2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A
and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013
respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued
on 5 September 2013.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and maintenance
management system (SHM&MMS), supervisory control and data acquisition
(SCADA) system, as well as operation and maintenance provisions of viaducts,
provisioning of facilities for installation of traffic control and surveillance
system (TCSS), provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning
works of affected existing facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P82 to P83 and 4 piles were
concreted in this reporting period.
(b) Total 139 pours
for column were completed with 17 pours
in this reporting period; 51 columns
were completed to top level (25
gridlines - P90 to P114).
(c) P84L water plugging and rebar
fixing are in progress, P84R excavation is in progress.
(d) Pre-bored for sheet
pile for cofferdam construction at P83R was completed.
(e) Pre-bored for sheet pile for
cofferdam construction at P81R commenced.
(f) Sewage diversion at P83 is in
progress.
(g) P83L piling work commenced.
(h) Portal P107 and P106 were
concreted on 17 and 21 November 2014 respectively. Dismantling of side formwork
is in progress.
(i) Portal P104 dismantling of steel
bracket system was completed.
(j) Portal P108 dismantling of falsework and steel bracket system is in progress.
(k) Portal P114 dismantling of
formwork was completed, temporary supporting jacks and nailing to be installed
before falsework removal.
(l) Portal P102 steel fixing is in
progress and will be concreted on 29 November 2014.
(m) Portal P101 steel fixing is in
progress.
(n) Portal P97 formwork erection was
completed and steel fixing will be commenced.
(o) Portal P98 erection of steel
bracket system is in progress.
(p) Portal P100 erection of formwork
is in progress.
(q) Portal P99 erection of falsework and steel beam supports are in progress.
(r) Portal P96 portal foundation work
is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction
of the temporary platform for piling works at P68 was suspended since 10 June
2014.
(b) Piling works at P69 was suspended on 12 July 2014 (9 out of 12 piles already
completed).
(c) Remobilization for P75’s works started on 25 September 2014. Excavation
by backhoe on flat top barge is on going.
(d) Piling
jackets were installed at P8.
(e) Piling
jackets were dismantled at P23 and D20.
(f) Pile
excavations and casing installation are in progress at P5, P9, P10 and P23 with
13 nos. piles concreted in the reporting period.
(g) Inter-face
coring tests were carried out at P23, P24, P25, P26 and P79.
(h) Full depth coring test was carried at P79.
(i) Sonic tests were carried out at P22, P24, P25, P26 and P79.
(j) Grouting works were carried out
at P53 and P79.
Kelly Method:
(k) Re-installation of platform was carried out at P2.
(l) Installation of permanent casing was carried out at P2R1a.
(m) Piling
platform removal and temporary pile extraction were carried out at P16, P31
& P32.
(n) Pile excavation
by Kelly method is in progress at P1, & P7 and 9 piles concreted in the
reporting period.
(o) All end-bearing piles by Kelly Method have been completed.
(p) Inter-face core
tests were carried out at P12 & P21.
(q) Full depth coring was carried out at P12-R3
& P30-R1.
(r) Sonic tests were carried out at P2, P3, P12,
P19-L & P21.
(s) Toe grouting works were carried
out at P2 & P3.
Disposal from
Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal Location |
No of Trip |
Type of Materials |
TM38 |
3 |
Inert Materials |
TMCLK |
2 |
Inert Materials |
HK Open Sea Mud Pits |
1 |
Type II Materials |
Cross Boundary Disposal |
5 |
Marine Mud |
Pilecap Construction:
(a) 10 precast cap shells were installed at P27, P28, P29, P63 & P67.
(b) Stage 1 concreting was completed
at P18, P29, P62, P63 & P67.
(c) Stage 1
works is in progress at P18, P29, P62, P63, P67 &
P68.
(d) Stage 2 concreting was completed
at P18L, P33, P34, P35, P61, P62 & P64.
(e) Stage 2
works is in progress at P18L&R, P29, P33, P34, P35, P61, P62, P63 & P64.
(f) Kingpost installation and associated steel welding works for precast
shell installation are in progress at P17, P27, P28, P30, P32
& P59.
(g) Concrete trimming and advanced
trimming (inside casing) works were carried out at P14, P16, P17, P27, P28,
P29, P30, P32, P53, P58, P59, P63, & P67.
Pier Location |
Side |
Progress |
P70 |
L |
Excavation completed; Concrete plug was casted on
18-Nov-14 |
R |
Excavation, concrete plug and
blinding layering completed; Trimming of pile head concrete
in progress |
|
P71 |
L |
Concreting works of pile cap
completed on 6-Oct-14 |
R |
Trimming of pile head concrete
completed; Cleaning works before formwork
and steel fixing works in progress |
|
P72 |
L |
Excavation works in progress |
R |
Concrete plug completed; Dewatering for Installation of
3rd layer of waling in progress |
|
P73 |
L |
Installation of formwork and
steel fixing for pile cap is in progress; |
R |
Trimming of pile head concrete
is in progress; |
|
P74 |
L |
Excavation works in progress |
R |
Excavation works in progress |
|
P76 |
L |
Installation of sheet pile
completed; Removal of temporary working
platform in progress; |
R |
Installation of sheet pile
completed; Installation of shear pin to
be started |
|
P77 |
L |
Installation of 1st waling
& strut in progress |
R |
Installation of sheet pile
completed. Removal of temporary working
platform in progress; |
|
P78 |
L |
Excavation works is in
progress |
R |
Excavation works is in
progress |
In-situ Column
Construction
(a) 1st lift works is in progress at P34, P35, P36, P60, P65 & P66.
(b) 1st lift concrete was poured at P35, P36, P60
& P65.
(c) 2nd lift works is in progress : N/A.
(d) 2nd lift concreting was poured: N/A.
(e) Pier head works is in progress at: P45, P48-R, P49, P52, P60, P65 & P66.
(f) Pier head concreting in progress at P45, P48-R & P52.
Precast Column
Erection
(g) P39 – Base unit (1 of 3) installed.
(h) P40 – Base unit (1 of 3) installed.
(i) P41 – All units installed.
(j) P43 – All units installed.
(k) P44 – All units installed and prestressed
tendon installation completed.
In-situ Double Blade
Column Construction
(l) 1st lift works is in progress at P19.
(m) 2nd lift works is in progress at P20.
(n) 1st lift works is in progress at P71.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Segment Unloading Frame
(SUF) |
Fully operational |
Lifting Frames 1 (LF1) |
Assembly of the first set of LF1 is on-going at WA4
but is hampered by lack of available area; Steelwork for the 4th set of Lifting
Frames is under fabrication with some deliveries commenced; |
Lifting Frames 2 (LF2) |
LF2 at P109-P110R has been removed |
Launching Gantry 1 (LG1) |
LG1 assembly continues at Portion C with all
components on site; Lower Cross Beam (LCB)’s and elements 3 – 14 of the
main trusses erected |
Launching Gantry 2 (LG2) |
Loading out of barges with LG2 components at River
Trade Terminal (RTT) has commenced with assembly imminent at P47/P46 |
- A total of 22 segments have been erected to
date with the P46 Segments on Pier (SOP) segments erected during the month.
Precast Segment
(a) Progress
for mould assembly:
Type of Segment |
Number of Mould |
Status |
A |
10 |
Completed (including 2
nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH1 |
2 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
2 |
Completed |
CP (long span SOP) |
4 |
2 CPA complete, 1 * CPB complete |
DT |
1 |
Completed |
E/EV |
2 |
Under fabrication |
(b) 210 segments were cast in this reporting
period.
(c) Cumulative
total 1386 segments cast.
(d) 76 segments have been delivered to site (28
in this reporting period).
(e) Piling works were completed for the precast
yard extension for both additional moulds and segment storage; Storage plinths
are well underway.
(f) Transportation of segments to an off-yard storage
yard at nearby area in Zhongshan continues.
Precast Concrete
Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of
Precast Shell Cast in this reporting period |
Cumulative No.
of Precast Shell Completed (up to 28th of each month) |
CP1 |
6 |
56 |
CP2 |
Completed |
12 |
CP3 |
2 |
2 |
CP4 |
Completed |
8 |
CP5 |
2 |
4 |
Ground Investigations
- All ground investigation /
predrilling holes were completed. No drill rig is on site for this purpose. The
Contractor is working to complete the reporting.
- All Founding
Level Proposals have been issued. The Contractor is working to close out
comments and review as piling works proceeding on site.
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/C |
05/09/2013 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
P101-P113: GW-RS0485-14 |
21/05/2014 (19:00) |
20/11/2014 (06:30) |
Expired |
WA4:
GW-RW0496-14 |
10/07/2014 (19:00) |
01/01/2015 (23:00) |
Valid |
WA7: GW-RW0509-14 |
14/07/2014 (19:00) |
13/01/2015 (07:00) |
Valid |
P69 – P74: GW-RW0785-14 |
30/07/2014 (00:00) |
29/11/2014 (07:00) |
Expired |
P81 – P114: GW-RW0812-14 |
05/08/2014 (19:00) |
04/11/2014 (23:00) |
Expired |
Portion A: GW-RW0838-14 |
23/08/2014 (19:00) |
22/02/2015 (23:00) |
Valid |
P0 – P68: GW-RS0855-14 |
27/08/2014 (19:00) |
26/11/2014 (24:00) |
Cancelled on 23 October 2014 |
P101 – P113: GW-RS0903-14 |
05/09/2014 (19:00) |
04/12/2014 (05:30) |
Valid |
P75 – P80: GW-RS0924-14 |
10/09/2014 (19:00) |
09/12/2014 (24:00) |
Cancelled on 1 November 2014 |
P81 – P82: GW-RS1064-14 |
11/10/2014 (00:00) |
10/04/2015 (24:00) |
Valid |
P110 – P114: GW-RS1126-14 |
16/10/2014 (19:00) |
30/11/2014 (07:00) |
Valid |
P0 – P68: GW-RS1163-14 |
23/10/2014 (19:00) |
22/01/2015 (24:00) |
Valid |
P75 – P80: GW-RS1179-14 |
01/11/2014(19:00) |
31/01/2015(24:00) |
Valid |
P81 – P114: GW-RS1250-14 |
06/11/2014(19:00) |
05/02/2015(23:00) |
Valid |
P101 – P113: GW-RS1297-14 |
21/11/2014(19:00) |
31/03/2015 (06:30) |
Valid |
P69 – P74: GW-RS1340-14 |
30/11/2014 (00:00) |
31/03/2015(24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
N/A |
Receipt acknowledged by EPD |
|
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
A/C# 7016948 (Vessel Disposal) |
11/08/2014 |
30/11/2014 |
Valid |
A/C# 7016948 (Vessel Disposal) |
18/11/2014 |
28/02/2015 |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A(DCVJV
site office): WT00014053-2012 |
12/09/2012 |
30/09/2017 |
Valid |
WA6B (SOR site office):
WT00014447-2012 |
30/10/2012 |
31/10/2017 |
Valid |
WA3:
WT00015118-2013 |
30/01/2013 |
31/01/2018 |
Valid |
Portion C:
WT00015356-2013 |
22/02/2013 |
28/02/2018 |
Valid |
Portion A:
WT00016076-2013 |
21/05/2013 |
31/05/2018 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
WA7:
WT00015722-2013 |
16/01/2013 |
31/01/2019 |
Valid |
P0 – P80: WT00018203-2014 |
30/01/2013 |
31/01/2019 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
Marine Dumping Permit |
|||
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1-Open Sea Disposal) marine sediment EP/MD/15-078 |
06/08/2014 |
31/01/2015 |
Valid |
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-127 |
10/10/2014 |
09/11/2014 |
Expired |
Dumping of Phase 1, 2a, 2b, 2c and 2d
(Type 1D and Type 2) marine sediment at the South of The Brothers EP/MD/15-141 |
01/11/2014 |
30/11/2014 |
Valid |
Cross-border
dumping of dredged sediment of Category L and Category Mp
at Erchau Island in China EP/MD/15-143 |
10/11/2014 |
09/12/2014 |
Valid |