P47/P46

 

-        A total of 22 segments have been erected to date with the P46 Segments on Pier (SOP) segments erected during the month.

Precast Segment

(a)      Progress for mould assembly:

Type of Segment

Number of Mould

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

4

2 CPA complete,  1 * CPB complete

DT

1

Completed

E/EV

2

Under fabrication

(b)  210 segments were cast in this reporting period.

(c) Cumulative total 1386 segments cast.

(d)  76 segments have been delivered to site (28 in this reporting period).

(e) Piling works were completed for the precast yard extension for both additional moulds and segment storage; Storage plinths are well underway.

(f) Transportation of segments to an off-yard storage yard at nearby area in Zhongshan continues.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

6

56

CP2

Completed

12

CP3

2

2

CP4

Completed

8

CP5

2

4

 

Ground Investigations

-       All ground investigation / predrilling holes were completed. No drill rig is on site for this purpose. The Contractor is working to complete the reporting.

-       All Founding Level Proposals have been issued. The Contractor is working to close out comments and review as piling works proceeding on site.


Status of Environmental Licences, Notification and Permits

 

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Contract is presented in Table 2.2.

Table 2.2        Status of Environmental Licences, Notification and Permits

 

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-352/2009/C

05/09/2013

N/A

Valid

Consruction Noise Permit (CNP)

P101-P113: GW-RS0485-14

21/05/2014 (19:00)

20/11/2014 (06:30)

Expired

WA4: GW-RW0496-14 

10/07/2014 (19:00)

01/01/2015 (23:00)

Valid

WA7: GW-RW0509-14

14/07/2014 (19:00)

13/01/2015 (07:00)

Valid

P69 – P74: GW-RW0785-14

30/07/2014 (00:00)

29/11/2014 (07:00)

Expired

P81 – P114: GW-RW0812-14

05/08/2014 (19:00)

04/11/2014 (23:00)

Expired

Portion A: GW-RW0838-14

23/08/2014 (19:00)

22/02/2015 (23:00)

Valid

P0 – P68: GW-RS0855-14

27/08/2014 (19:00)

26/11/2014 (24:00)

Cancelled on 23 October 2014

P101 – P113: GW-RS0903-14

05/09/2014 (19:00)

04/12/2014 (05:30)

Valid

P75 – P80: GW-RS0924-14

10/09/2014 (19:00)

09/12/2014 (24:00)

Cancelled on 1 November 2014

P81 – P82: GW-RS1064-14

11/10/2014 (00:00)

10/04/2015 (24:00)

Valid

P110 – P114: GW-RS1126-14

16/10/2014 (19:00)

30/11/2014 (07:00)

Valid

P0 – P68: GW-RS1163-14

23/10/2014 (19:00)

22/01/2015 (24:00)

Valid

P75 – P80: GW-RS1179-14       

01/11/2014(19:00)

31/01/2015(24:00)

Valid

P81 – P114: GW-RS1250-14

06/11/2014(19:00)

05/02/2015(23:00)

Valid

P101 – P113: GW-RS1297-14

21/11/2014(19:00)

31/03/2015 (06:30)

Valid

P69 – P74: GW-RS1340-14

30/11/2014 (00:00)

31/03/2015(24:00)

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

345773

04/06/2012

N/A

Receipt acknowledged by EPD

Billing Account for Construction Waste Disposal

A/C# 7015341

(Construction Site)

11/06/2012

N/A

Valid

A/C# 7016948      

(Vessel Disposal)

11/08/2014

30/11/2014

Valid

A/C# 7016948      

(Vessel Disposal)

18/11/2014

28/02/2015

Valid

Registration of Chemical Waste Producer

WPN 5213-951-D2499-01

18/07/2012

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

WA6A(DCVJV site office): WT00014053-2012

12/09/2012

30/09/2017

Valid

WA6B  (SOR site office): WT00014447-2012

30/10/2012

31/10/2017

Valid

WA3: WT00015118-2013

30/01/2013

31/01/2018

Valid

Portion C: WT00015356-2013

22/02/2013

28/02/2018

Valid

Portion A: WT00016076-2013

21/05/2013

31/05/2018

Valid

WA4B: WT00014750-2012

12/08/2013

31/08/2018

Valid

WA7: WT00015722-2013

16/01/2013

31/01/2019

Valid

P0 – P80: WT00018203-2014

30/01/2013

31/01/2019

Valid

P114: WT00018631-2014

31/03/2014

31/03/2019

Valid

Marine Dumping Permit

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1-Open Sea Disposal) marine sediment

EP/MD/15-078

06/08/2014

31/01/2015

Valid

Cross-border dumping of dredged sediment of Category L and Category Mp at Erchau Island in China

EP/MD/15-127

10/10/2014

09/11/2014

Expired

Dumping of Phase 1, 2a, 2b, 2c and 2d (Type 1D and Type 2) marine sediment at the South of The Brothers

EP/MD/15-141

01/11/2014

30/11/2014

Valid

Cross-border dumping of dredged sediment of Category L and Category Mp at Erchau Island in China

EP/MD/15-143

10/11/2014

09/12/2014

Valid