7               ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 4th, 11th, 18th and 28th November 2014 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 28th November 2014. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 7th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 30th September 2014 and next inspection will be conducted in December 2014.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

04/11/2014

Muddy water was observed directly discharges into the sea at P84. The Contractor was reminded to provide sedimentation tank to treat the muddy water before discharging out.

Rectification/improvement was observed during the follow-up audit session on 3 December 2014.

04/11/2014

Muddy water was also observed directly discharges into the public gullies at P81 – P82. The Contractor was reminded to provide proper mitigation measures to rectify deficiency as soon as possible.

Rectification/improvement was observed during the follow-up audit session on 11 November 2014.

04/11/2014

Concrete wastewater was observed pumping out from the cofferdam into the sea at P73. The Contractor was reminded to ensure all discharge from site comply with WPCO.

Rectification/improvement was observed during the follow-up audit session on 11 November 2014.

11/11/2014

Muddy water was pumped to the excavation pit before discharging to the sea at P84. The Contractor was reminded to check this discharging procedure whether comply with WPCO.

Rectification/improvement was observed during the follow-up audit session on 3 December 2014.

18/11/2014

Concrete debris was observed at the deck of roro barges. The Contractor was reminded to clear it as soon as possible.

Rectification/improvement was observed during the follow-up audit session on 28 November 2014.

18/11/2014

Clear the accumulated concrete waste at the waste skip properly (Kam Shun 338).

Rectification/improvement was observed during the follow-up audit session on 28 November 2014.

28/11/2014

To avoid the gap at the silt curtain at P71.

Rectification/improvement was observed during the follow-up audit session on 3 December 2014.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

18/11/2014

Regular check the sprinkler system for dust suppression at floating concrete plant to ensure it can function properly.

Rectification/improvement was observed during the follow-up audit session on 28 November 2014.

Noise

04/11/2014

Provide noise emission label for the hand held breaker at P73.

Rectification/improvement was observed during the follow-up audit session on 11 November 2014.

Waste / Chemical Management

11/11/2014

Properly clear construction materials / wastes at near the trees at P89, P94 and P102.

Rectification/improvement was observed during the follow-up audit session on 18 November 2014.

28/11/2014

Properly clear the general refuse at the edge of barge at P71.

Rectification/improvement was observed during the follow-up audit session on 3 December 2014.

28/11/2014

To plug the outlet of drip tray at P71.

Rectification/improvement was observed during the follow-up audit session on 3 December 2014.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

N/A(2)

N/A(2)

N/A(2)

Remark: N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

N/A(2) No archaeological site inspection was conducted in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 6,785m3 inert C&D materials were generated during the reporting month. 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.